Final year of Highway 12 Litchfield to Cokato project starts June 9
WILLMAR, Minn. – The final year of construction for the two-year Highway 12 Litchfield to Cokato resurfacing and concrete repair project gets underway June 9, according to the Minnesota Department of Transportation.
Traffic impacts
A detour will be in place from June 9 until the project’s completion, scheduled for Aug. 15, 2025 (see map below).
- Highway 12 will be closed to through traffic from Dassel to Cokato.
- Through traffic will be routed to Highway 15 and County Roads 21 and 3.
- Highway 12 will be accessible to local homes and businesses. To provide access, only one lane will be worked on at a time, starting from west to east.
- Construction dates are subject to change depending on weather and other unforeseeable circumstances.
2024 project summary: Litchfield to Dassel – COMPLETED
- Highway 12 was resurfaced from Holcombe Avenue in Litchfield to east of Meeker County Road 14 in Darwin.
- Sidewalks and pedestrian ramps were upgraded to improve accessibility in Litchfield and Darwin.
- New sidewalk was created from Davis Avenue to Hubbard Avenue in Litchfield.
- A culvert was replaced at the county ditch 1.5 miles east of the Highway 12 and Meeker County Road 34 intersection in Litchfield.
- A pedestrian push button station was installed at Davis Street in Litchfield.
- The concrete was repaired, and asphalt shoulders were replaced on Highway 12 from east of Meeker County Road 14 in Darwin through the Highway 15 intersection in Dassel.
- The Darwin Rest Stop was resurfaced, and improvements made to sidewalks.
2025 project summary: Dassel to Cokato
- The concrete will be repaired, and asphalt shoulders will be replaced from east of Highway 15 in Dassel to the end of the concrete section in Cokato.
- Sidewalks and pedestrian ramps in Dassel will be upgraded to improve accessibility.
- Ramps along the trail from Dassel to Cokato will be upgraded to improve accessibility.
Project benefits and cost
Benefits of the project include a smoother road surface, improved drainage, and improved accessibility and enhanced safety for pedestrians. Duininck, Inc., is the contractor, and the project cost is approximately $11.3 million.
Stay connected
- Learn more about the Highway 12 project at mndot.gov/d8/projects/hwy12litchtocokato.
- Join the Southwest Minnesota Facebook group for news, events, and updates
- Follow us on Twitter @MnDOTsouthwest for news, events, and updates
- For real-time traffic and travel information in Minnesota, visit www.511mn.org or get the free smartphone app at Google Play or the App Store
###