Summary of MnDOT work

map of Hwy 19/College Dr. project showing work zone areas
  • MnDOT is reconstructing Highway 19/College Drive from 700 ft west of Marlene St through the intersection of Bruce Street in the City of Marshall.
  • The City of Marshall is replacing sanitary sewer and water main utilities.
  • A single-lane roundabout will be constructed at the intersection of Highway 19/College Drive, Country Club Drive, and South 2nd Street.
  • An EV Charging Station will be installed in the Avera parking lot.
  • Sidewalk improvements will be made along the project area to improve accessibility.
  • Several traffic control changes throughout the route will be made to enhance safety.
  • A bike lane will be striped from Marlene St. to just west of Fairgrounds Rd.
  • Trees will be replanted in the fall of 2026(PDF). Tree selections can be viewed here(PDF), please note, these are subject to change.

Project update: May 22, 2026

Memorial Day weekend:

  • Crews will stop work at 5:00 p.m. (or earlier if weather changes) on Fri., May 22. Work will start again Tues., May 26, at 7:00 a.m. 

Work zone: Main Street to Liberty Park Bridge

  • Dirt work is finished from Lyon Street to Marshall Street.
  • Gravel base is placed from Lyon Street to Marshall Street. 
  • Utility crews have finished their work from Main Street to Marshall Street.
  • All required cleanup of older building materials is done. 
  • The concrete panels leading up to the Liberty Park Bridge were planned to be poured on Thu., May 21.
  • Crews are installing curb and gutter between Lyon Street and Marshall Street.
  • Sidewalk accessibility work is underway between Lyon Street and Marshall Street.
    • this work helps make sidewalks and crossings easier and safer for people using wheelchairs, walkers, strollers, or anyone with mobility or vision challenges.
  • Street-light electrical work underground is underway between Lyon Street and Main Street. 
  • Concrete paving of the road was scheduled for Fr., May 22 but will happen next week due to the rain in the forecast.

Work zone: Main Street/ East College Drive intersection (Hwy 19/Hwy 59/Hwy 68)

  • Detours for Hwy 59 and Hwy 68 started Mon., May 18. The Hwy 19 detour is in place for the duration of the project.
  • Pavement has been removed. 
  • The old traffic signal has been taken down. 
  • Old sewer pipes have been removed and news ones installed along Main Street.
  • Dirt work is finished.
  • Remaining cleanup of older materials should be completed on Thu., May 21.
  • Gravel base is planned to be finished by the end of the day, Thu., May 21.

Work zone: Bruce Street/ Highway 19 intersection 

  • Utility work continues.
  • Temporary water lines are set up for property owners who will be impacted.
  • New concrete sewer parts have arrived and are sitting near the intersection. 

Work zone: Legion Field Bridge to Main St. 

  • Finishing work is underway.

Work planned for next week
*all proposed work is weather permitting

Main Street to Liberty Park Bridge

  • Curb and gutter installation will continue.
  • Concrete paving will begin.
  • Sidewalk accessibility work will continue.
  • Streetlight electrical work will continue.

Main Street/ East College Drive intersection

  • Curb and gutter installation will start.
  • Concrete paving will start.
  • Sidewalk accessibility will start. 
  • Traffic signal electrical work underground will start.
  • Traffic signal foundation work will start.

Bruce Street/ Highway 19 intersection

  • The Bruce Street Intersection will close Tues., May 26.
  • Pavement removal is planned to be completed. 
  • Groundwater monitoring tools (piezometers) will be removed.
    • these tools measure water levels underground so crews can work safely.
  • The traffic signal will be removed.
  • City streetlights will be removed in the work area.
  • Watermain removal and installation will be begin.

Legion Field Bridge to Main Street on Highway 19 (year 1 project area)

  • Crews will finish remaining small items. 

Traffic access and impacts

  • The Bruce St. / East College Dr. intersection will be closed starting Tues., May 26.
  • Main St. to Liberty Park Bridge on Hwy 19 is closed.
    • thru traffic must use the detour on Lyon CR 7 and Hwy 23.
  • Main St./Hwy 19 intersection is closed.
    • Thru traffic should use CR 33 and Hwy 23
  • W. Redwood St. will be open for crossing at Hwy 19 is open.
  • Hwy 19 is open to local traffic from N. 3rd Street. to Bruce Street.
  • W. Lyon St., and W. Marshall St. are closed at Highway 19.
  • Alleys between W. Lyon St. and W. Redwood St., and between W. Redwood St. and W. Marshall St. are closed at Highway 19.
  • Businesses within the work zone remain open.
  • Addison Public Parking Lot is open
  • Please watch for pedestrians.

2025: Stages 1-4

Mapping and Detour for the 2025 construction season - stages 1 through 4

2026: Stages 5-7

Year 2 map and detour with stages 5 through 7