This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.
Traffic impacts
All traffic impacts are tentative and weather dependent. Access to residences and businesses will remain open.
Current
Road closures
6 a.m. Mon, June 17 through November
- Hwy 101 is closed to through traffic in both directions between Hwy 5 and Co. Rd. 62/Townline Rd.
- Hwy 101 will only be open to local traffic
- Southbound detour: Hwy 101 to WB Hwy 7 to SB Hwy 41 to EB Hwy 5 to Hwy 101 (PNG)
- Northbound detour: Hwy 101 to WB Hwy 5 to NB Powers Blvd. to EB Hwy 7 to Hwy 101 (PNG)
Upcoming
Information about upcoming traffic impacts will be posted as details become available.
About this project
Crews will resurface 2 miles of road, add trail connections, reconstruct trail, improve accessibility of ramps and signals, repair shoulders, and improve drainage.
Summary of work
- Resurface travel lanes
- Install ADA compliant curb ramps
- Add or upgrade pedestrian ramps and crossings
- Improve drainage
- Install accessible pedestrian signals
- Reconstruct trail on west side of road
- Connect trail on west side of road with Twilight Trail path
- Repair shoulders along several areas of the project
- Replace existing guardrail