2025 roadwork
About this project
MnDOT will resurface and improve Hwy 55 from Brown Ave. to east of Annandale Blvd. (1.4 miles) in Annandale, includes utilities and access. The project will require a detour mid-April to mid-October 2025.
Summary of work
Hwy 55
Brown Ave. to Poplar Ave. N
- Reconstruct the asphalt road surface
- Replace or update underground utilities, includes city water, sewer and storm water
- Update the signal system at Hwy 55 and Excelsior Ave.
- Realign to improve access at Hwy 55 and Oak Ave./Hwy 24/Harrison St.
- Install a flashing pedestrian crosswalk signal
- Realign to improve access at Hwy 55 and Poplar Ave. N
- Close the west end Service Rd. entrance, just east of Poplar Ave. N. and install a cul-de-sac
- Update or add pedestrian sidewalk along both sides of Hwy 55 between Brown Ave. and Cherry St.; continue on the north side to Poplar Ave. N and connect to Service Rd.
- Update street lighting
Poplar Ave. N to Annandale Blvd.
- Repave the asphalt road surface
- Widen the road along the north side shoulder to add a center left-turn lane from east of Poplar Ave. N to west of Annandale Blvd.
- Update storm/ditch drainage
- Install shoulder rumble strips