Hwy 59, 108 - Pelican Rapids Complete Streets Project

Pelican Rapids

Highway 59 reduced to one-lane of traffic. Obey the automated traffic signals.

Current traffic impacts

Project map for Stage 2B on Highway 59 in Pelican Rapids, shows work zone from Fifth Ave to 8th Ave, with traffic traveling on one side at a time through work area.
When construction starts up in 2025, work will begin on Stage 2B on Highway 59.
  • Stage 2B underway: Highway 59 reduced to one lane between Fifth Avenue NE and Eighth Avenue NW
    • Automated traffic signals setup on each side of work zone to direct traffic one lane at a time. Be prepared to stop.Your patience is important!
    • There will be a thru-traffic detour set up for truck traffic and those who are seeking an alternate route around construction
  • Downtown work: Bridge crews are completing work at the bridge over the Pelican River on Highway 59 downtown. Parking and sidewalk restrictions on the east side of the bridge.
  • In May, work will resume on Highway 108 east, too!

Construction schedule

Construction will be completed in phases, starting in April 2024 through Fall 2025. All work and schedules are weather dependent.

Upcoming stages and work:

  • Starting April 28 Bridge work downtown, parking/sidewalk restrictions
  • Starting May 2 Stage 2B: Hwy 59, Fifth Ave NE to Eighth Ave NW
  • Starting in mid-May Stage 4A & 4B: Hwy 108 east, 2 1/2 Street to 6th Street
  • View all project staging maps.To be updated for 2025 staging plans.

Stay informed

You can sign up for project email updates, or submit questions or comments at any time by either using the comment form on the project home page, or by contacting a MnDOT representative directly by email or phone.