This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.
Traffic impacts

Hwy 316 project location map.
All traffic impacts are tentative and weather dependent. Local access to all businesses and residences will be maintained throughout construction.
Upcoming
Information about upcoming traffic impacts will be added as details become available. Motorists can expect full road closures with detours during construction.
Road closures
6 a.m. Mon, April 28 through early June
- Hwy 316 is closed in both directions between 200th St. and the south junction of Hwy 61 in Welch Township
- Detour: Hwy 316 to Hwy 61 (PNG)
- Local access: Hwy 61 to Nicolai Ave. to 190th St. (PNG)
Early June through mid-July
- Hwy 316 is closed in both directions between Nicolai Ave.and 200th St.
- Detour: Hwy 316 to Hwy 61 (PNG)
- Local access: Hwy 316, 200th St. to Ravenna Trail to 10th St. east (PNG)
About this project
The purpose of this project is to repave the road for a smoother surface, improve safety by adding several turn lanes in Ravenna Township, and improving drainage on the north end of the project near Tuttle Dr.
Summary of work
- Repave Hwy 316 between south junction of Hwy 61 and Tuttle Dr.
- Add left turn lanes at the following locations:
- Oxley Ave.
- Bauer Circle
- Pine Ridge Rd