Hwy 13 at Nicollet Avenue Interchange
SP 1901-207 Letting August 2026
Purpose
To replace the traffic signal at Hwy 13 and Nicollet Ave in the City of Burnsville with a grade-separated interchange.
Procurement schedule
- RFQ: Winter 2025-6
- RFP: Late spring 2026
- Letting: August 2026
- Construction start: 2027
Information
Oversight
- Design and construction post-letting oversight will utilize consultant contracts