Hwy 13 at Nicollet Avenue Interchange

SP 1901-207 Letting August 2026

Purpose

To replace the traffic signal at Hwy 13 and Nicollet Ave in the City of Burnsville with a grade-separated interchange.

Procurement schedule

  • RFQ: Winter 2025-6
  • RFP: Late spring 2026
  • Letting: August 2026
  • Construction start: 2027

Information

Oversight

  • Design and construction post-letting oversight will utilize consultant contracts