2022 Demonstration Project
In Sept/October 2022, in collaboration with the City of Moorhead and Metro COG, MnDOT installed a demonstration project on Main Avenue/Highway 10 between the Red River and Highway 75/Eighth Street. Main Avenue users encountered barrels, signs and additional striping in both directions between Fourth Street and Eighth Street to evaluate:
- Three-lane highway configuration
- Curb extensions, or bump outs, at intersection crossings for pedestrian visibility
- On-street parking spaces
- Signal modifications to match demonstration layout
Demonstration projects allow public agencies, community partners, and people walking, bicycling, taking transit, and driving to evaluate potential infrastructure improvements before potentially investing in permanent changes.
The demonstration project tested the benefits of a three-lane section at this location to help MnDOT evaluate if these changes could become a permanent solution as we begin preparing plans to reconstruct this portion of Main Avenue/Highway 10/75 in the future.
Demonstration components
For this demonstration project, Main Avenue was reconfigured to three lanes (one driving lane in each direction with with a center left turn lane), with curb extensions/bump outs at pedestrian crossings and on-street parking. The proposed layout was very similar to what travelers currently experience on the other side of the river in downtown Fargo.
Eastbound layout: Starts at Fourth Street, ends at Eighth Street
- Near Fourth Street, the southernmost driving lane transitioned into a right turn lane
- Curb extensions/bump outs continued at Fourth, Fifth, Sixth and Seventh Streets
- Parking spaces were delineated between the bump outs
- Dedicated right turn lane at Seventh and Eighth Streets
- Signal operations adjusted to match the layout
Westbound layout: Starts at Eighth Street, ends at Fourth Street
- Near Eighth Street, the northernmost driving lane was closed
- Curb extensions/bump outs continued at Sixth, Fifth and Fourth Streets
- Parking spaces were delineated between the bump outs
- Signal operations adjusted to match the layout