-94 between East River Pkwy./Franklin Ave. and just west of Hwy 55/Hiawatha Ave./I-35W project area map.

I-94 in Minneapolis project area map

View full-size map

All traffic impacts are tentative and weather dependent.

Current

Lane closures

5 a.m. Mon, Oct. 28 through Fri, Nov. 29
  • I-94 is reduced to two lanes in both directions between 11th Ave. S. and Franklin Ave. S.E.

Ramp closures

11 p.m. Wed, Oct. 30 through 5 a.m. Thu, Oct. 31 
  • The ramp from EB I-94 to 9th St. is closed 
5 a.m. Mon, Oct. 28 through Fri, Nov. 29

Upcoming

Information about upcoming traffic impacts will be posted as details become available. Motorists can expect lane and ramp closures on I-94 between downtown Minneapolis and the Franklin Ave. bridge over I-94.

About this project

We will be doing maintenance and repair work on five bridges along I-94 in Minneapolis. These bridges include:

  • I-94 bridge (Dartmouth Bridge) that spans the Mississippi River
  • Riverside Ave. bridge over I-94
  • I-94 over Cedar Ave.
  • I-94 over the Light Rail Transit (Blue Line)
  • I-94 over Hwy 55/Hiawatha Ave.

Summary of work

  • Construct temporary crossovers
  • Repair bridge decks
  • Resurface bridge pavement
  • Remove and replace bridge joints
  • Update guardrails
  • Upgrade drainage
  • Repaint bridge steel