Minnesota Department of Transportation

511 Travel Info

Hwy 57 reconstruction

Kasson, from Veterans Memorial Highway/Dodge County Road 34 to 11th Street NE.

About this project

Highway 57 Reconstruction Map
Hwy 57 reconstruction project map
Highway 57 Reconstruction Map close up with details
Hwy 57 roundabouts project map

Summary of work

Construction occurred over two years, 2022-2023. The work was completed August 16, 2023, and the road re-opened to traffic. Work included the following.

  • Reconstruction of Hwy 57 in Kasson from Veterans Memorial Highway/Dodge Co. Rd. 34 to 11th St. NE.
  • Construction of roundabout at Hwy 57 and Veterans Memorial Highway/Dodge Co. Rd. 34.
  • Construction of mini roundabout at Hwy 57 and Main St.

Work was split into stages.

  • Stage 1A was completed in 2022 and included all reconstruction work from just north of 1st St. NE to south of 7th St. NE.
  • Stage 1B was completed in 2022, including reconstruction work from south of 7th St. NE to north of 11th St. NE.
  • Stage 2 was completed Aug. 16, 2023 and included all reconstruction work from south of Veterans Memorial Highway/Dodge Co. Rd. 34 to just north of 1st St. NE, including the roundabout at Co. Rd. 34 and the mini roundabout at Main St.

Resources

Hwy 57 and 16th St. roundabout

Another project occurred in Kasson from April through August 2023. This was a local partnership project and it was led by the City of Kasson. A roundabout was constructed at Hwy 57 and 16th St. More details and contact information can be found on the project website.

Traffic impacts

Project is complete - no current traffic impacts.