Hwy 59

South of Marshall/South of Garvin/Marshall

About this project

Summary of MnDOT work

Traffic impacts

  • A detour will be required to complete the concrete repair in each section (see maps below).
  • The segment south of Marshall is scheduled to go first and take about 5 weeks to complete.
  • The segment south of Garvin is scheduled to take about 7 weeks to complete.
  • Work in both segments may overlap.
  • Short-term, intermittent intersection closures will take place along Hwy 59 for ADA work and minor detours may be required.

Hwy 59 concrete repair work zone and detour south of Garvin

  • Hwy 59 travelers south of Garvin will be detoured on CR 48, CR 29, CR 5, Hwy 14

Hwy 59 detour and work zone south of Marshall

  • Hwy 59 travelers south of Marshall will be detoured on Hwy 23, CR 35, CR 6