Central Minnesota

2025 work

These roadwork projects on state highways will have traffic impacts, but will be led, constructed and communicated by the city, township or county. Check 511mn.org for current impacts on these projects.

2025 roadwork

Improve drainage at Hwy 371 and Design Rd. in Baxter

  • Construct: 2025
  • Impacts: Access detours at Design Rd. Lane or shoulder closures on Hwy 371.
  • Led by: City of Baxter

Construct roundabout

Project location
Hwy 371B and Willow St traffic plan map. Select map for larger image (PNG)

Update and improve access at the intersection with a new roundabout at Hwy 371B (S 6th St.) and Willow St. in Brainerd, Crow Wing Coutny (city led)

  • Construct: June-August 2025
  • Impacts: Intersection closed Hwy 371B between Joseph St. and Vine St.; Willow Street between Vine St. and 7th St.
    • Local detour for those who live, work or visit those in the neighborhood
    • Truck detour for through traffic, larger, longer vehicles, RV's and semi-trucks
  • Led by: City of Brainerd

 

Project location
Sherburne County project location on Hwy 10. Select map for larger image (PNG)

Improve access

Sherburne County to update access and improve safety along Hwy 10, east of St. Cloud, near Haven Town Hall, as follows:

  • Update access on Hwy 10 at Co. Rd. 65 (42nd St. SE) and Co. Rd. 7 (45th Ave. SE) with a J-turn design
  • Reconfigure access on Hwy 10 at Co. Rd. 61 (47th St. SE) with a right in/out design; includes an acceleration lane
  • Construct: 2025
  • Impacts: Lane or shoulder closures on Hwy 10; local access changes, follow road signs
  • Estimated cost: $3 million
  • Led by: Sherburne County

Construct interchange

Construct new interchange at Hwy 169 and Co. Rd. 4 (Freemont Ave.) in Zimmerman

Improve access

Construct right turn-lane on Hwy 25 to 14th St NE in Buffalo

  • Construct: 2025
  • Impacts: Lane or shoulder closure on Hwy 25; local access changes to 14th St. NE
  • Estimated cost: $200,000
  • Led by: City of Buffalo

Improve access at interchange

Construct roundabouts at the I-94 interchange on/off ramps and Co. Rd. 137