A 1.2-mile stretch of Hwy 56 will be reconstructed in LeRoy to address deteriorating pavement conditions, improve drainage, enhance student crosswalk safety and make pedestrian improvements to meet current accessibility standards. At the same time, the City of LeRoy will replace aging city utilities underneath the road.
Construction for this project will take place in three stages in 2024. Learn more in the traffic impacts section below.
Construction started April 29, 2024. It anticipated to be completed in October 2024. MnDOT also plans to conduct additional landscaping work (tentatively in 2025), which will include adding new trees to boulevards.
The following is the planned work:
Reconfigure Mower Co. Rd. 12, Hwy 56 and Main St. E. intersection to improve safety by reducing vehicle speeds while maintaining efficient traffic flow
Construct a cul-de-sac west of Mower Co. Rd. 12
Create a buffer zone between traffic and parking from Mather St. to Everett St. for biking
Improve school crosswalk safety by constructing a bump out at Mower Co. Rd. 14 and creating a wider school parking zone
Replace aging storm water, sanitary sewer and water main utilities underneath Hwy 56
Extend water main past Ada St.
Replace and install new curb and gutter
Replace and install new sidewalks
Landscaping, such as adding trees to boulevards (likely in 2025)
Below are project plans and detour routes. The timeframes are weather dependent. Construction will take place in three stages to better align with the city’s sewer reconstruction efforts.
People will be able to reach their destination within the construction zone. However, which direction they take may depend upon the day’s work.
Residents and business owners with questions about access to properties can contact
Trevor Minnich, 507-272-3142.
Stage 1
Crews removed select trees along the corridor in early 2024.
Stage 2a
April 29 to early August 2024
Crews will work between Co. Rd. 56 to S Mather St. (green zone) and Everett St. and east of Ada St. (yellow zone). Traffic will be detoured along Co. Rd. 12, 53 and 11, as well as W County Rd. and 105th St.
Crews will start on the east end and then move to the west end during Stage 2a. The full detour will be in place during this stage. Residents will be able to access their properties in the work zone.
Tentatively: August to mid-October 2024
Once stages 2a and 2b are complete, crews will work between S Mather St. and Everett St (blue zone). Traffic will be detoured south of Co. Rd. 56 and N Mather St.