CONCRETE PAVING PLANT MONITOR

Review the Contract and Plans:
  • Become familiar with applicable specifications based upon the size of the project and delivery method of concrete. 
  • Review incentives and disincentives available. 
  • Check Schedule of Materials Control (SMC) for testing rates and sample sizes.
  • Attend the pre-construction meeting if possible.
  • Attend the pre-paving meeting.
Preliminary Testing and Mix Design Requirements:
  • Verify the Contractor’s aggregate sources and make sure preliminary testing if required has been done well in advance of the project start date.
  • Make sure the Contractor submits mix designs to the Concrete Engineering Unit for review a minimum of 21 days prior to initial placement of mix design.
Complete a Concrete Paving Contact Report:
  • The Contractor fills out the Contact Report - Paving (CONC-403).
  • Perform an on-site inspection of the plant with the Contractor.
  • Review the Contractor’s concrete paving combination plant-lab office for compliance.
  • Verify whether the Contractor has an electronic means of communication (email).
  • Check that scales and water meter are calibrated and retain a copy of the calibration certificate.
  • Obtain pre-production coarse aggregate samples for quality testing including the -#200 test in accordance with the SMC. 
  • Verify cement, fly ash, other cementitious materials (if used) and admixtures are on the Approved/Qualified Products list.
  • Obtain cement, fly ash, other cementitious materials (if used) and admixture samples from the Contractor per the SMC.  Provide sampling containers and witness sampling when possible.
  • Include cementitious invoices when submitting samples to the laboratory for testing.
  • Fill out lab sample I.D. cards completely and enclose them with the samples.
  • Submit the signed Contact Report and certificate of compliance to the Concrete Engineering Unit for final review at: conc1off.dot@state.mn.us.
  • All material and equipment changes during the construction of the project must be updated on the Contact Report and sent to the Concrete Office.
Become familiar with concrete batching and mixing equipment and the duties of the Contractor. 
  • Obtain the Contractor’s organizational chart listing names, phone numbers and emails of individuals responsible for mix design, process control administration and inspection.
  • Ensure compliance with minimum and maximum mixing times.
  • Inspect batch trucks for compliance with specifications. Check for mortar tightness, proper operation of box vibrators, cleanliness, and legal load limits.
During Concrete Production:
  • Monitor stockpiling and unloading of delivered aggregates. The stockpiles should be built long and wide and not high and on a stable base that is properly drained.
  • Check the aggregate stockpiles for segregation and contamination throughout the day.
  • Observe the loader operator periodically during the day for proper stockpile management. Check for contamination (e.g. clay balls) from trucks unloading or from the loader digging too deep.
  • Check field hoppers for contamination.  If contaminated, have Contractor empty storage and weigh hoppers and re-charge.
  • Review mix designs and ensure the Contractor is using correct mix design weights.
  • Check multiple times daily that batch weights are adjusted in accordance with current moisture tests, the correct mix design weights are being used and the w/c ratio is not exceeding the specification requirements.
  • Ensure compliance with minimum and maximum mixing times.
Alkali Silica Reactivity (ASR) Sampling:
  • Obtain samples of cement, supplementary cementitious materials (fly ash or slag) and sand in accordance with the SMC. 
  • Fill out the Sample I.D. card completely and enclose with lab samples.  Identify ASR sample with “Project Specific ASR Testing” on ID card.
Water/Cementitious Ratio Testing:
  • Verify contractor performs start-up moisture tests prior to production.
  • Obtain aggregate samples for moisture testing in accordance with the SMC.
  • Take additional moistures whenever moisture appearance of delivered aggregate seems to vary or batch water deviates greatly from previous loads.
  • Use Concrete W/C Ratio Calculation Worksheet (CONC-409) to determine the moisture contents, water/cementitious ratio, microwave oven water/cementitious ratio, and water/cementitious ratio incentive/disincentives. The Contractor performs the unit weight and provides the results.
  • Provide the Contractor with aggregate moisture results and verify that the batch ticket weights are adjusted in accordance with the moisture test results.
  • Review water/cementitious ratio results for compliance with project specifications and verify with microwave oven testing.
Aggregate Gradation Testing:
  • Obtain aggregate samples for verification testing in accordance with the SMC.
  • If testing aggregate gradations in the field, use QA JMF Concrete Aggregate Workbook (CONC-411) for gradation testing, otherwise submit to the lab.
  • The Contractor uses the QC JMF Concrete Aggregate Workbook (CONC-410) for both (QC and verification companion) gradation testing, and for determining JMF moving average and well-graded incentives. 
  • Review Contractor’s verification companion test results for compliance and compare to the Agency verification test results (split samples).
  • Review the Contractor’s JMF Aggregate Summary Workbook.
  • If submitting gradation samples to the lab, fill out Aggregate Sample I.D. cards including the JMF number and the Contractor’s verification companion gradation results.  Identify “QA Gradation” on ID card.
  • Determine if Contractor is eligible for well-graded aggregate incentives using the QC JMF Concrete Aggregate Workbook
% Passing 75 mm (#200) Sieve:
  • Perform all percent passing the #200 (75 mm) sieve at the Contractor’s plant site.
  • Sample and test in accordance with the SMC.
  • Use QA JMF Concrete Aggregate Workbook to calculate the percent passing the #200 (75 mm) sieve in the field.
  • Review the Contractor’s percent passing the #200 (75 mm) sieve for the coarse aggregate results to determine compliance or if additional testing is required.
  • Compare to Agency results with Contractor results when testing split samples.
  • Record Agency test results in the Additional Remarks/Comments within the Contractor’s QC JMF Concrete Aggregate Workbook.
Aggregate Quality Sampling:
  • Determine when Aggregate Quality samples will be taken in accordance with the SMC.
  • Fill out Aggregate Sample I.D. cards completely and record the Contractor and Agency -#200 (75 mm) test results. 
  • Identify Quality samples with a “Q” including the specification reference (Spec 3126 for sand and 3137.2D3 for coarse aggregate) on ID card. 
  • Identify the Quality Companion samples with a “Q”.
Coarse Aggregate Quality Incentive/Disincentive Sampling:
  • Determine when random Coarse Aggregate Quality Incentive/Disincentive samples (Class B or Class C aggregates only) will be taken using the CA Quality Incentive/Disincentive Workbook (CONC-405) and in accordance with the SMC.
  • Fill out Aggregate Sample I.D. cards completely and enclose with lab samples.  Identify Incentive samples with “I/D” on ID card.
  • Enter the Class B absorption results or Class C carbonate results into the CA Quality Incentive/Disincentive Workbook to determine the incentive. Using Class A aggregate is an automatic incentive, so sampling and testing is not required to determine the incentive.

Concrete Ingredient Summary:

  • Collect a production summary in an electronic format from the Contractor of the daily total concrete produced and daily total ingredient quantities (aggregate, cementitious and water) including the percent overrun/underrun.
  • Collect final project total quantities for concrete produced and ingredients in an electronic format including the percent overrun/underrun.
Contractor Records and Charts:
  • Obtain the Contractor’s on-site QC records and charts daily or as directed by the Engineer.
  • Review the Contractor’s on-site QC records and charts daily for accuracy and completeness.
  • Obtain batch tickets daily or as directed by the Engineer.
Maintain a daily diary:
  • Use the Concrete Batch Plant Diary (CONC-407).
  • Includes hours of production, equipment, weather, test results conducted at the plant, air temperatures, concrete yardage totals, and problems or unique circumstances encountered.
Submit the following to the MnDOT Concrete Engineering Unit:
  • Contact Report
  • W/C Ratio Incentive Calculation Worksheets
  • Well-graded Aggregate Incentive Worksheets
  • Quality Incentive/Disincentive Worksheets

References:    MnDOT Specification 2301, 2461, 3126, 3137, Special Provisions, Schedule of Materials Control and MnDOT Concrete Manual.