Future work, impacts

Here's a six-month look ahead on tentative roadwork and traveler impacts on Hwy 55 between Annandale Blvd. and Brown Ave. in Annandale, Wright County.

Through traffic

Hwy 55 Annandale - through traffic detour map
Through traffic to detour map. Select PNG image to enlarge

Local traffic: Annandale is open

  • Access open and maintained at all times to those who live, work or visit those along the Hwy 55 work zone; however, expect changes and use of alternate accesses between Brown Ave. and Annandale Blvd:
    • Plan to encounter gravel or grooved surfaces, narrowed lanes, lane shifts, flaggers controlling traffic, heavy equipment entering and exiting work zone areas
    • Expect segments of hard closures at times as crews work on structures beneath the road; follow signs to next available access point
    • Poplar Ave. will remain open to/from Hwy 55 most of the time (except two weeks to realign the intersection)
  • Pedestrians: Sidewalk closures, follow signs, usually on alternate side of road

Schedule at a glance

Mid-April to mid-October 2025

Table figure: Provides project timeframe, location, work and expected impacts on Hwy 55.

Timeframe
Location
Work
Hwy 55 impacts

Mid-April to late April

Annandale Blvd. to Poplar Ave.

Prep-work: widen shoulders along south side of Hwy 55 for future traffic lanes, set up equipment, road devices, etc.

Minimal impacts, shoulder closures

May to October

Annandale Blvd. to Poplar Ave.

East to west: widen road along north side, pave, add center turn lane

Narrow lanes, two-way traffic with no shoulders

June to mid-October

Brown Ave. to Poplar Ave.

West to east: reconstruct road, sidewalks, replace signals, improve access

Road closed to through traffic. Detour: Wright Co. Rd. 3, County Rd. 39, Hwy 24 and Co. Rd. 6 (PNG)

Mid-April to mid-October

Annandale Blvd. to Brown Ave.

All

Hwy 55 access maintained to those who live, visit or work along Hwy 55

Information subject to change - weather, contractor schedules and material delays can occur.