University Avenue and 4th Street at 35W
SP 2783-168 Letting First Quarter 2026
Purpose
To enhance safety for pedestrians and bicyclists, improve the corridor  infrastructure, and provide access to bus rapid transit along University Ave  and 4th Street in the vicinity of 35W. These corridors have a history of  pedestrian and bicyclist crashes at high volume intersections therefore  protected intersections, ADA improvements, and separated bike facilities will  be installed to improve safety. In addition, the pavement condition of the  corridor is categorized as poor, the bridges over I-35W do not meet vertical  clearance standards and are due for replacement, and numerous signal systems  are at the end of their life cycle therefore the roadway, sidewalks, and  bridges will be reconstructed in-addition to signal and drainage improvements.
	  
Procurement schedule
- Request for Letters of Interest: July 2025
- RFQ: Fall 2025
- RFP: Fourth Quarter 2025
- Letting: First Quarter 2026
- Construction start: 2026, although 2027 is the heavier year
Information
Oversight
- Design and construction post-letting oversight will utilize consultant contracts