Non-National Highway System pavement projects

MnDOT District 8

Scoring criteria for non-national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on the potential to transfer jurisdiction of the road to a city or county, and 5 points are based on the miles covered by the project.

Learn more about how MnDOT evaluates and selects pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated August 2024

Total Score Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
87 Hwy 67 Construct cul-de-sac on Hwy 67 at entrance to Upper Sioux Agency State Park and replace signs.  $           330,000   2026 NA
85 Hwy 4 Resurface Hwy 4 from Fairfax to Hector.  $     14,045,000  2027/2028  NA
85 Hwy 68 Resurface Hwy 68 from Porter to Minneota; upgrade sidewalks to meet ADA standards in Porter, Taunton and Minneota; replace box culverts and bridges along project area.  $     10,500,000  2032/2033  NA
83 Hwy 24 Medium overlay Highway 12 (Litchfield) to Highway 15  $       8,800,000  Not Selected  This section has not been selected because it is a thin whitetopping test section (4-inch bonded concrete overlay in 2015). District will continue to monitor performance for research purposes.
81 Hwy 30 Resurface Hwy 30 from the Minnesota/South Dakota state line to 8th St in Pipestone.  $       1,500,000  2029 NA
81 US75 Cold in place recycling and medium overlay from Yellow Medicine County Road 3 (Canby) to 0.4 mi. S. of US 212  $       4,000,000  Not selected  Project was not selected due to fiscal constraints in 2030 (no new non-NHS projects were added in FY 2030)
81 US75 Medium overlay from Murray County Road 3 to US212  $       4,000,000  Not Selected  Not a district priority will continue to monitor pavement performance.
80 US75 Resurface Hwy 75 from Pipestone Creek to S Valley St in Lake Benton.  $       9,300,000  2031/2032  NA
78 Hwy 40 Resurface Hwy 40 from Milan to the west jct of Hwy 29.  $       3,300,000   2028 NA
78 Hwy 40 Resurface Hwy 40 from Milan to the west jct of Hwy 29.  $       7,400,000  2028/2029  NA
78 Hwy 30 Resurface Hwy 30 from Hwy 59 to the Murray/Cottonwood county line; replace bridge over Des Moines River.  $     17,150,000  2029/2030  NA
78 Hwy 22 Medium overlay from Hutchinson to Highway 7  $       3,300,000  Not Selected  Candidate for reconstruction in 2034
75 Hwy 19 Resurface Hwy 19 from Ivanhoe to CR 5.  $     22,300,000  2031/2032  NA
75 Hwy 22 Resurface from US 12 to Fredericks Ave. (Eden Valley)  $       9,300,000  2032/2033  NA
75 US59 Reclaim and overlay from 15th Ave. (Clarkfield) to W. JCT. US 212  $       3,800,000  Not selected  NA
74 Hwy 40 Resurface Hwy 40 from CR 4 to Willmar.  $     20,200,000  2028/2029  NA
74 Hwy 55 Medium overlay from Stearns/Meeker County Line to Eden Valley  $       3,000,000  Not Selected  Candidate for preventive maintenance in 2024
74 Hwy 68 Reclaim and overlay from N. JCT. US 71 to 0.2 mi. W. of Hwy 67 (Morgan)  $       3,900,000  Not selected  NA
74 Hwy 68 Reclaim and overlay from US71 to Hwy 57 in Morgan   $       3,900,000  Not Selected  NA
73 Hwy 30 Cold in place recycling and medium overlay from US 75 to Ravine St. (Lake Wilson)  $       4,300,000  Not selected  NA
72 US59 Resurface Hwy 59 from Hwy 14 to CR 6 in Marshall.  $       5,300,000  2028 NA
71 Hwy 67 Resurface Hwy 67 from Hwy 23 to the Upper Sioux Agency State Park.  $       3,200,000 2029 NA
71 US75 Resurface Hwy 75 from CR 34 to Hwy 30 in Pipestone.  $       4,700,000  2029 NA
71 US75 Resurface Hwy 75 from 0.12 miles south of CR 9 to CR 34 in Pipestone.  $     15,700,000  2026/2027  NA
71 Hwy 119 Medium mill and overlay from Highway 212 (Dawson) to Highway 40  $       2,700,000  Not Selected  Candidate for preventive maintenance in 2021
71 Hwy 4 Resurface Hwy 4 from Hwy 12 to Hwy 55.  $     18,900,000  Not Selected  NA
69 Hwy 24 Repair concrete on Hwy 24 from Hwy 12 to Hwy 15.  $       1,000,000  2024 NA
68 Hwy 7 Resurface Hwy 7 from Hwy 71 to Hwy 4.  $     13,000,000  2032 NA
67 Hwy 68 Resurface Hwy 68 from Wabasso to Hwy 71.  $       1,900,000 2031 NA
66 Hwy 30 Surface Hwy 30 from Hwy 75 in Pipestone to 60th Avenue in Lake Wilson. Upgrade sidewalks to meet ADA standards in Lake Wilson.  $       7,000,000  2030 NA
66 Hwy 40 Resurface Hwy 40 from Madison to Hwy 119.  $       5,700,000 2033 NA
65 US75 Resurface Hwy 75 from Hwy 67 to Hwy 212.  $       5,400,000 2033 NA
65 Hwy 4 Resurface Hwy 4 from US 212 to Cosmos.  $       9,300,000 2033 NA
65 Hwy 40 Resurface Hwy 40 from Hwy 119 to 0.1 miles west of 5th Street in Milan.  $       3,400,000  2026/2027  NA
65 Hwy 68 Reclaim and overlay from Redwood County Road 3 (Morgan) to Redwood/Brown County Line  $       3,100,000  Not Selected  Candidate for reconstruction in 2030
65 Hwy 7 Reclaim and overlay from Highway 4 (Cosmos) to Highway 22  $       7,400,000  Not Selected  Candidate for preventive maintenance in 2025
65 Hwy 7 Reclaim and overlay Highway 71 to Highway 4 (Cosmos)  $     13,000,000  Not Selected  NA
64 Hwy 4 Reclaim and overlay from Cosmos to  Meeker County Road 23  $       5,400,000  2023  This section has been prioritized due to maintenance patching losing effectiveness because of the level of deterioration. 
64 Hwy 271 Resurface Hwy 271 from CR 17 to W Ash Street in Hendricks.   $       3,200,000  2032 NA
64 Hwy 7 Resurface Hwy 7 from Milan to Montevideo.  $     12,100,000  2033/2034  NA
64 Hwy 267 Reclaim and overlay from Iona to Highway 30  $       4,000,000  Not Selected  NA
63 Hwy 68 Reclaim and overlay from South Dakota/Minnesota State Line to Canby  $       6,400,000  Not Selected  NA
62 Hwy 29 Medium mill and overlay from west junction of Highway 40 to east junction Highway 40 and additional locations on Highway 40  $       5,200,000  2024  Coordinated with projects on Highway 40
62 Hwy 29, Hwy 40 Resurface Hwy 29 from west jct of Hwy 40 to east jct of Hwy 40; resurface Hwy 40 from east jct of Hwy 29 to Chippewa CR 4.  $       7,700,000 2030 NA
62 Hwy 29 Reclaim and overlay from Airport Ave (Montevideo) to Hwy 40  $       3,700,000  Not selected  NA
62 Hwy 67 Reclaim and overlay from Redwood Falls to Fergus Ave. (Morgan)  $       8,600,000  Not Selected  NA
61 Hwy 9 Resurface Hwy 9 from Hwy 23 to Hwy 71.  $       2,700,000 2031 NA
61 Hwy 274 Reclaim and overlay from Wood Lake to Highway 23  $       6,500,000  Not Selected  NA
59 Hwy 67 Reclaim and overlay from Travers Ln. to Highway 19  $     12,300,000  Not Selected  NA
58 Hwy 67 Reclaim and overlay from US 75 to US59 near Clarkfield  $       7,200,000  Not Selected  NA
58 Hwy 68 Reclaim and overlay Highway 71 to Redwood County Road 3 (Morgan)  $       7,700,000  Not Selected  NA
56 Hwy 68 Resurface Hwy 68 from N Grant St in Minneota to CR 33 in Marshall, excluding the city of Ghent.  $           900,000 2024 NA
56 Hwy 68 Resurface Hwy 68 from N Grant St in Minneota to Hwy 59 in Marshall, excluding the city of Ghent.  $       1,800,000 2024 NA
56 Hwy 15 Resurface Hwy 15 from Winthrop to Hwy 212.  $     15,300,000  Not Selected  NA
55 Hwy 67 Resurface Hwy 67 from Hwy 75 to Hwy 59.  $     10,900,000  Not Selected  NA
54 US59 Reclaim and overlay from Yellow Medicine County Road 3 to Clarkfield  $       4,100,000  Not Selected  NA
50 Hwy 40 Resurface Hwy 40 from Minnesota/South Dakota border to Hwy 75.  $     13,500,000 2033 NA
43 Hwy 22 Resurface Hwy 22 from Glencoe to Hutchinson.  $       6,500,000 2033 NA
43 Hwy 9 Resurface Hwy 9 from Hwy 71 to Sunburg.  $       7,400,000 2034 NA
42 Hwy 267 Resurface Hwy 267 from Iona to Hwy 30.  $       1,800,000 2033 NA
42 Hwy 22 Thin overlay from .1 miles east of Hwy 7 to .2 miles west of Hwy 7  $           100,000  Not Selected  NA
40 Hwy 67 Thin mill and overlay Highway 23 (Granite Falls) to Travers Ln.   $       2,100,000  Not Selected  NA
39 Hwy 269 Thin overlay from South Dakota/Minnesota State Line to Highway 23 (Jasper)  $           600,000  Not Selected  NA
37 Hwy 9 Thin overlay from Kandiyohi County Road 7 (Sunberg) to Kandiyohi / Swift Co. Line  $           100,000  Not selected  NA
36 US75 Thin overlay from 4th St. N. (Pipestone) to Pipestone County Road 22  $           100,000  Not Selected  NA
32 Hwy 29 Thin overlay from Hwy 40 to Chippewa/Swift County Line  $           400,000  Not Selected  NA
31 Hwy 68 Thin overlay on from Highway 19 to Redwood County Road 32 (Milroy)  $           700,000  Not Selected  NA
29 Hwy 19 Thin overlay from Reference point 3 to Reference point 4  $           200,000  Not selected  NA
29 Hwy 19 Thin overlay from Reference pt 003 to Reference pt 004  $           200,000  Not Selected  NA
18 US59 Repair and smooth concrete pavement on Hwy 59 from 201st Street to Lyon CR 14 and from Lyon CR 6 to Hwy 23.  $       4,500,000  2024 NA
6 Hwy 22 Thin overlay from Sibley/McLeod County line to US212  $           200,000  Not Selected  NA
6 Hwy 330 Thin overlay from Highway 14 to University of Minnesota SW Research and Outreach Center  $           500,000  Not Selected  NA
5 Hwy 22 Thin overlay from Sibley/McLeod County Line to Highway 212  $           400,000  Not Selected  NA
3 Hwy 104 Thin mill and overlay Highway 9 to Kandiyohi/Pope County Line  $       1,400,000  Not Selected  NA

Previous years

    View more detailed scores (Excel).

    Total Score Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
    87 Hwy 67 Construct cul-de-sac on Hwy 67 at entrance to Upper Sioux Agency State Park and remove pavement between cul-de-sac and bridge #87011. $600,000 2025 NA
    85 Hwy 68 Resurface Hwy 68 from Canby to Minneota; upgrade sidewalks to meet ADA standards in Porter, Taunton and Minneota; replace box culverts and bridges along project area. $3,300,000 2033 NA
    85 Hwy 4 Resurface Hwy 4 from Fairfax to Hector. $11,225,000 2026/2027 NA
    85 Hwy 68 Resurface Hwy 68 from Porter to Minneota; upgrade sidewalks to meet ADA standards in Porter, Taunton and Minneota; replace box culverts and bridges along project area. $10,500,000 2032/2033 NA
    83 Hwy 24 Medium overlay Highway 12 (Litchfield) to Highway 15 $8,800,000 Not Selected This section has not been selected because it is a thin whitetopping test section (4-inch bonded concrete overlay in 2015). District will continue to monitor performance for research purposes.
    81 Hwy 30 Resurface Hwy 30 from the Minnesota/South Dakota state line to 8th St in Pipestone. $1,500,000 2029 NA
    81 US75 Cold in place recycling and medium overlay from Yellow Medicine County Road 3 (Canby) to 0.4 mi. S. of US 212 $4,000,000 Not selected Project was not selected due to fiscal constraints in 2030 (no new non-NHS projects were added in FY 2030)
    81 US75 Medium overlay from Murray County Road 3 to US212 $4,000,000 Not Selected Not a district priority will continue to monitor pavement performance.
    80 US75 Resurface Hwy 75 from Pipestone Creek to S Valley St in Lake Benton. $9,300,000 2030/2031 NA
    78 Hwy 40 Resurface Hwy 40 from Milan to the west jct of Hwy 29. $3,300,000 2026 NA
    78 Hwy 30 Resurface Hwy 30 from Hwy 59 to the Murray/Cottonwood county line; replace bridge over Des Moines River. $15,400,000 2028/2029 NA
    78 Hwy 22 Medium overlay from Hutchinson to Highway 7 $3,300,000 Not Selected Candidate for reconstruction in 2034
    75 Hwy 19 Resurface Hwy 19 from Ivanhoe to CR 5. $19,800,000 2031/2032 NA
    75 Hwy 22 Resurface Hwy 22 from Hwy 12 to Eden Valley. $16,300,000 2032/2033 NA
    75 US59 Reclaim and overlay from 15th Ave. (Clarkfield) to W. JCT. US 212 $3,800,000 Not selected NA
    74 Hwy 40 Reclaim and overlay Old Highway 277 to Kandiyohi County Road 5 (Willmar) $12,700,000 2026 NA
    74 Hwy 40 Resurface Hwy 40 from CR 4 to Willmar. $17,400,000 2030/2031 NA
    74 Hwy 68 Reclaim and overlay from N. JCT. US 71 to 0.2 mi. W. of Hwy 67 (Morgan) $3,900,000 Not selected NA
    74 Hwy 55 Medium overlay from Stearns/Meeker County Line to Eden Valley $3,000,000 Not Selected Candidate for preventive maintenance in 2024
    73 Hwy 19 Resurface (concrete) Hwy 19 from Redwood Falls to Morton; resurface (concrete) Hwy 71 from Hwy 19 to CR 15. $5,400,000 2031 NA
    73 Hwy 30 Cold in place recycling and medium overlay from US 75 to Ravine St. (Lake Wilson) $4,300,000 Not selected NA
    71 US75 Resurface Hwy 75 from CR 9 to CR 34 in Pipestone. $15,700,000 2026 NA
    71 Hwy 67 Resurface Hwy 67 from Hwy 23 to the Upper Sioux Agency State Park. $3,100,000 2029 NA
    71 US75 Resurface Hwy 75 from CR 9 to Hwy 30 in Pipestone. $5,550,000 2026/2027 NA
    71 Hwy 119 Medium mill and overlay from Highway 212 (Dawson) to Highway 40 $2,700,000 Not Selected NA
    69 Hwy 4 Reclaim and overlay from Hector to Cosmos $10,100,000 Not Selected NA
    67 Hwy 68 Resurface Hwy 68 from Wabasso to Hwy 71. $1,800,000 2030 NA
    67 Hwy 24 Repair concrete on Hwy 24 from Hwy 12 to Hwy 15. $1,500,000 Not Selected NA
    66 Hwy 30 Surface Hwy 30 from Hwy 75 in Pipestone to 60th Avenue in Lake Wilson. Upgrade sidewalks to meet ADA standards in Lake Wilson. $7,000,000 Not Selected NA
    66 Hwy 40 Resurface Hwy 40 from Madison to Hwy 119. $5,700,000 Not Selected NA
    65 US75 Resurface Hwy 75 from county line to Hwy 212. $5,400,000 2033 NA
    65 Hwy 40 Resurface Hwy 40 from Hwy 119 to 5th Street in Milan. $5,800,000 2025/2026 NA
    65 Hwy 7 Reclaim and overlay Highway 71 to Highway 4 (Cosmos) $13,000,000 Not Selected NA
    65 Hwy 4 Resurface Hwy 4 from US 212 to Cosmos. $9,300,000 Not Selected NA
    65 Hwy 7 Reclaim and overlay from Highway 4 (Cosmos) to Highway 22 $7,400,000 Not Selected Candidate for preventive maintenance in 2025
    65 Hwy 68 Reclaim and overlay from Redwood County Road 3 (Morgan) to Redwood/Brown County Line $3,100,000 Not Selected Candidate for reconstruction in 2030
    64 Hwy 7 Resurface Hwy 7 from Milan to Montevideo. $12,100,000 2031/2032 NA
    64 Hwy 267 Reclaim and overlay from Iona to Highway 30 $4,000,000 Not Selected NA
    64 Hwy 271 Resurface Hwy 271 from CR 17 to W Ash Street in Hendricks.  $3,200,000 Not Selected NA
    63 Hwy 68 Reclaim and overlay from South Dakota/Minnesota State Line to Canby $6,400,000 Not Selected NA
    62 Hwy 29, Hwy 40 Resurface Hwy 29 from west jct of Hwy 40 to east jct of Hwy 40; resurface Hwy 40 from east jct of Hwy 29 to Chippewa CR 4. $3,500,000 2029 NA
    62 Hwy 15 Resurface Hwy 15 from Hwy 12 in Dassel to Meeker/Stearns county line.
    $9,400,000 2024/2025 NA
    62 Hwy 67 Reclaim and overlay from Redwood Falls to Fergus Ave. (Morgan) $8,600,000 Not Selected NA
    62 Hwy 29 Medium mill and overlay from west junction of Highway 40 to east junction Highway 40 and additional locations on Highway 40 $5,200,000 Not Selected NA
    62 Hwy 29 Reclaim and overlay from Airport Ave (Montevideo) to Hwy 40 $3,700,000 Not selected NA
    62 Hwy 40 Construct turn lanes on Hwy 40 from Bridge 34032 to 0.3 miles W of 30th Street SW in Willmar. $900,000 Not Selected NA
    61 Hwy 274 Reclaim and overlay from Wood Lake to Highway 23 $6,500,000 Not Selected NA
    61 Hwy 9 Resurface Hwy 9 from Hwy 23 to Hwy 71. $2,700,000 Not Selected NA
    59 Hwy 67 Reclaim and overlay from Travers Ln. to Highway 19 $12,300,000 Not Selected NA
    58 Hwy 68 Reclaim and overlay Highway 71 to Redwood County Road 3 (Morgan) $7,700,000 Not Selected NA
    58 Hwy 67 Reclaim and overlay from US 75 to US59 near Clarkfield $7,200,000 Not Selected NA
    56 Hwy 68 Resurface Hwy 68 from N Grant St in Minneota to Hwy 59 in Marshall, excluding the city of Ghent. $1,803,000 2024 NA
    56 Hwy 68 Resurface Hwy 68 from N Grant St in Minneota to CR 33 in Marshall, excluding the city of Ghent. $900,000 2024 NA
    54 US59 Reclaim and overlay from Yellow Medicine County Road 3 to Clarkfield $4,100,000 Not Selected NA
    43 Hwy 22 Resurface Hwy 22 from Glencoe to Hutchinson. $6,900,000 2032 NA
    42 Hwy 22 Thin overlay from .1 miles east of Hwy 7 to .2 miles west of Hwy 7 $100,000 Not Selected NA
    40 Hwy 67 Thin mill and overlay Highway 23 (Granite Falls) to Travers Ln.  $2,100,000 Not Selected NA
    39 Hwy 269 Thin overlay from South Dakota/Minnesota State Line to Highway 23 (Jasper) $600,000 Not Selected NA
    37 Hwy 9 Thin overlay from Kandiyohi County Road 7 (Sunberg) to Kandiyohi / Swift Co. Line $100,000 Not selected NA
    36 US75 Thin overlay from 4th St. N. (Pipestone) to Pipestone County Road 22 $100,000 Not Selected NA
    32 Hwy 29 Thin overlay from Hwy 40 to Chippewa/Swift County Line $400,000 Not Selected NA
    31 Hwy 68 Thin overlay on from Highway 19 to Redwood County Road 32 (Milroy) $700,000 Not Selected NA
    29 Hwy 19 Thin overlay from Reference point 3 to Reference point 4 $200,000 Not selected NA
    29 Hwy 19 Thin overlay from Reference pt 003 to Reference pt 004 $200,000 Not Selected NA
    18 US59 Repair and smooth concrete pavement on Hwy 59 from 211th Street to Lyon CR 14 and from Lyon CR 6 to Hwy 23. $1,500,000 2024 NA
    6 Hwy 330 Thin overlay from Highway 14 to University of Minnesota SW Research and Outreach Center $500,000 Not Selected NA
    6 Hwy 22 Thin overlay from Sibley/McLeod County line to US212 $200,000 Not Selected NA
    5 Hwy 22 Thin overlay from Sibley/McLeod County Line to Highway 212 $400,000 Not Selected NA
    3 Hwy 104 Thin mill and overlay Highway 9 to Kandiyohi/Pope County Line $1,400,000 Not Selected NA

    View more detailed scores (Excel).

    Total Score Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
    87 Hwy 67 Construct cul-de-sac on Hwy 67 at entrance to Upper Sioux Agency State Park and remove pavement between cul-de-sac and bridge #87011. $620,000 Not Selected NA
    85 Hwy 68 Resurface Hwy 68 from Porter to Minneota; upgrade sidewalks to meet ADA standards in Porter, Taunton and Minneota; replace box culverts and bridges along project area. $10,500,000 2032 NA
    85 Hwy 68 Resurface Hwy 68 from Canby to Minneota; upgrade sidewalks to meet ADA standards in Porter, Taunton and Minneota; replace box culverts and bridges along project area. $10,900,000 2033 NA
    85 Hwy 4 Resurface Hwy 4 from Fairfax to Hector. $14,200,000 2026/2027 NA
    83 Hwy 24 Medium overlay Highway 12 (Litchfield) to Highway 15 $8,800,000 Not Selected This section has not been selected because it is a thin whitetopping test section (4-inch bonded concrete overlay in 2015). District will continue to monitor performance for research purposes.
    81 Hwy 30 Resurface Hwy 30 from the Minnesota/South Dakota state line to 8th St in Pipestone. $1,600,000 2029 NA
    81 US75 Cold in place recycling and medium overlay from Yellow Medicine County Road 3 (Canby) to 0.4 mi. S. of US 212 $4,000,000 Not selected Project was not selected due to fiscal constraints in 2030 (no new non-NHS projects were added in FY 2030)
    81 US75 Medium overlay from Murray County Road 3 to US212 $4,000,000 Not Selected Not a district priority will continue to monitor pavement performance.
    80 US75 Resurface Hwy 75 from Pipestone Creek to S Valley St in Lake Benton. $9,300,000 2030/2031 NA
    78 Hwy 30 Resurface Hwy 30 from Hwy 59 to the Murray/Cottonwood county line; replace bridge over Des Moines River. $14,400,000 2028/2029 NA
    78 Hwy 22 Medium overlay from Hutchinson to Highway 7 $3,300,000 Not Selected Candidate for reconstruction in 2034
    75 Hwy 22 Resurface Hwy 22 from Hwy 12 to Eden Valley. $9,300,000 2032 NA
    75 Hwy 19 Resurface Hwy 19 from Ivanhoe to CR 5. $22,700,000 2031/2032 NA
    75 US59 Reclaim and overlay from 15th Ave. (Clarkfield) to W. JCT. US 212 $3,800,000 Not selected NA
    74 Hwy 40 Reclaim and overlay Old Highway 277 to Kandiyohi County Road 5 (Willmar) $12,700,000 2026 NA
    74 Hwy 40 Resurface Hwy 40 from CR 4 to Willmar. $18,500,000 2030/2031 NA
    74 Hwy 68 Reclaim and overlay from N. JCT. US 71 to 0.2 mi. W. of Hwy 67 (Morgan) $3,900,000 Not selected NA
    74 Hwy 68 Reclaim and overlay from US71 to Hwy 57 in Morgan  $3,900,000 Not Selected NA
    74 Hwy 55 Medium overlay from Stearns/Meeker County Line to Eden Valley $3,000,000 Not Selected Candidate for preventive maintenance in 2024
    73 Hwy 22 Resurface Hwy 22 from Hwy 212 to Cedar Ave in Glencoe; update sidewalks in Glencoe to meet ADA standards. $3,000,000 2023 NA
    73 Hwy 30 Cold in place recycling and medium overlay from US 75 to Ravine St. (Lake Wilson) $4,300,000 Not selected NA
    71 Hwy 67 Resurface Hwy 67 from Hwy 23 to the Upper Sioux Agency State Park. $3,300,000 2029 NA
    71 US75 Resurface Hwy 75 from CR 9 to Hwy 30 in Pipestone. $4,700,000 Not Selected NA
    71 Hwy 119 Medium mill and overlay from Highway 212 (Dawson) to Highway 40 $2,700,000 Not Selected NA
    70 Hwy 15 Resurface Hwy 15 from Hwy 12 in Dassel to Meeker/Stearns county line. $9,724,000 2024/2025 NA
    69 Hwy 4 Reclaim and overlay from Hector to Cosmos $10,100,000 Not Selected NA
    68 Hwy 4 Resurface Hwy 4 from Cosmos to Meeker CR 23. (4701-32) $3,060,000 2023 This section has been prioritized due to maintenance patching losing effectiveness because of the level of deterioration. 
    67 Hwy 68 Resurface Hwy 68 from Wabasso to Hwy 71. $1,900,000 2030 NA
    65 Hwy 40 Resurface Hwy 40 from Hwy 119 to 5th Street in Milan. $4,900,000 2025/2026 Coordinated with other projects
    65 Hwy 7 Reclaim and overlay Highway 71 to Highway 4 (Cosmos) $13,000,000 Not Selected NA
    65 Hwy 7 Reclaim and overlay from Highway 4 (Cosmos) to Highway 22 $7,400,000 Not Selected Candidate for preventive maintenance in 2025
    65 Hwy 68 Reclaim and overlay from Redwood County Road 3 (Morgan) to Redwood/Brown County Line $3,100,000 Not Selected Candidate for reconstruction in 2030
    64 Hwy 267 Reclaim and overlay from Iona to Highway 30 $4,000,000 Not Selected NA
    63 Hwy 40/US75 Resurface Hwy 40 from Hwy 75 to Western Ave; resurface Hwy 75 from Hwy 40 to 8th St in Madison; upgrade sidewalks to meet ADA standards. $2,651,000 2023 NA
    63 US75 Reconstruct Hwy 75 from S Valley St in Lake Benton to south jct of Hwy 14. $5,500,000 2027 NA
    63 Hwy 68 Reclaim and overlay from South Dakota/Minnesota State Line to Canby $6,400,000 Not Selected NA
    62 Hwy 29/Hwy 40 Resurface Hwy 29 from west jct of Hwy 40 to east jct of Hwy 40; resurface Hwy 40 from east jct of Hwy 29 to Chippewa CR 4. $7,400,000 2029/2033 NA
    62 Hwy 67 Reclaim and overlay from Redwood Falls to Fergus Ave. (Morgan) $8,600,000 Not Selected NA
    62 Hwy 29 Reclaim and overlay from Airport Ave (Montevideo) to Hwy 40 $3,700,000 Not selected NA
    61 Hwy 274 Reclaim and overlay from Wood Lake to Highway 23 $6,500,000 Not Selected NA
    59 Hwy 67 Reclaim and overlay from Travers Ln. to Highway 19 $12,300,000 Not Selected NA
    58 Hwy 68 Reclaim and overlay Highway 71 to Redwood County Road 3 (Morgan) $7,700,000 Not Selected NA
    58 Hwy 67 Reclaim and overlay from US 75 to US59 near Clarkfield $7,200,000 Not Selected NA
    56 Hwy 68 Resurface Hwy 68 from N Grant St in Minneota to Hwy 59 in Marshall, excluding the city of Ghent; upgrade sidewalks on Hwy 19 from Hwy 23 to Tiger Dr and on Hwy 59 from Windstart St to Susan Dr in Marshall to meet ADA standards. $2,700,000 2024 NA
    56 Hwy 68 Resurface Hwy 68 from N Grant St in Minneota to CR 33 in Marshall, excluding the city of Ghent. $890,910 2024 NA
    54 US59 Reclaim and overlay from Yellow Medicine County Road 3 to Clarkfield $4,100,000 Not Selected NA
    42 Hwy 22 Thin overlay from .1 miles east of Hwy 7 to .2 miles west of Hwy 7 $100,000 Not Selected NA
    40 Hwy 67 Thin mill and overlay Highway 23 (Granite Falls) to Travers Ln.  $2,100,000 Not Selected NA
    39 Hwy 269 Thin overlay from South Dakota/Minnesota State Line to Highway 23 (Jasper) $600,000 Not Selected NA
    37 Hwy 9 Thin overlay from Kandiyohi County Road 7 (Sunberg) to Kandiyohi / Swift Co. Line $100,000 Not selected NA
    36 US75 Thin overlay from 4th St. N. (Pipestone) to Pipestone County Road 22 $100,000 Not Selected NA
    32 Hwy 29 Thin overlay from Hwy 40 to Chippewa/Swift County Line $400,000 Not Selected NA
    31 Hwy 68 Thin overlay on from Highway 19 to Redwood County Road 32 (Milroy) $700,000 Not Selected NA
    29 Hwy 19 Thin overlay from Reference point 3 to Reference point 4 $200,000 Not selected NA
    6 Hwy 330 Thin overlay from Highway 14 to University of Minnesota SW Research and Outreach Center $500,000 Not Selected NA
    5 Hwy 22 Thin overlay from Sibley/McLeod County Line to Highway 212 $400,000 Not Selected NA
    3 Hwy 104 Thin mill and overlay Highway 9 to Kandiyohi/Pope County Line $1,400,000 Not Selected NA

    View more detailed scores (Excel).

    Total Score Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
    83 US71 Rural reconstruction from Highway 23 to Willmar Bypass and additional locations on Highway 71  $               25,000,000 2028 NA
    79 Hwy 23 Medium mill and overlay from Highway 75 (Pipestone) to north of Highway 91 (Russel)  $               13,400,000 2024 NA
    79 US71 Reclaim and overlay from Redwood County Road 115 (Sanborn) to Highway 68  $                 8,800,000 2027 NA
    78 Hwy 23 Major concrete rehabilitation from north of Highway 91 (Russel) to Highway 19 (Marshall)  $               20,400,000 2029 NA
    77 US71 Major CPR and diamond grinding from US212 to Hwy 7  $                 4,800,000 Not selected Project not selected due to the previous fix being a minor CPR in 2018; it is expected that the average life of those repair are approx. 15 years. This project will be reconsidered approx. 2033
    77 US212 Major concrete rehabilitation from Highway 23 (Granite Falls) to east of Highway 23  $                 8,600,000 Not Selected The district is currently prioritizing other concrete segments that have not yet received a rehabilitation
    75 Hwy 15 Thin mill and overlay from Highway 212 (Brownton) to Hutchinson  $                 3,200,000 Not Selected Candidate for Preventative Maintenance work in 2024
    75 US14 Medium overlay and cold in inplace recycling from Lake Benton to Lincoln/Lyon County Line  $                 5,200,000 2027 NA
    75 US12 Major concrete pavement rehabilitation from Darwin to Cokato  $               10,700,000 2024 NA
    75 US212 Medium overlay from Renville County road 16 to Renville County Road 7  $                 3,700,000 2030 NA
    74 US71 Major CPR and diamond grinding from  Cottonwood/Redwood County line to 120th St   $                     900,000 Not selected Project not selected due to short length (2 miles); this pavement section continues south into District 7. This project will be selected when District 7 schedules a project.
    73 Hwy 7 and Hwy 22 Major concrete rehabilitation on Highway 7 from Hutchinson to Silver Lake, and on Highway 22 from McLeod County road 25 to  Highway 7 (Hutchinson Bypass)  $                 6,200,000 2027 NA
    73 Hwy 19 and US71 Major rehabilitation on Hwy 19 from Qualit Dr to Centennial Dr and on US71 from Hwy 19 to Renville County Road 19  $                 3,000,000 2031 NA
    72 US59 Cold in place recycling and medium overlay from Highway 14 to Lyon County Road 6 (Marshall)  $                 5,800,000 2028 NA
    71 Hwy 15 Medium overlay from Hutchinson to Highway 12 (Dassel)  $                 6,400,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
    71 US71 Reclaim and overlay from Highway 68 to Redwood Falls  $                 6,800,000 2029 NA
    71 US12 Medium overlay from Kerkhoven to Pennock  $                 3,800,000 Not Selected Candidate for preventive maintenance work in 2025
    70 Hwy 15 Reclaim and overlay from Highway 12 (Dassel) to Meeker/Stearns County Line  $                 8,400,000 2023 This section has been prioritized because maintenance patching is losing effectiveness.
    70 US14 Medium mill and overlay from Highway 23 to Tracy  $                 9,400,000 2028 NA
    70 Hwy 23 Thin mill and overlay Highway 19 (Marshall) to Lyon County Road 33  $                 1,200,000 2028 This section has been prioritized because a thin mill and overlay will improve performance.
    69 US59 Medium overlay Highway 30 (Slayton) to north junction of Highway 30  $                 3,000,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
    69 US212 Minor concrete pavement rehab and diamond grinding from Olivia to Bird Island  $                 1,000,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
    68 US14 Thin mill and overlay from South Dakota/Minnesota State line to US75  $                 1,400,000 2029 NA
    67 Hwy 23 Medium mill and overlay from Rock/Pipestone County Line (Jasper) to Highway30 (Pipestone)   $                 5,700,000 Not Selected NA
    67 US71 Medium mill and overlay from Highway 19 (Morton) to Olivia  $                 7,500,000 Not Selected NA
    65 US14 Medium overlay and cold in place recycling from Revere to Redwood/Brown County Line  $                 6,300,000 Not Selected NA
    64 Hwy 7 Reclaim and overlay from Highway 40 (Milan) to Montevideo  $               11,100,000 Not Selected NA
    58 Hwy 15 Reclaim and overlay from Hwy 19 to US212  $                 4,600,000 Not selected NA
    56 US71 Concrete reconstruction from Highway 23 to Willmar Bypass  $                 7,900,000 Not Selected NA
    53 US59 Reconstruction from Highway 68 (Marshall) to Lyon County Road 33  $                 8,900,000 Not Selected NA
    48 US71 Cold in place recycling and medium overlay from Hwy 7 to Hwy 23  $                 2,500,000 Not selected NA
    46 US212 Minor CPR and diamond grinding from Hwy 22 to Morningside Dr  $                 1,400,000 Not selected NA
    45 US212 Unbonded overlay from Morningside Dr to Hwy 5  $               12,400,000 Not selected NA
    44 US212 Minor CPR and diamond grinding from US75 to .5 miles west of Hwy 29 (excluding Dawson)  $                 3,400,000 Not selected NA
    43 Hwy 22 Cold in place recycling and medium overlay from Cedar Ave to McLeod County Road 115  $                 2,600,000 Not selected NA
    40 Hwy 22 Concrete reconstruction from Glencoe to Hutchinson  $               50,600,000 Not Selected NA
    40 US12 Thin overlay from Highway 22 to Highway 24 (Litchfield)  $                     200,000 Not Selected NA
    39 US12 Concrete reconstruction from Highway 71 to Kandiyohi/Meeker County Line  $               58,300,000 Not Selected NA
    37 Hwy 15 Thin overlay from Meeker County Road 18 to south of US12  $                     200,000 Not selected NA
    37 US71 Thin overlay from Kandiyohi County Road 93 to Hwy 23  $                     100,000 Not selected NA
    37 US59 Thin overlay from Nobles/Murray County Line to Highway 62 (Fulda)  $                     400,000 Not Selected NA
    36 US71 Thin overlay from Quality Drive (Redwood Falls) to Highway 71 and additional locations on Highway 71  $                 1,300,000 Not Selected NA
    36 US12 Thin mill and overlay from 25th St. SE (Willmar) to Highway 71  $                     400,000 Not Selected NA
    35 Hwy 7 Thin overlay from the end of bridge 8518 to Carver County Road 33  $                     100,000 Not selected NA
    33 Hwy 23 Major CPR and diamond grinding from .1 mile south of Hwy 7 to .3 miles north of Hwy 7  $                     200,000 Not selected NA
    31 US14 Thin overlay from Redwood  County Road 7 to Main St   $                     100,000 Not selected NA
    30 US59 Thin overlay from .6 miles south of Hwy 62 to Hwy 62  $                     100,000 Not selected NA
    20 US212 Thin overlay eastbound from west of Highway 5 to Highway 5  $                     100,000 Not Selected NA
    12 US59 Thin overlay from Murray County Road 6 to 1st St  $                     100,000 Not selected NA
    8 Hwy 15 Minot CPR and diamond grinding from north of High Dr/County Road 15 to north of High Drive  $                     100,000 Not selected NA
    8 Hwy 7 Thin mill and overlay on Highway 7 & Highway 25 Roundabout  $                     100,000 Not Selected NA
    8 US71 Thin overlay on Highway 71 & Highway 7 Roundabout  $                     100,000 Not Selected NA
    7 Hwy 15 Thin overlay on Highway 19 (Winthrop) to north of Highway 19  $                     100,000 Not Selected NA
    6 Hwy 7 Thin overlay from Swift Chippewa County Line to Hwy 40  $                     500,000 Not selected NA
    6 Hwy 7 Minor concrete pavement rehab and diamond grinding at the intersection of Highway 23 & Highway 7 (Clara City) - approx. 1000 feet on each leg  $                     300,000 Not Selected NA

    View more detailed scores (Excel).

    Total Score Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
    85 Hwy 4 Reclaim and overlay from Highway 19 (Fairfax) to Highway 12 (Hector) $9,200,000 2025 NA
    85 Hwy 68 Reclaim and overlay from Canby to Minneota $13,000,000 2030 NA
    83 Hwy 24 Medium overlay Highway 12 (Litchfield) to Highway 15 $8,800,000 Not Selected This section has not been selected because it is a thin whitetopping test section (4-inch bonded concrete overlay in 2015). District will continue to monitor performance for research purposes.
    81 US 75 Medium overlay from Murray County Road 3 to Hwy212 $4,000,000 Not Selected Not a district priority. Will continue to monitor pavement performance. 
    81 Hwy 30 Thin mill and overlay from South Dakota/Minnesota State line to 8th St in Pipestone $1,200,000 2029 NA
    80 Hwy 271 Reclaim and overlay from Highway 19 to Minnesota/South Dakota State Line $4,900,000 2023 NA
    80 US75 Medium overlay from Pipestone Creek to Lake Benton $5,400,000 2026 NA
    78 Hwy 40 Medium mill and overlay from Highway 59 (Milan) to Highway 29 $4,000,000 2024 NA
    78 Hwy 22 Medium overlay from Hutchinson to Highway 7 $3,300,000 Not Selected Candidate for reconstruction in 2034
    78 Hwy 30 Reclaim and overlay from Hwy59 to Murray/Cottonwood County line $4,900,000 2026 NA
    75 Hwy 19 Reclaim and overlay from Ivanhoe to Lincoln County Road 5 $13,900,000 2029 NA
    75 US 59 Reclaim and overlay from 15th Ave to west junction of Hwy212 $3,800,000 Not Selected NA
    75 Hwy 22 Thin overlay from Hwy12 to Fredricks Ave  $1,100,000 2026 NA
    74 Hwy 68 Reclaim and overlay from Hwy71 to Hwy 57 in Morgan  $3,900,000 Not Selected NA
    74 Hwy 40 Reclaim and overlay Old Highway 277 to Kandiyohi County Road 5 (Willmar) $12,700,000 2026 NA
    74 Hwy 55 Medium overlay from Stearns/Meeker County Line to Eden Valley $3,000,000 Not Selected Candidate for preventive maintenance in 2024
    73 Hwy 30 Medium overlay from Hwy75 to Ravine St in Lake Wilson $4,300,000 Not Selected NA
    71 Hwy 119 Medium mill and overlay from Highway 212 (Dawson) to Highway 40 $2,700,000 Not Selected Candidate for preventive maintenance in 2021
    71 Hwy 67 Thin mill and overlay from Hwy 23 to Upper Sioux Agency State Park $1,000,000 2027 Project was selected because a thin mill & overlay is a low cost treatment with a large performance benefit for this segment (as indicated by low levels of cracking)
    69 Hwy 4 Reclaim and overlay from Hector to Cosmos $10,100,000 Not Selected Candidate for preventive maintenance in 2021
    67 Hwy 68 Thin mill and overlay from Redwood County Road 6 in Wabasso to south junction with Hwy71 $1,100,000 2029 Project was selected because a thin mill & overlay is a low cost treatment with a large performance benefit for this segment (as indicated by low levels of cracking)
    65 Hwy 40 Medium mill from Highway 119 to Highway 59 (Milan) $3,600,000 2025 Coordinated with other projects
    65 Hwy 68 Reclaim and overlay from Redwood County Road 3 (Morgan) to Redwood/Brown County Line $3,100,000 Not Selected Candidate for reconstruction in 2030
    65 Hwy 7 Reclaim and overlay Highway 71 to Highway 4 (Cosmos) $13,000,000 Not Selected NA
    65 Hwy 7 Reclaim and overlay from Highway 4 (Cosmos) to Highway 22 $7,400,000 Not Selected Candidate for preventive maintenance in 2025
    64 Hwy 4 Reclaim and overlay from Cosmos to  Meeker County Road 23 $5,400,000 2023 This section has been prioritized due to maintenance patching losing effectiveness because of the level of deterioration. 
    64 Hwy 267 Reclaim and overlay from Iona to Highway 30 $4,000,000 Not Selected NA
    63 Hwy 68 Reclaim and overlay from South Dakota/Minnesota State Line to Canby $6,400,000 Not Selected NA
    62 Hwy 29 Medium mill and overlay from west junction of Highway 40 to east junction Highway 40 and additional locations on Highway 40 $5,200,000 2024 Coordinated with projects on Highway 40
    62 Hwy 67 Reclaim and overlay from Redwood Falls to Fergus Ave. (Morgan) $8,600,000 Not Selected NA
    62 Hwy 29 Reclaim and overlay from Airport Trail to Hwy 40 $3,700,000 Not Selected NA
    61 Hwy 274 Reclaim and overlay from Wood Lake to Highway 23 $6,500,000 Not Selected NA
    59 Hwy 67 Reclaim and overlay from Travers Ln. to Highway 19 $12,300,000 Not Selected NA
    58 Hwy 68 Reclaim and overlay Highway 71 to Redwood County Road 3 (Morgan) $7,700,000 Not Selected NA
    58 Hwy 67 Reclaim and overlay from Hwy 75 to Hwy59 near Clarkfield $7,200,000 Not Selected NA
    54 US59 Reclaim and overlay from Yellow Medicine County Road 3 to Clarkfield $4,100,000 Not Selected NA
    42 Hwy 22 Thin overlay from .1 miles east of Hwy 7 to .2 miles west of Hwy 7 $100,000 Not Selected NA
    40 Hwy 67 Thin mill and overlay Highway 23 (Granite Falls) to Travers Ln.  $2,100,000 Not Selected NA
    39 Hwy 269 Thin overlay from South Dakota/Minnesota State Line to Highway 23 (Jasper) $600,000 Not Selected NA
    37 Hwy 9 Thin overlay from Kandiyohi County Road 7 to Kandiyohi/Swift County line $100,000 Not Selected NA
    36 US75 Thin overlay from 4th St. N. (Pipestone) to Pipestone County Road 22 $100,000 Not Selected NA
    32 Hwy 29 Thin overlay from Hwy 40 to Chippewa/Swift County Line $400,000 Not Selected NA
    31 Hwy 68 Thin overlay on from Highway 19 to Redwood County Road 32 (Milroy) $700,000 Not Selected NA
    29 Hwy 19 Thin overlay from Reference pt 003 to Reference pt 004 $200,000 Not Selected NA
    6 Hwy 330 Thin overlay from Highway 14 to University of Minnesota SW Research and Outreach Center $500,000 Not Selected NA
    6 Hwy 22 Thin overlay from Sibley/McLeod County line to Hwy212 $200,000 Not Selected NA
    3 Hwy 104 Thin mill and overlay Highway 9 to Kandiyohi/Pope County Line $1,400,000 Not Selected NA

    View more detailed scores (Excel).

    Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
    85 Hwy 4 Reclaim and overlay from Highway 19 (Fairfax) to Highway 12 (Hector) $9,200,000 2024 NA
    85 Hwy 68 Reclaim and overlay from Canby to Minneota $13,000,000 2028 NA
    83 Hwy 24 Medium overlay Highway 12 (Litchfield) to Highway 15 $8,800,000 Not Selected This section has not been selected because it is a thin whitetopping test section (4-inch bonded concrete overlay in 2015). District will continue to monitor performance for research purposes.
    80 Hwy 271 Reclaim and overlay from Highway 19 to Minnesota/South Dakota State Line $4,900,000 2023 NA
    80 US75 Medium overlay from Pipestone Creek to Lake Benton $5,400,000 2026 NA
    80 US75 Medium overlay from Highway 268 (Trosky) to Highway 30 (Pipestone) $5,200,000 2028 NA
    78 Hwy 40 Medium mill and overlay from Highway 59 (Milan) to Highway 29 $4,000,000 2024 NA
    78 Hwy 22 Medium overlay from Hutchinson to Highway 7 $3,300,000 Not Selected Candidate for reconstruction in 2034
    75 Hwy 19 Reclaim and overlay from Ivanhoe to Lincoln County Road 5 $14,000,000 2029 NA
    74 Hwy 40 Reclaim and overlay from old Highway 277 to Kandiyohi County Road 5 (Willmar) $13,000,000 2026 NA
    74 Hwy 55 Medium overlay from Stearns/Meeker County Line to Eden Valley $3,000,000 Not Selected Candidate for preventive maintenance in 2024
    71 Hwy 119 Medium mill and overlay from Highway 212 (Dawson) to Highway 40 $2,700,000 Not Selected Candidate for preventive maintenance in 2021
    69 Hwy 4 Reclaim and overlay from Hector to Cosmos $10,000,000 Not Selected Candidate for preventive maintenance in 2021
    65 Hwy 40 Medium mill from Highway 119 to Highway 59 (Milan) $3,600,000 2025 Coordinated with other projects
    65 Hwy 68 Reclaim and overlay from Redwood County Road 3 (Morgan) to Redwood/Brown County Line $3,100,000 Not Selected Candidate for reconstruction in 2030
    65 Hwy 7 Reclaim and overlay Highway 71 to Highway 4 (Cosmos) $13,000,000 Not Selected NA
    65 Hwy 7 Reclaim and overlay from Highway 4 (Cosmos) to Highway 22 $7,400,000 Not Selected Candidate for preventive maintenance in 2025
    64 Hwy 4 Reclaim and overlay from Cosmos to  Meeker County Road 23 $5,400,000 2023 This section has been prioritized due to maintenance patching losing effectiveness because of the level of deterioration. 
    64 Hwy 267 Reclaim and overlay from Iona to Highway 30 $4,000,000 Not Selected NA
    63 Hwy 68 Reclaim and overlay from South Dakota/Minnesota State Line to Canby $6,400,000 Not Selected NA
    62 Hwy 67 Reclaim and overlay from Redwood Falls to Fergus Ave. (Morgan) $8,600,000 Not Selected NA
    62 Hwy 29 Medium mill and overlay from west junction of Highway 40 to east junction Highway 40 and additional locations on Highway 40 $5,200,000 2024 Coordinated with projects on Highway 40
    61 Hwy 274 Reclaim and overlay from Wood Lake to Highway 23 $6,500,000 Not Selected NA
    59 Hwy 67 Reclaim and overlay from Travers Ln to Highway 19 $12,000,000 Not Selected NA
    58 Hwy 68 Reclaim and overlay Highway 71 to Redwood County Road 3 (Morgan) $7,700,000 Not Selected NA
    54 US59 Reclaim and overlay from Yellow Medicine County Road 3 to Clarkfield $4,100,000 Not Selected NA
    40 Hwy 67 Thin mill and overlay Highway 23 (Granite Falls) to Travers Ln $2,100,000 Not Selected NA
    39 Hwy 269 Thin overlay from South Dakota/Minnesota State Line to Highway 23 (Jasper) $600,000 Not Selected NA
    36 US75 Thin overlay from 4th St. N. (Pipestone) to Pipestone County Road 22 $100,000 Not Selected NA
    31 Hwy 68 Thin overlay on from Highway 19 to Redwood County Road 32 (Milroy) $700,000 Not Selected NA
    6 Hwy 330 Thin overlay from Highway 14 to University of Minnesota SW Research and Outreach Center $500,000 Not Selected NA
    5 Hwy 22 Thin overlay from Sibley/McLeod County Line to Highway 212 $400,000 Not Selected NA
    3 Hwy 104 Thin mill and overlay from Highway 9 to Kandiyohi/Pope County Line $1,400,000 Not Selected NA