Traffic impacts
All traffic impacts are tentative and weather-dependent.
Current
Lane closures
5 a.m. Sun, Nov. 3 through mid-November
- I-94 is reduced to two lanes in both directions between Century Ave. and Woodbury Dr.
Ramp closures
Through Wed, Nov. 13
- The ramp from 10th St. N. to NB I-694 is closed
Upcoming
Information about upcoming traffic impacts will be posted as details become available.
Ramp closures
5 a.m. Thu, Nov. 7 through Wed, Nov. 13
- The ramp from WB I-94 to SB I-494 is closed
- The ramp from NB I-694 to WB I-94 is closed
About this project
A large pavement project on I-94 between Century Ave. and the St. Croix River will begin in July 2022. This project work is anticipated to take two and a half years to complete.
Summary of work
- Resurface pavement and ramps
- Construct new eastbound lane from I-494 to Woodbury Dr.
- Resurface frontage road (Hudson Rd.) in the project area
- Upgrade pedestrian/bicycle accessibility
- Repair drainage
- Replace signage
- Upgrade lighting
- Install median barrier