This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.
Traffic impacts

Hwy 169 and Hwy 282 in Jordan project location map
All traffic impacts are tentative and weather dependent. Syndicate St. to/from Hwy 169 is permanently closed.
Current
Road closures
7 p.m. Sun, May 4 through late July
- Valley View Dr. is closed at Co. Rd. 9
9 p.m. Wed, April 30 through fall
- Creek Ln. to/from Hwy 169 is closed
Lane closures
Through Fri, Nov. 21
- Co. Rd. 9 is reduced to one lane in both directions between Ervin Industrial Dr. and Hwy 169
5 a.m. Tue, April 15 through late November
- Hwy 169 is reduced to one lane in both directions between Hwy 282 and Hwy 21
Access changes
5 a.m. Tue, July 1
- Triangle ln. is permanently limited to right in/right out access to/from Hwy 282
Upcoming
Information about upcoming traffic impacts will be posted as details become available.
Road closures
Late July through Fri, Nov. 21
- 190th St. is closed at Co. Rd. 9
About this project
We are partnering with the city of Jordan and Scott County on a project which will include a new Hwy 169 and Hwy 282/Co. Rd. 9 interchange, two bridges (over Hwy 169 and railroad tracks), two roundabouts, pedestrian tunnel, sidewalks, retaining walls, and noise walls.
Summary of work
- Construct new interchange at Hwy 169 and Hwy 282/Co. Rd. 9
- Build roundabout at the Co. Rd. 9 and Syndicate St. intersection
- Build roundabout at the Co. Rd. 9 and 190th St./Valley View Dr. intersection
- Build Co. Rd. 9 bridge over Union Pacific railroad tracks
- Widen and repair Hwy 169 bridge over Sand Creek
- Add traffic signal at NB Hwy 169 exit ramp and Hwy 282
- Build pedestrian tunnel under Hwy 169 and add new trail connections
- Construct Hwy 169 acceleration and deceleration lanes
- Build stormwater improvements
- Create retaining walls along various areas of the project
- Add noise walls on both sides of Hwy 169, north of Syndicate St. and Creek Lane
Project timeline
The following tentative traffic impacts are anticipated and subject to change:

Hwy 169 and Hwy 282 in Jordan project staging map
Stage 1: Spring to early summer 2025
- Work begins on Hwy 169 interchange
- Single-lane Hwy 169 traffic in each direction
Stage 2: Summer to fall 2025
- Single-lane Hwy 169 traffic in each direction
- Roundabout construction at Co. Rd. 9 and Valley View Dr.
- Co. Rd. 9 remains open
- Alternating detour for 190th St./Valley View Dr.
- Construct pedestrian underpass
Stage 3: 2026
- Work on Hwy 282/Co. Rd. 9 overpass
- Single-lane Hwy 169 traffic in each direction
- Occasional overnight closures of Hwy 169 for bridge work
- Temporary traffic light at Hwy 169 and Creek Ln.
- Truck traffic exiting and entering Hwy 169 at Co. Rd. 9 will instead be detoured to Delaware Ave./Co. Rd. 59
Stage 4: 2027
- Median and finishing work on Hwy 169
- Single-lane Hwy 169 traffic in each direction
- Remove temporary traffic light at Hwy 169 and Creek Ln.
- Hwy 282/Co. Rd. 9 overpass opens to traffic