District 4 signs design-build completed project

SP 8824-65, Letting 07/20/07

Status

Project completed in 2008.

Project purpose, benefits

  • To relocate, replace and/or add signs along five highways in MnDOT's District 4 Detroit Lakes/Morris region
  • Project included an engineering assessment to determine which signs needed to be relocated, replaced, and/or added in order to meet standards
  • Construction activities included relocating, replacing and/or adding signs in accordance with the engineering assessment
  • Contractors were required to provide a database containing final sign installation information to MnDOT

Approximate timetable

Approximate Timetable
Phase I – Request for Qualifications
Request for Letters of Interest (LOI) March 26, 2007
Issue Request for Qualifications (RFQ) April 9, 2007
Statement of Qualifications (SOQ) due April 27, 2007
Evaluation of SOQ’s May 9, 2007
Notify Short Listed Submitters May 9, 2007
Phase II – Request for Proposals
Issue RFP May 25, 2007
Project Information Meeting with Proposers June 4, 2007
Technical and Price Proposals due July 10, 2007
Evaluation of Technical Proposals July 11– July 20, 2007
Price Proposal Opening July 20, 2007
First Notice to Proceed August 13, 2007
Substantial Completion June 15 , 2008