About this project
Summary of work
A resurfacing and bridge replacement project will occur on I-90 between Nodine and Dakota in Winona County. Construction is scheduled to begin May 4, 2026. Work is expected to be completed in November.
The following is the planned work on I-90:
- Repave 5 miles of westbound and 4.7 miles of eastbound I-90.
- Replace the westbound I-90 bridge over Winona Co. Rd. 101.
- Replace approach panels and bridge barrier guardrail connections on the westbound I-90 bridge over southbound Hwy 61.
- Improve safety by providing a slight banking of the right lane of northbound I-90 approaching the bridge over southbound Hwy 61.
- Install new guardrail on the eastbound and westbound lanes and improve drainage.
- Install a reinforcement and a synthetic liner to reduce sinkhole risks associated with Karst geology.
- Clean and reestablish rock catchment areas.
Traffic impacts
During construction, the following impacts will occur.
- I-90 lane closures have been in place since March 30 for construction preparation. The lane closures will continue for the resurfacing work and will remain in place through late fall.
- Winona County Road 101 will be closed and detoured during the bridge replacement, which begins mid-May. The county road detour is expected to be several months at a time as crews replace the bridge half at a time, while keeping one I-90 lane open.
- The County Road 101 detour route is: Winona County Road 12 west at Dakota to Dakota Valley Drive east.
