Minnesota Department of Transportation

511 Travel Info

Project selection

Increasing the transparency of how we select highway construction projects

National Highway System pavement projects

MnDOT Metro District

Scoring criteria for national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on network designation, and 5 points are based on the miles covered by the project.

Learn more about how MnDOT evaluates and selects pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2024

Score Route  Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
0 Hwy 55 Replace signal, reconstruct pavement, improve ADA at TH55 at Pine St and River St in Hastings   $1,326,000   Not Selected NA
0 Hwy 62 Resurface Hwy 62 from Lexington Ave to Northbound 35E Ramp.   $3,044,445   Not Selected NA
0 Hwy 65 Improve TH65 in Columbia Heights   $25,000,000   2028   NA
96 Hwy 100 Resurface road, repair 14 bridges, curb and gutter repair, access removal, ramp realignment and removal of bridge 27042 on Hwy 100 from under pedestrian bridge/exit Cedar Lake Rd in St Louis Park to I-694 in Brooklyn Center    $49,618,000   2027, 2028   Poor pavement conditions; preventive maintenance. 
95 I35E Repair road surface from Little Canada Rd to County Rd E bridge $8,000,000 Not Selected  Repair early distresses.
95 I35E Repair road from I-35W/I-35E split to Lone Oak Rd in Burnsville $128,834,599 2030 Projected poor pavement conditions. 
95 I494 Repair road from France Ave to US 12 $18,000,000 Not selected Preventive maintenance.
94 I694 Resurface Hwy 694 from Hwy 61 to CR 10 in Vadnais Heights $23,400,000 2033 Repair early distresses.
93.5 I35E Resurface I-35E from Lone Oak Rd to bridge over Marie in Mendota Heights $24,079,234 2033 NA
91 US169 Medium mill and overlay from Hwy 55 to 77th Ave $7,800,000 Not Selected  Program limited by available funding.
91 US52 Medium mill and overlay from I-494 to Lafayette bridge $5,100,000 Not Selected  Program limited by available funding.
90 I35W Medium mill and overlay from Hwy 13 to 106th St $4,000,000 Not Selected  Construction of I-35W River Crossing at time of DIV run, bypass pavement is rough.
90 I35W Medium mill and overlay from 4th St bridge to Ramsey County Road C $8,000,000 Not Selected  RQI does not reflect on the ground conditions
90 I494 Medium mill and overlay from 24th Ave to France Ave $29,400,000 Not selected Poor pavement conditions. Coordinate with 494 Corridors of Commerce project. 
90 I94 Medium mill and overlay from I-494 to Nicollet Ave bridge $27,400,000 Not Selected  RQI does not reflect on the ground conditions
89 I35W Repair road from 82nd to 66th Street    $25,378,591   Not selected Repair early distresses.
89 I394 Resurface I 394 from I-494/US 212 to Hwy 100 in Golden Valley, Minnetonka and Saint Louis Park $56,244,000 2031 Projected poor pavement conditions.
89 I94 Resurface I 94 from E. of Nicollet Ave Bridge in Minneapolis to .1 mi. W of Western Ave in St. Paul $82,347,797 2034 Projected poor pavement conditions.
89 US212 Resurface road from I-494 to Hwy 62 in Eden Prairie $28,270,000 2033 Poor pavement conditions.
88 I394 Medium mill and overlay from Hwy 100 to Washington Ave N $3,200,000 Not Selected  Recent major rehab. Low RQI attributed largely to high percentage of bridge decks. Also, after a recent lane reconfiguration of WB, part of the outside lane is on rough bituminous shoulder.
88 I494 Medium mill and overlay from 5th Ave to Dakota/Hennepin County Line $13,600,000 Not Selected  RQI does not reflect on the ground conditions
87 I35 Repair road surface, I 35 from County Rd 70 to 35E/35W split and from County Road 50 to the 35E/35W split. Replace I-35 bridges over CSAH 50 & 205th St and repair I-35 bridges over Lake Marion in Burnsville and Lakeville $75,830,000 2029 Poor pavement conditions.
85 I494 Medium mill and overlay from Hardman bridge to 5th Ave $2,200,000 Not Selected  RQI does not reflect on the ground conditions
84 Hwy 280 Resurface road, ADA, signal work, rehabilitate bridges 9471, 9472, 62033, 62034, 62843 on Hwy 280 from Wabash Ave in St Paul to north of Broadway Ave in Lauderdale and close median on Hwy 280 at Broadway Ave in Lauderdale and install signals at Kosata Ave and ramps with Energy Park Dr in St Paul   $7,700,000   2028   NA
84 Hwy 280 Repair pavement, guardrail, rehab 7 bridges on Hwy 280 from Wabash in St Paul to junction with I-35W in Lauderdale    $25,972,000   2026, 2027   Poor pavement conditions; coordinate with bridge work. 
84 US10 Resurface Hwy 10 from US169/Hwy 47 to Creek Medows Bridge in Coon Rapids and Anoka $19,620,000 2032 Projected poor pavement conditions.
83 I694 Medium mill and overlay from I-494/694 to Lexington Ave $2,900,000 Not Selected  This segment consists of older concrete pavement with recent CPR and fairly new UBOLs. 2020 RQI is very good to excellent. Minor CPR is ongoing due to dowel bar issues.
83 US169 Medium mill and overlay from Hwy 62 to Hwy 55 $6,300,000 Not Selected  Program limited by available funding.
81 I35W Medium mill and overlay from Washington Ave bridge to 4th St Bridge $1,600,000 Not Selected  This is new pavement but is predominantly comprised of St. Anthony Falls bridge deck. 2020 RQI is excellent.
81 I494 Medium mill and overlay from Tamarack bridge to Hardman bridge $6,100,000 Not Selected  RQI does not reflect on the ground conditions
81 Hwy 7 Resurface road from the Hennepin/Carver County line to Division St and replace bridge over County Road 82 in Excelsior $40,910,000 2029 Recent resurfacing project. Construction in progress at time of DIV run. Roughness at intersection contribute to poor ride.
81 US169 Resurface road from 77th Ave N to 101st Ave N $4,400,000 Not Selected  Poor pavement conditions.
81 US61 Thin mill and overlay from Goodhue/Dakota County Line to Hwy 316 $9,000,000 Not Selected Projected poor pavement conditions.
80 US12 Resurface road, upgrade ADA, drainage on TH12 from the Wright/Hennepin County line in Delano to CR 29 in Maple Plain and Construct roundabout at TH12 and County Line Road in Delano    $12,940,000   2028, Future   Poor pavement conditions.
80 US52 Medium mill and overlay from Hwy 65 to University Ave $1,600,000 Not selected Program limited by available funding.
80 US52 Resurface US 52 from Clayton to south of Inver Grove Trail; replace 2 and resurface 2 US 52 bridges over the UP Railroad, and replace the Hwy 55 bridge over US 52 in Inver Grove Heights $54,190,000 2032 NA
79 US61 Resurface road and repair bridge 19075 on Hwy 61 (Vermillion St) from N Jct Hwy 316 (Red Wing Blvd) to 4th St in Hastings   $10,867,000   2027   Poor pavement conditions. 
78 I35W Medium mill and overlay from 42nd st bridge to Chicago Ave Bridge $6,500,000 Not Selected  Construction of Lake St project at time of DIV run, bypass pavement is rough.
78 Hwy 7 Medium mill and overlay from Shady Oak Rd to Texas Ave $3,000,000 Not Selected  RQI does not reflect on the ground conditions
78 US10 Medium mill and overlay from US61 to .1 miles east of US61 $100,000 Not selected Program limited by available funding. Short piece of 4 lane east of USTH 61. Recently received a UTBWC surface treatment.
77 I35 Medium mill and overlay from US 8 to Hwy 95 $15,700,000 Not Selected  Program limited by available funding. Proposed thin overlay within next few years.
77 US8 Resurface US 8 from W Wyoming Ave to Tern Ave in Center City $32,032,920 2032 Poor pavement conditions.
76 Hwy 100 Medium mill and overlay from I-494 to Cedar Lake Bridge $10,900,000 Not Selected  RQI does not reflect on the ground conditions
76 Hwy 610 Medium mill and overlay from Hwy 252 to Mississippi River Bridge  $1,000,000 Not Selected  Program limited by available funding.
76 US10 Medium mill and overlay from Foley Blvd to Hwy 56 $4,100,000 Not Selected  RQI does not reflect on the ground conditions
76 US212 Repair and resurface US 212 from Mcleod/Carver County line to Hwy 5 in Norwood Young America $5,362,800 2032 NA
76 US52 Medium mill and overlay from Lafayette bridge to I-94 $200,000 Not Selected  Program limited by available funding.
75.5 I35W Resurface I 35W from Portland Ave to Washington Ave Bridge in Minneapolis $11,020,783 2034 Projected poor pavement conditions.
75 I35E Medium mill and overlay from University Ave to Cayuga/Railroad Bridge $2,100,000 Not Selected  Program limited by available funding. Section is predominantly bridge decks.
74 Hwy 25 Medium mill and overlay from Hwy 5 to Hwy 7 $3,900,000 Not Selected  Program limited by available funding.
74 Hwy 62 Medium mill and overlay from Tracy ave bridge to Penn Ave Bridge $3,200,000 Not Selected  Program limited by available funding.
74 US10 Resurface road, drainage on Hwy 10 from Cleveland/Jarvis St in Elk River to 0.5 miles W to Ramsey Blvd in Anoka and intersection improvements on Hwy 10 from Cleveland/Jarvis St in Elk River to 0.5 miles W to Ramsey Blvd in Anoka - TIED LET GROUP 10174   $11,170,000   2027   NA
73 I694 Medium mill and overlay from County Road 10 to Anoka Isanti County Line $1,000,000 Not Selected  Under construction at time of DIV run. New concrete pavement at system interchange (94/494/694).
73 Hwy 62 Medium mill and overlay from 43rd Ave to Mendota Bridge $1,600,000 Not Selected  Program limited by available funding.
73 Hwy 7 Medium mill and overlay from Texas Ave to Railroad Bridge  $700,000 Not Selected  RQI does not reflect on the ground conditions
73 US10 Medium mill and overlay from I-35W to I694 $3,000,000 Not selected RQI does not match on the ground conditions
73 US52 Medium mill and overlay from Dakota County Road 42 to Clayton Ave $800,000 Not Selected  Program limited by available funding.
72 I35E Thin mill and overlay from bridge 9532 to 10th St bridge $5,700,000 Not Selected  Projected poor pavement conditions.
72 Hwy 7 Resurface Hwy 7 from Hwy 25 to Carver County Line in Mayer $13,762,776 2033 Projected poor pavement conditions.
72 US169 Medium mill and overlay from Catrerbury rd to Valley View Rd $8,600,000 Not Selected  Program limited by available funding.
72 US169 Medium mill and overlay from Anderson Lakes Pkwy to Valley View Rd $1,500,000 Not Selected  Program limited by available funding.
71 Hwy 25 Medium mill and overlay from Scott County line to Hwy 5 $7,100,000 Not selected RQI does not match on the ground conditions
71 US10 Medium mill and overlay from east of 114th Ave NW to east Foley Blvd $2,200,000 Not Selected  RQI does not reflect on the ground conditions
70 I35W Medium mill and overlay from 76th St to 66th ST $1,800,000 Not Selected  Program limited by available funding.
70 Hwy 62 Resurface Hwy 62 from Penn Ave to Portland Ave in Minneapolis - Future Project $26,955,808 2035 Repair early distresses.
70 Hwy 65 Resurface road from NE 37th Ave CL to 53rd Ave NE    $5,270,000   Not Selected Projected poor pavement conditions.
70 US12 Medium mill and overlay from County Road 90 to eastern Independence City limits $400,000 Not Selected  Program limited by available funding.
70 US52 Resurface US 52 from Inver Grove Trail to Hwy 55 and Hwy 55 bridge over US 52 in Inver Grove Heights $5,040,000 2032 NA
69 Hwy 252 Medium mill and overlay from 85th to Hwy 610 $1,100,000 Not Selected  Program limited by available funding.
69 Hwy 62 Medium mill and overlay from I-35E to US52 $3,500,000 Not selected Program limited by available funding.
69 US212 Medium mill and overlay from Hwy 5 to Tacoma Ave $3,500,000 Not Selected  Program limited by available funding.
69 US52 Medium mill and overlay from Goodhue/Dakota County Line to County Road 86 $2,300,000 Not Selected  Program limited by available funding.
68 Hwy 65 Medium mill and overlay from 26th St to 10th ST $1,300,000 Not Selected  Program limited by available funding.
68 US169 Medium mill and overlay from Elm creek Blvd to Mississippi River Bridge $500,000 Not Selected  Program limited by available funding.
68 US212 Medium mill and overlay from 2.2 miles east of Hwy 284 to 4 lane section $2,200,000 Not Selected  Program limited by available funding.
67 I35W Pavement repair on I35W from 66th St in Richfield to 42nd St Bridge in Minneapolis $61,038,073 2034 NA
67 Hwy 41 Medium mill and overlay from US169 to Pioneer Trail $1,200,000 Not Selected  Program limited by available funding.
67 Hwy 7 Medium mill and overlay from Railroad bridge to Hwy 100 $900,000 Not Selected  Program limited by available funding.
67 US12 Medium mill and overlay from Wright/Hennepin County line to Hennepin County Road 90 $7,600,000 Not Selected  Poor pavement conditions.
67 US212 Repair US 212 from Highway 41 to County Rd. 4 in Chaska $23,680,250 2032 Preventive maintenance.
66 I35E Medium mill and overlay from 76th St to 66th ST $900,000 Not Selected  Program limited by available funding.
66 Hwy 36 Medium mill and overlay from I35W to east of Edgerton St $9,500,000 Not Selected  Poor pavement conditions; maintenance liability.
66 Hwy 610 Repair road from US 169 to Mississippi River $20,000,000 Not Selected  Projected poor pavement conditions.
66 Hwy 7 Medium mill and overlay from I-494 to Shady Oak Road $1,000,000 Not Selected  Program limited by available funding.
66 US212 Meduim mill and overlay from Hwy 5 to .4 miles east of Hwy 5 $400,000 Not Selected  Program limited by available funding.
65 I35E Pavement repair I35E from Hwy 5 to 10th St in St. Paul $29,604,018 2034 Projected poor pavement conditions.
65 Hwy 62 Medium mill and overlay from I-494 to Clearwater Dr $300,000 Not Selected  Program limited by available funding.
65 US10 Resurface road on Hwy 10 (Point Douglas Dr S) from Hwy 61 to the West end of the St Croix bridge in Hastings and Prescott $7,609,482 2033 Projected poor pavement conditions. 2020 RSL 10 years.
65 US169 Medium mill and overlay from Hwy 282 to Hwy 21 $1,400,000 Not Selected  Program limited by available funding.
65 US8 Medium mill and overlay from Tern Ave roundabout to Minnesota/Wisconsin State line $1,900,000 Not Selected  Program limited by available funding.
64 I35E Replace pavement on I-35E from north exit of Shepard Rd to Hwy 5 (W 7th St) and replace bridge 9534 over Shepard Rd and overlay bridge 62912 in St Paul   $18,700,000   2026   Poor pavement conditions.
64 Hwy 55 Resurface Road from Highway 52 to US 61 $19,500,000 Not Selected  Poor pavement conditions.
64 US12 Medium mill and overlay from Hennepin County Road 29 to Wayzata Blvd exit $3,000,000 Not Selected  Program limited by available funding.
63.5 Hwy 65 Resurface Hwy 65 from 53rd to Moore Lake Dr. in Fridley $7,086,744 2031 Poor pavement conditions.
63 Hwy 62 Medium mill and overlay from Portland Ave to 28th ave $1,800,000 Not Selected  Program limited by available funding.
63 US212 Medium mill and overlay from Tacoma Ave to Carver County Road 36 $2,700,000 Not Selected  Program limited by available funding.
63 US61 Medium mill and overlay from 70th St to Carver Ave $4,400,000 Not Selected  Program limited by available funding.
63 US61 Medium mill and overlay from Trailer Pk entrance to 170th St  $1,000,000 Not selected Program limited by available funding.
62 Hwy 41 Medium mill and overlay from Hwy 5 to Hwy 7 $1,100,000 Not selected Program limited by available funding.
62 Hwy 55 Medium mill and overlay from Pine Bend Trail to Hastings CL $3,500,000 Not Selected  Program limited by available funding.
62 Hwy 62 Medium mill and overlay from Clearwater to Tracy Ave $3,300,000 Not Selected  Program limited by available funding.
61 Hwy 62 Medium mill and overlay from Portland Ave bridge to .154 miles east of Portland bridge $200,000 Not Selected  Program limited by available funding.
61 Hwy 7 Minor CPR from Kings Dr to I-494 $800,000 Not Selected  Poor pavement conditions.
61 US12 Medium mill and overlay from Railroad bridge to 7th St $300,000 Not Selected  Program limited by available funding.
60 I694 Resurface I-694 from Dupont Ave to I-35W, and resurface I-694 bridges over TH65, Mississippi River, and TH 252 in New Brighton $70,187,280 2031 Projected poor pavement conditions.
60 Hwy 62 Reconstruct road, curb and gutter, guardrail, drainage, sidewalk, railing replacement and repair bridge #27521 on Hwy 62 from 28th Ave to 0.1 miles E of 43rd Ave in Mpls - TIED LET GROUP 10170   $25,500,000   2027, 2028   Poor pavement conditions. 
60 Hwy 77 Medium mill and overlay from Minnesota River bridge to I-494 $3,100,000 Not Selected  Program limited by available funding.
60 US212 Medium mill and overlay from Chaska Creek to Hwy 41 $1,700,000 Not Selected  Program limited by available funding.
59 I35W Medium mill and overlay from County Road C to Sunset Ave $15,100,000 Not Selected  Program limited by available funding.
59 Hwy 25 Resurface Hwy 25 from US 212 to Hwy 5 in Norwood Young America $3,597,000 2032 Projected poor pavement conditions. 2020 RSL 11 years.
59 Hwy 252 Medium mill and overlay from I-94 WB in Brooklyn Center to .4 miles north of I-94 $500,000 Not Selected  Program limited by available funding.
59 Hwy 36 Medium mill and overlay from Washington Ave to Hwy 95  $1,800,000 Not Selected  Program limited by available funding.
59 US10 Medium mill and overlay from Fairoak Ave to US169/Hwy 47 $900,000 Not Selected  Program limited by available funding.
59 US169 Medium mill and overlay from .1 miles north of Ash St to 1.2 miles north of Ash St $1,300,000 Not Selected  Program limited by available funding.
58 I35W Resurface road, replace bridge 6583, construct auxiliary lanes, construct additional southbound exit at CR 42, signal system, roadway lighting, and ADA improvements from I-35W/I-35E split to 0.4 miles north of Cliff Rd in Burnsville and replace bridge 9779 and 9780 and install cable median barrier on Hwy 13 and Construct additional SB exit ramp and roundabout from I-35W to Buck Hill Rd and Replace bridge 19863 at I35W and Burnsville Parkway in Burnsville and Install continuous street lighting on I-35W/Hwy 13 to I-35E in Burnsville    $97,220,000   2025, 2026   Mobility needs; bridge replacement coordination. 
58 US169 Medium mill and overlay from Elm Creek Blvd to US10 $1,400,000 Not Selected  Program limited by available funding.
58 US169 Medium mill and overlay from 4.5 miles north of Hwy 19 to 5.7 miles north of Hwy 19 $1,100,000 Not Selected  Program limited by available funding.
58 US212 Medium mill and overlay from 4 lane section to Chaska Creek $2,700,000 Not Selected  Program limited by available funding.
58 I35W Reconstruct and widen bituminous shoulders, construct bituminous crossovers and temporary drainage and on Hwy 35W from Hwy 35W/Hwy 35E split to 0.4 mi N of Cliff Rd and on Hwy13 at Hwy 35W   $2,766,360   2025   NA
57 US169 Medium mill and overlay from LeSueur/Scott County line to Hwy 19 $400,000 Not Selected  Program limited by available funding.
57 US61 Medium mill and overlay from RP163 to 250TH St $200,000 Not selected Program limited by available funding.
57 Hwy 62 Resurface roadway and bridges, improve ADA, install cable median barrier, signals on TH62 from 0.1 miles west TH13 to 5th Ave S in Mendota Heights   $13,255,000   2028   NA
56 Hwy 610 Medium mill and overlay from I-94 to Elm Creek Blvd $2,400,000 Not Selected  Program limited by available funding.
55 I694 Medium mill and overlay from Lexington Ave to Hwy 49 $4,600,000 Not Selected  Program limited by available funding.
55 Hwy 62 Medium mill and overlay from Clearwater Dr to .32 miles east of Clearwater $400,000 Not Selected  Program limited by available funding.
54 I494 Medium mill and overlay from US12 to I-94 $12,800,000 Not Selected  Program limited by available funding.
54 US10 Resurface road from Hwy 65 to the north junction I-35W - Future Project $7,500,000 Not selected Poor pavement conditions; bad longitudinal joints.
54 US212 Medium mill and overlay from .1 miles south of Hwy 62 to Hwy 62 $1,000,000 Not Selected  Program limited by available funding.
51 US52 Unbonded concrete overlay from Clayton to I-494 $43,300,000 Not Selected  Poor pavement conditions.
50 I35 Medium mill and overlay from Scott County road 2 to Hwy 50 $6,400,000 Not Selected  Program limited by available funding.
46 Hwy 55 Resurface Hwy 55 from the Wright-Hennepin county line to Fernbrook in Plymouth $28,710,000 2029 NA
45 I35 Medium mill and overlay from Hwy 95 to Chisago County Road 9 $6,700,000 Not Selected  Program limited by available funding.
43 I94 Medium mill and overlay from Mounds Blvd to Ramsey/Washington County line $6,800,000 Not Selected  Program limited by available funding.
43 Hwy 65 Repair road from 217th Ave to Anoka-Isanti County line $18,000,000 Not Selected  Repair early distresses.
41 Hwy 77 Resurface Hwy 77 (Cedar) from 138th St (Hwy 23) to the Dakota-Hennepin County line in Apple Valley    $62,184,000   2026, 2027   Poor pavement conditions. 
40 US8 Expand from two-lane undivided to four-lane divided roadway, signals, trail bridges on Hwy 8 from Chisago County line in Wyoming to Karmel Ave/Wyoming Ave in Chisago City and reconstruct Hwy 8 from I-35 to Chisago County line in Forest Lake and Resurface, drainage repair, construct pond from jct I-35 in Forest Lake to 0.1 miles west of Wyoming Ave in Chisago City, and construct left turn lane on Hwy 8 (Lake Blvd) at Hazel Ave and close 250th St at Hwy 8 in Wyoming Township and Construct J turn at Hale Ave and close Hazel Ave, Hamlet Ave, 250th St, and 14 driveway access points on Hwy 8 (Lake Blvd) in Wyoming Township    $80,962,000   2026, 2028   Coordination with County safety improvements. Poor pavement conditions. 
39 I35E Replace short segment of pavement either side of bridge 9532 $3,000,000 Not Selected  Poor pavement conditions. Coordinate with Shepard Rd bridge replacement.
39 I694 Major rehabilitation from Hwy 49 to Washington County Road 10 $18,400,000 Not Selected  Repair early distresses.
39 US12 Resurface road, lighting, drainage improvements, ADA, pier protection on bridges 27129 and 27130 on Hwy 12 (Wayzata Blvd) from 0.5 miles west Shoreline Dr in Wayzata to 0.5 miles east of I-494 in Wayzata and Minnetonka   $48,448,000   2026, 2027   Poor pavement conditions.
38 I94 Medium mill and overlay from Exit 207 to I494 $14,500,000 Not Selected  Program limited by available funding.
36.5 I694 Pavement rehab on I694 from 0.5 miles E Hwy 49 to Hwy 61 in Vadnais Heights and Little Canada $27,380,000 2034 NA
36 US12 Thin mill and overlay from the eastern Independence City limits to Hennepin County Road 29 $3,800,000 Not Selected  Poor pavement conditions.
36 US169 Medium mill and overlay from Valley View Rd to US 212/Hwy 62 $1,900,000 Not Selected  Program limited by available funding.
35 Hwy 55 Medium mill and overlay from General Mills Blvd to Schaper Rd $2,100,000 Not Selected  Program limited by available funding.
34 US169 Resurface road on Hwy 169 from the north end of Bloomington Ferry bridge to Anderson Lakes bridge in Eden Prairie $11,078,760 2033 Poor pavement conditions. 
33 I94 Medium mill and overlay from Wright/Hennepin County line $3,400,000 Not Selected  Program limited by available funding.
33 Hwy 25 Resurface road from US 169 to Minnesota River bridge in Belle Plaine $2,375,000 2032 Poor pavement conditions. 
33 US61 Resurface US 61 from 3rd St. to US 10 in Hastings $8,175,000 2032 Poor pavement conditions.
32.5 I694 Resurface road on Hwy 694 from Hwy 49 to Hwy 61 in Vadnais Heights and White Bear Lake $10,464,000 2033 Repair early distresses.
32 Hwy 280 Unbonded overlay from Como to I-35W $23,400,000 Not selected Poor pavement conditions.
32 US61 Medium mill and overlay from RP155 to 170th ST $200,000 Not selected Program limited by available funding.
31 Hwy 41 Repair Hwy 41 from County Hwy 61 to Hundertmark Rd in Chaska $16,977,840 2030 Poor pavement conditions.
31 Hwy 7 Repair road from W end of 494 bridge. to I-494    $500,000   Not Selected Poor pavement conditions.
29 I35E Medium mill and overlay from Cayuga to Little Canada Rd $7,700,000 Not Selected  Program limited by available funding.
29 I494 Medium mill and overlay from I-94/694 to Lake Dr $2,300,000 Not Selected  Program limited by available funding.
29 Hwy 610 Medium mill and overlay from Elm Creek Blvd to US 169 $2,700,000 Not Selected  Program limited by available funding.
29 Hwy 65 Medium mill and overlay from south of E Moore Lake Dr to Anoka County Road 10 $3,100,000 Not Selected  Program limited by available funding.
29 US10 Medium mill and overlay from Hwy 101 to Cleveland Ave $3,400,000 Not Selected  Program limited by available funding.
29 US61 Medium mill and overlay from 267th St to I35 $300,000 Not selected Program limited by available funding.
28.5 US169 Resurface TH 169 from CR15 to NE end of bridge 27624A in Shakopee   $50,782,100   2028, Future   Poor pavement conditions. 
28 I35E Medium mill and overlay from Ramsey County Road 96 to 80th St $10,600,000 Not Selected  Program limited by available funding.
27 I35W Medium mill and overlay from Sunset Ave to I35W/I35E $7,100,000 Not Selected  Program limited by available funding.
25 I35 Medium mill and overlay from I35W/E to US8 $6,400,000 Not Selected  Program limited by available funding.
25 I35 Medium mill and overlay from Chisago County Road 9 to Chisago/Pine County line $8,600,000 Not Selected  Program limited by available funding.
25 Hwy 610 Repair and resurface Hwy 610 from Mississippi River to Coon Rapids Blvd in Coon Rapids $19,620,000 2033 NA
23 I494 Medium mill and overlay from I94/694 to Tamarack Rd $800,000 Not Selected  Program limited by available funding.
23 US212 Resurface pavement on Hwy 212, Hwy 5 (W 78th St) from 0.37 miles east of Eden Prairie Rd to Hwy 212 and on Hwy 212 from 0.1 mile west of Eden Prairie Rd to 0.1 mile east of I494 in Eden Prairie    $6,741,000   2025   NA
21 US169 Medium mill and overlay from Hwy 19 to Hwy 25 $4,500,000 Not Selected  Program limited by available funding.
18 Hwy 316 Resurface pavement on Hwy 316 (Red Wing Blvd) from south jct Hwy 61 to Tuttle in Hastings and construct turn lanes at various locations on Hwy 316 (Red Wing Blvd) in Ravenna Township   $11,800,000   2025   Poor pavement conditions. 
18 Hwy 55 Resurface pavement, overlay bridge 27237, construct trail, guardrail, ADA and turn lane reconstruction at Dahlberg Drive on Hwy 55 (Olson Memorial Pkwy) from 0.2 miles west of Hwy 100 in Golden Valley to east end of bridge over BNSF tracks in Mpls    $7,200,000   2025   Poor pavement conditions. 
18 US169 Medium mill and overlay from 93rd Ave to Elm Creek Blvd $4,000,000 Not Selected  Program limited by available funding.
18 US169 Medium mill and overlay from 1.2 miles north of Hwy 282 to .27 miles north of Hwy 282 $5,900,000 Not Selected  Program limited by available funding.
17.5 Hwy 41 Resurface Hwy 41 from 0.17 mi S of Hundermark to 0.23 mi N of Pioneer Trail in Chaska $10,428,131 2034 RQI does not match on the ground conditions
17.2 US52 Resurface pavement, replace signs and mark pavement on TH52 from Belvidere St to I94 in St Paul    $2,300,000   2025   NA
17 I35E Medium mill and overlay from County Road E to County Road 96 $2,300,000 Not Selected  Program limited by available funding.
17 Hwy 55 Resurface Hwy 55 from County Road 63 to US 52 in Eagan and Inver Grove Heights $9,170,000 2032 Poor pavement conditions.
17 US52 Resurface US 52 from Hwy 55 from County Road 63 in Inver Grove Heights $9,156,000 2032 Poor pavement conditions.
16.5 Hwy 252 Resurface Hwy 252 from I-94 to 85th Street in Brooklyn Center and Brooklyn Park $11,118,000 2033 Poor pavement conditions. Coordination with 252 CoC project.
15 US169 Medium mill and overlay from Hwy 25 to Ash St $1,800,000 Not Selected  Program limited by available funding.
15 US212 Repair road from Highway 41 to County Rd. 4 in Chaska and Eden Prairie $51,573,104 2034 NA
11.5 US61 Resurface Hwy 61 from Hwy 97 to N of Hwy 8 in Forest Lake $6,698,268 2029 Poor pavement conditions.
11 I35E Medium mill and overlay from  south of I-35W to I35E/W $1,300,000 Not Selected  Program limited by available funding.
5 Hwy 55 Resurface roadway, sidewalk, ADA and signal replacement on TH 55 west of BNSF bridge in Golden Valley to I-94 in Mpls. Resurface TH55 bridge 27785 over I-94 and replace bridge 5908 over Bassett Creek   $19,158,000   2028   Poor pavement conditions. Frontage road and ADA needs.

Previous years

View more detailed scores (Excel).

Score Route Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
96 Hwy 100 Resurface road, repair 12 bridges, curb and gutter repair, access removal, ramp realignment and removal of bridge 27042 on Hwy 100 from under pedestrian bridge/exit Cedar Lake Rd in St Louis Park to I-694 in Brooklyn Center    $49,440,000   2027, Future   Poor pavement conditions; preventive maintenance. 
91 US169 Medium mill and overlay from Hwy 55 to 77th Ave 7800000 Not Selected  Program limited by available funding.
91 US52 Medium mill and overlay from I-494 to Lafayette bridge 5100000 Not Selected  Program limited by available funding.
89 US212 Reconstruct road from I-494 to Hwy 62    $21,615,000   2033 Poor pavement conditions.
89 US212 Hwy 212 from County Road 4 to I-494 resurfacing project.   $24,267,842   2033 NA
85 US169 Resurface Hwy 169 from CSAH 15 to Ferry Bridges   $27,588,542   2028 Poor pavement conditions. 
84 US10 Resurface Hwy 10 from US169/Hwy 47 to Creek Medows Bridge    $15,000,000   2032 Projected poor pavement conditions.
83 US169 Medium mill and overlay from Hwy 62 to Hwy 55 $6,300,000 Not Selected  Program limited by available funding.
82 Hwy 55 Repair pavement and bridge culverts 6732 and 6745, traffic management system and add turn lane on Hwy 55 (Olson Memorial Hwy) from Old Rockford Rd in Plymouth to just east General Mills Blvd in Golden Valley    $19,080,000   2024   Poor pavement conditions. 
82 Hwy 55 Thick mill and overlay from Fernbrook to General Mills Blvd $10,200,000 Not Selected  Poor pavement conditions.
81 US169 Resurface road from 77th Ave N to 101st Ave N 4400000 Not Selected  Poor pavement conditions.
80 Hwy 62 Resurface road from Penn Ave to Portland Ave $11,000,000 Not Selected  Repair early distresses.
80 US12 Resurface US 12 from the Wright/Hennepin County line to County Road 29    $9,602,500   2028.0000 Poor pavement conditions.
80 US52 Medium mill and overlay from Hwy 65 to University Ave 1600000 Not selected Program limited by available funding.
80 US52 Resurface US 52 from Clayton to south of Inver Grove Trail; replace 2 and resurface 2 US 52 bridges over the UP Railroad, and replace the Hwy 55 bridge over US 52.   $36,210,000   2032 Poor pavement conditions.
79 US10 Thin mill and overlay from Hwy 65 to I35W 9600000 Not Selected Poor pavement conditions; bad longitudinal joints.
78 US10 Medium mill and overlay from US61 to .1 miles east of US61 $100,000 Not selected Program limited by available funding. Short piece of 4 lane east of USTH 61. Recently received a UTBWC surface treatment.
78 US169 Medium mill and overlay and CPR from Hwy 21 to 173rd St W 12600000 Not Selected Poor pavement conditions.
78 US169 Repair pavement on Hwy 169 (Johnson Memorial Hwy) from Hwy 21 (Broadway St N) to 0.54 mile west of CR 15 (Marystown Rd) in Shakopee and modify access on Hwy 169 (Johnson Memorial Hwy) from Hwy 21 (Broadway St N) to Bluff Dr in Shakopee    $9,921,775   2024   Poor pavement conditions. 
77 US8 Resurface road from W Wyoming Ave to Tern Ave    $24,490,000   2032 Poor pavement conditions.
76 Hwy 100 Medium mill and overlay from I-494 to Cedar Lake Bridge 10900000 Not Selected  RQI does not reflect on the ground conditions
76 Hwy 610 Medium mill and overlay from Hwy 252 to Mississippi River Bridge  1000000 Not Selected  Program limited by available funding.
76 US10 Medium mill and overlay from Foley Blvd to Hwy 56 $4,100,000 Not Selected  RQI does not reflect on the ground conditions
76 US169 Medium mill and overlay from 77th Ave to 93rd Ave in Osseo $5,600,000 Not Selected Poor pavement conditions.
76 US212 Repair and resurface road from Mcleod/Carver County line to Hwy 5   $4,100,000   2032 NA
76 US52 Medium mill and overlay from Lafayette bridge to I-94 200000 Not Selected  Program limited by available funding.
74 Hwy 25 Medium mill and overlay from Hwy 5 to Hwy 7 3900000 Not Selected  Program limited by available funding.
74 Hwy 62 Medium mill and overlay from Tracy ave bridge to Penn Ave Bridge $3,200,000 Not Selected  Program limited by available funding.
74 US10 Resurface road, drainage on Hwy 10 from Cleveland/Jarvis St in Elk River to 0.5 miles W to Ramsey Blvd in Anoka and intersection improvements on Hwy 10 from Cleveland/Jarvis St in Elk River to 0.5 miles W to Ramsey Blvd in Anoka    $10,422,000   2027   Poor pavement conditions.
73 Hwy 62 Medium mill and overlay from 43rd Ave to Mendota Bridge $1,600,000 Not Selected  Program limited by available funding.
73 US10 Medium mill and overlay from Cleveland RT/Jarvis LT to Fairoak Ave $14,800,000 Not Selected  Poor pavement conditions.
73 US10 Medium mill and overlay from I-35W to I694 $3,000,000 Not selected RQI does not match on the ground conditions
73 US52 Medium mill and overlay from Dakota County Road 42 to Clayton Ave 800000 Not Selected  Program limited by available funding.
72 Hwy 280 Repair pavement, guardrail, rehab 13 bridges on Hwy 280 from junction with I-94 in St Paul to junction with I-35W in Roseville and close median on Hwy 280 at Broadway in Lauderdale and install signals at Kosata Ave and ramps with Energy Park Dr in St Paul    $32,476,000   2026, 2027   Poor pavement conditions; coordinate with bridge work. 
72 US169 Medium mill and overlay from Anderson Lakes Pkwy to Valley View Rd $1,500,000 Not Selected  Program limited by available funding.
72 US169 Medium mill and overlay from Catrerbury rd to Valley View Rd $8,600,000 Not Selected  Program limited by available funding.
71 Hwy 25 Medium mill and overlay from Scott County line to Hwy 5 $7,100,000 Not selected RQI does not match on the ground conditions
71 US10 Medium mill and overlay from east of 114th Ave NW to east Foley Blvd $2,200,000 Not Selected  RQI does not reflect on the ground conditions
70 Hwy 101 Resurface road from Hwy 5 (W 78th St) to CSAH 62/Townline Rd, resurface road, drainage repairs and ADA improvements on Hwy 101 (W 192nd Ave) from Hwy 5 to Townline Rd in Chanhassen/Eden Prairie    $1,887,000   2024   Poor pavement conditions. 
70 US12 Medium mill and overlay from County Road 90 to eastern Independence City limits $400,000 Not Selected  Program limited by available funding.
70 US52 US 52 from Inver Grove Trail to Hwy 55 resurfacing and Hwy 55 bridge over US 52 resurfacing.   $5,010,000   2032 NA
69 Hwy 252 Medium mill and overlay from 85th to Hwy 610 $1,100,000 Not Selected  Program limited by available funding.
69 Hwy 316 Medium mill and overlay from Southern to northern limits $7,600,000 Not selected Poor pavement conditions.
69 Hwy 316 Resurface pavement on Hwy 316 (Red Wing Blvd) from south jct Hwy 61 to Tuttle in Hastings and construct turn lanes at various locations on Hwy 316 (Red Wing Blvd) in Ravenna Township   $6,907,000   2024   Poor pavement conditions. 
69 Hwy 62 Medium mill and overlay from I-35E to US52 3500000 Not selected Program limited by available funding.
69 US212 Medium mill and overlay from Hwy 5 to Tacoma Ave 3500000 Not Selected  Program limited by available funding.
69 US52 Medium mill and overlay from Goodhue/Dakota County Line to County Road 86 2300000 Not Selected  Program limited by available funding.
68 Hwy 101 Medium mill and overlay from NB split with US169 to SB merge with US169  $3,400,000 Not Selected  Program limited by available funding.
68 Hwy 252 Hwy 252 from I-94 to 85th Street, resurfacing project.   $8,500,000   2033 Poor pavement conditions. Coordination with 252 CoC project.
68 US169 Medium mill and overlay from Elm creek Blvd to Mississippi River Bridge $500,000 Not Selected  Program limited by available funding.
68 US212 Medium mill and overlay from 2.2 miles east of Hwy 284 to 4 lane section 2200000 Not Selected  Program limited by available funding.
67 Hwy 41 Medium mill and overlay from US169 to Pioneer Trail 1200000 Not Selected  Program limited by available funding.
67 US212 Repair road from Highway 41 to County Rd. 4    $18,104,167   2032 Preventive maintenance.
66 Hwy 36 Resurface pavement on Hwy 36 from Jct I-35W in Roseville to just east Edgerton in Maplewood/Little Canada and extend auxiliary lane, guardrail replacement, ADA improvements and reconstruct ramp at I-35W SB/Cleveland Ave to Hwy 36 EB    $13,814,000   2024   Poor pavement conditions; maintenance liability. 
66 Hwy 610 Repair road from US 169 to Mississippi River $20,000,000 Not Selected  Projected poor pavement conditions.
66 US212 Meduim mill and overlay from Hwy 5 to .4 miles east of Hwy 5 400000 Not Selected  Program limited by available funding.
65 Hwy 55 Resurface roadway, sidewalk ADA and signal replacement on Hwy 55 west of BNSF bridge to I-94. Resurface Hwy 55 bridges over I-94 and Replace Hwy 55 over Bassett Creek.   $11,045,888   2028 Poor pavement conditions. Frontage road and ADA needs.
65 Hwy 62 Medium mill and overlay from I-494 to Clearwater Dr 300000 Not Selected  Program limited by available funding.
65 US10 Resurface road from US61 to the West end of the St Croix bridge    $5,817,647   2033 Projected poor pavement conditions. 2020 RSL 10 years.
65 US169 Medium mill and overlay from Hwy 282 to Hwy 21 $1,400,000 Not Selected  Program limited by available funding.
65 US8 Medium mill and overlay from Tern Ave roundabout to Minnesota/Wisconsin State line 1900000 Not Selected  Program limited by available funding.
64 Hwy 55 Resurface Road from Highway 52 to US 61 19500000 Not Selected  Poor pavement conditions.
64 Hwy 610 Repair and resurface Hwy 610 from Mississippi River to Coon Rapids Blvd   $15,000,000   2033 NA
64 US12 Medium mill and overlay from Hennepin County Road 29 to Wayzata Blvd exit 3000000 Not Selected  Program limited by available funding.
63 Hwy 55 Hwy 55 from County Road 63 to US 52 resurfacing project.   $7,000,000   2032.0000 Poor pavement conditions.
63 Hwy 62 Medium mill and overlay from Portland Ave to 28th ave $1,800,000 Not Selected  Program limited by available funding.
63 US212 Medium mill and overlay from Tacoma Ave to Carver County Road 36 2700000 Not Selected  Program limited by available funding.
62 Hwy 41 Medium mill and overlay from Hwy 5 to Hwy 7 $1,100,000 Not selected Program limited by available funding.
62 Hwy 55 Medium mill and overlay and ADA work from Hwy 100 to Railroad overpass 3400000 Not Selected  Poor pavement conditions.
62 Hwy 55 Medium mill and overlay from Pine Bend Trail to Hastings CL 3500000 Not Selected  Program limited by available funding.
62 Hwy 55 Resurface pavement, overlay bridge 27237, construct trail, ADA and turn lane reconstruction at Dahlberg Drive on Hwy 55 (Olson Memorial Pkwy) from 0.2 miles west of Hwy 100 in Golden Valley to west end of bridge over BNSF tracks in Mpls    $6,407,000   2025 Poor pavement conditions. 
62 Hwy 62 Medium mill and overlay from Clearwater to Tracy Ave $3,300,000 Not Selected  Program limited by available funding.
61 Hwy 62 Medium mill and overlay from Portland Ave bridge to .154 miles east of Portland bridge $200,000 Not Selected  Program limited by available funding.
61 US12 Medium mill and overlay from Railroad bridge to 7th St $300,000 Not Selected  Program limited by available funding.
60 US212 Medium mill and overlay from Chaska Creek to Hwy 41 1700000 Not Selected  Program limited by available funding.
59 Hwy 25 Resurface road from US 212 to Hwy 5   $2,750,000   2032 Projected poor pavement conditions. 2020 RSL 11 years.
59 Hwy 252 Medium mill and overlay from I-94 WB in Brooklyn Center to .4 miles north of I-94 500000 Not Selected  Program limited by available funding.
59 Hwy 36 Medium mill and overlay from Washington Ave to Hwy 95  $1,800,000 Not Selected  Program limited by available funding.
59 US10 Medium mill and overlay from Fairoak Ave to US169/Hwy 47 $900,000 Not Selected  Program limited by available funding.
59 US169 Medium mill and overlay from .1 miles north of Ash St to 1.2 miles north of Ash St $1,300,000 Not Selected  Program limited by available funding.
58 US169 Medium mill and overlay from 4.5 miles north of Hwy 19 to 5.7 miles north of Hwy 19 $1,100,000 Not Selected  Program limited by available funding.
58 US169 Medium mill and overlay from Elm Creek Blvd to US10 $1,400,000 Not Selected  Program limited by available funding.
58 US212 Medium mill and overlay from 4 lane section to Chaska Creek 2700000 Not Selected  Program limited by available funding.
57 Hwy 62 Resurface Hwy 62 from Lexington Ave to Northbound 35E Ramp.   $3,044,445   2028 Poor pavement conditions.
57 Hwy 62 Repair pavement on Hwy 62 between Hwy 13 and Lexington Ave in Mendota Heights   $2,650,826   2024   Poor pavement conditions. 
57 US169 Medium mill and overlay from LeSueur/Scott County line to Hwy 19 $400,000 Not Selected  Program limited by available funding.
56 Hwy 610 Medium mill and overlay from I-94 to Elm Creek Blvd $2,400,000 Not Selected  Program limited by available funding.
55 Hwy 121 Medium mill and overlay from I35W to Pedestrian bridge 300000 Not Selected  Program limited by available funding.
55 Hwy 62 Medium mill and overlay from Clearwater Dr to .32 miles east of Clearwater $400,000 Not Selected  Program limited by available funding.
54 US10 Resurface road from Hwy 65 to the north junction I-35W - Future Project $7,500,000 Not selected Poor pavement conditions; bad longitudinal joints.
54 US212 Medium mill and overlay from .1 miles south of Hwy 62 to Hwy 62 1000000 Not Selected  Program limited by available funding.
53 Hwy 62 Reconstruct road, curb and gutter, guardrail, drainage, sidewalk, railing replacement and repair bridge #27521 on Hwy 62 from 28th Ave to Hwy 55 in Mpls    $22,904,000   2027, Future   Poor pavement conditions. 
46 Hwy 101 Repair and resurface road, update guardrail and median barrier, signal replacement, ADA curb ramps, drainage, turn lane extension and pork chop island realignment on Hwy 101 from I-94 in Rogers to CR 38 (70th St NE) in Otsego    $12,674,000   2027 Poor pavement conditions. 
46 Hwy 55 Resurface road from the Wright-Hennepin county line to Fernbrook   $21,948,000   2029 Poor pavement conditions.
45 US169 Resurface road from the north end of Bloomington Ferry bridge to Anderson Lakes bridge    $8,470,000   2033 Poor pavement conditions. 
40 US8 Expand from two-lane undivided to four-lane divided roadway, signals, trail on Hwy 8 from Chisago County line in Wyoming to Karmel Ave/Wyoming Ave in Chisago City and reconstruct Hwy 8 from I-35 to Chisago County line in Forest Lake    $80,000,000   2024   NA
40 US8 Resurface, drainage repair, construct pond from jct I-35 in Forest Lake to 0.1 miles west of Wyoming Ave in Chisago City, and construct left turn lane on Hwy 8 (Lake Blvd) at Hazel Ave and close 250th St at Hwy 8 in Wyoming Township    $14,275,000   2025   Coordination with County safety improvements. Poor pavement conditions. 
36 US12 Resurface road, lighting, drainage improvements, ADA, pier protection on bridges 27129 and 27130 on Hwy 12 (Wayzata Blvd) from 0.5 miles west Shoreline Dr in Orono to 0.5 miles east I-494 in Minnetonka    $50,081,000   2026, 2027   Poor pavement conditions.
36 US169 Medium mill and overlay from Valley View Rd to US 212/Hwy 62 1900000 Not Selected  Program limited by available funding.
35 Hwy 55 Medium mill and overlay from General Mills Blvd to Schaper Rd $2,100,000 Not Selected  Program limited by available funding.
33 Hwy 25 Resurface road from US 169 to Minnesota River bridge    $2,375,000   2032 Poor pavement conditions. 
31 Hwy 41 Repair road from Count Hwy 61 to Hundertmark Rd    $12,980,000   2030 Poor pavement conditions.
29 Hwy 610 Medium mill and overlay from Elm Creek Blvd to US 169 2700000 Not Selected  Program limited by available funding.
29 US10 Medium mill and overlay from Hwy 101 to Cleveland Ave $3,400,000 Not Selected  Program limited by available funding.
21 US169 Medium mill and overlay from Hwy 19 to Hwy 25 4500000 Not Selected  Program limited by available funding.
18 US169 Major rehabilitation from Scott County Road 16 to Canterbury Rd 13100000 Not Selected Poor pavement conditions.
18 US169 Medium mill and overlay from 1.2 miles north of Hwy 282 to .27 miles north of Hwy 282 $5,900,000 Not Selected  Program limited by available funding.
18 US169 Medium mill and overlay from 93rd Ave to Elm Creek Blvd 4000000 Not Selected  Program limited by available funding.
15 US169 Medium mill and overlay from Hwy 25 to Ash St $1,800,000 Not Selected  Program limited by available funding.

View more detailed scores (Excel).

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
29 Hwy 610 Medium mill and overlay from Elm Creek Blvd to US 169 $2,700,000 Not Selected  Program limited by available funding.
31 Hwy 41 Repair road from Count Hwy 61 to Hundertmark Rd $12,980,000 2032 Poor pavement conditions.
32 Hwy 280 Unbonded overlay from Como to I-35W $23,400,000 2027 Poor pavement conditions.
33 Hwy 25 Resurface road from US 169 to Minnesota River bridge $2,400,000 2031 Poor pavement conditions. 
35 Hwy 55 Medium mill and overlay from General Mills Blvd to Schaper Rd $2,100,000 Not Selected  Program limited by available funding.
46 Hwy 55 Resurface road from the Wright-Hennepin county line to Fernbrook $22,000,000 2028 Poor pavement conditions.
53 Hwy 62 Resurface road from 28th Ave to Hwy 55 $10,000,000 2027 Poor pavement conditions. 
55 Hwy 62 Medium mill and overlay from Clearwater Dr to .32 miles east of Clearwater $400,000 Not Selected  Program limited by available funding.
56 Hwy 610 Medium mill and overlay from I-94 to Elm Creek Blvd $2,400,000 Not Selected  Program limited by available funding.
57 Hwy 62 Repair pavement on Hwy 62 between Hwy 13 and 0.2 miles east of I-35E in Mendota Heights $5,172,000 2024 Poor pavement conditions. 
59 Hwy 25 Resurface road from US 212 to Hwy 5 $2,600,000 2031 Projected poor pavement conditions. 2020 RSL 11 years.
59 Hwy 252 Medium mill and overlay from I-94 WB in Brooklyn Center to .4 miles north of I-94 $500,000 Not Selected  Program limited by available funding.
59 Hwy 36 Medium mill and overlay from Washington Ave to Hwy 95  $1,800,000 Not Selected  Program limited by available funding.
61 Hwy 62 Medium mill and overlay from Portland Ave bridge to .154 miles east of Portland bridge $200,000 Not Selected  Program limited by available funding.
62 Hwy 41 Resurface Hwy 41 from 0.23 miles north of Pioneer Trl in Chaska to Hwy 5 (Arboretum Blvd) in Chanhassen $1,834,000 2023 Poor pavement conditions. 
62 Hwy 41 Medium mill and overlay from Hwy 5 to Hwy 7 $1,100,000 Not selected Program limited by available funding.
62 Hwy 55 Resurface pavement, construct trail and turn lane reconstruction at Dahlberg Drive on Hwy 55 (Olson Memorial Pkwy) from 0.2 miles west of Hwy 100 in Golden Valley to west end of bridge over BNSF tracks in Mpls $3,337,000 2025 Poor pavement conditions. 
62 Hwy 55 Medium mill and overlay from Pine Bend Trail to Hastings CL $3,500,000 Not Selected  Program limited by available funding.
62 Hwy 62 Medium mill and overlay from Clearwater to Tracy Ave $3,300,000 Not Selected  Program limited by available funding.
63 Hwy 55 Repair road from County Rd 63 to US 52 $7,000,000 2028 Poor pavement conditions.
63 Hwy 62 Medium mill and overlay from Portland Ave to 28th ave $1,800,000 Not Selected  Program limited by available funding.
64 Hwy 55 Resurface Road from Highway 52 to US 61 $19,500,000 2030 Poor pavement conditions.
64 Hwy 610 Repair and resurface Hwy 610 from Mississippi River to Coon Rapids Blvd $15,000,000 2028 NA
65 Hwy 55 Resurface roadway, sidewalk ADA and signal replacement on Hwy 55 west of BNSF bridge to I-94 $5,800,000 2026 Poor pavement conditions. Frontage road and ADA needs.
65 Hwy 62 Medium mill and overlay from I-494 to Clearwater Dr $300,000 Not Selected  Program limited by available funding.
66 Hwy 36 Resurface pavement on Hwy 36 from Jct I-35W in Roseville to just east Edgerton in Maplewood/Little Canada and extend auxiliary lane and reconstruct ramp at I-35W SB/Cleveland Ave to Hwy 36 EB $12,352,000 2025 Poor pavement conditions; maintenance liability. 
66 Hwy 610 Repair road from US 169 to Mississippi River $20,000,000 2031 Projected poor pavement conditions.
67 Hwy 41 Medium mill and overlay from US169 to Pioneer Trail $1,200,000 Not Selected  Program limited by available funding.
68 Hwy 252 Resurface road from I-94 to 85th St $8,500,000 2031 Poor pavement conditions. Coordination with 252 CoC project.
69 Hwy 252 Medium mill and overlay from 85th to Hwy 610 $1,100,000 Not Selected  Program limited by available funding.
69 Hwy 316 Resurface pavement on Hwy 316 (Red Wing Blvd) from south jct Hwy 61 to Tuttle in Hastings and widen shoulder at various locations on Hwy 316 (Red Wing Blvd) in Ravenna Township $6,222,000 2025 Poor pavement conditions. 
69 Hwy 62 Medium mill and overlay from I-35E to US52 $3,500,000 Not selected Program limited by available funding.
71 Hwy 25 Medium mill and overlay from Scott County line to Hwy 5 $7,100,000 Not selected RQI does not match on the ground conditions
72 Hwy 280 Repair pavement, guardrail, rehab 13 bridges on Hwy 280 from junction with I-94 in St Paul to junction with I-35W in Roseville and close median on Hwy 280 at Broadway in Lauderdale and install signals at Kosata Ave and ramps with Energy Park Dr in St Paul $25,763,000 2026, Future Poor pavement conditions; coordinate with bridge work. 
73 Hwy 62 Medium mill and overlay from 43rd Ave to Mendota Bridge $1,600,000 Not Selected  Program limited by available funding.
74 Hwy 25 Medium mill and overlay from Hwy 5 to Hwy 7 $3,900,000 Not Selected  Program limited by available funding.
74 Hwy 62 Medium mill and overlay from Tracy ave bridge to Penn Ave Bridge $3,200,000 Not Selected  Program limited by available funding.
75 Hwy 41 Resurface road including pavement marking and guardrail work at Hwy 41 intersection with Peavey Rd in Chaska $82,000 2023 NA
76 Hwy 100 Medium mill and overlay from I-494 to Cedar Lake Bridge $10,900,000 Not Selected  RQI does not reflect on the ground conditions
76 Hwy 610 Medium mill and overlay from Hwy 252 to Mississippi River Bridge  $1,000,000 Not Selected  Program limited by available funding.
80 Hwy 62 Resurface road from Penn Ave to Portland Ave $11,000,000 2032 Repair early distresses.
82 Hwy 55 Repair pavement and bridge culverts 6732 and 6745 and add turn lane on Hwy 55 (Olson Memorial Hwy) from Old Rockford Rd in Plymouth to just east General Mills Blvd in Golden Valley $18,102,000 2024 Poor pavement conditions. 
96 Hwy 100 Resurface road from the Cedar Lake Rd to I-694 $18,000,000 2027 Poor pavement conditions; preventive maintenance. 

View more detailed scores (Excel).

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
95 I94 Medium mill and overlay from Nicollet Ave Bridge to Western Ave $53,300,000 2031 Projected poor pavement conditions.
95 I494 Minor rehabilitation from France Ave to US12 $24,900,000 2029 Preventive maintenance.
94 I35E Unbonded overlay from I35W/E to Lone Oak Rd $83,500,000 2031 Projected poor pavement conditions. SP1982-207
94 I694 Minor rehabilitation from Washington County Road 49 to US61 $12,000,000 2031 Repair early distresses.
93 I35E Medium mill and overlay from Lone Oak Rd to Bridge over Marie Ave  $21,200,000 2028 Projected poor pavement conditions.
91 US169 Medium mill and overlay from Hwy 55 to 77th Ave $7,800,000 Not Selected  Program limited by available funding.
91 I494 Major rehabilitation from Minnesota River Bridge to 24th Ave  $12,800,000 2023 Poor pavement conditions. Coordinate with 494 Corridors of Commerce project. SP 2785-433.
91 US52 Medium mill and overlay from I-494 to Lafayette bridge $5,100,000 Not Selected  Program limited by available funding.
90 I94 Medium mill and overlay from I-494 to Nicollet Ave bridge $27,400,000 Not Selected  RQI does not reflect on the ground conditions
90 I494 Medium mill and overlay from 24th Ave to France Ave $29,400,000 2027 Poor pavement conditions. Coordinate with 494 Corridors of Commerce project. 1785-424
90 I35E Minor rehabilitation from Little Canada Road to Ramsey County Road E bridge  $12,000,000 2031 Repair early distresses.
90 I35W Medium mill and overlay from Hwy 13 to 106th St $4,000,000 Not Selected  Construction of I-35W River Crossing at time of DIV run, bypass pavement is rough.
90 I35W Medium mill and overlay from 4th St bridge to Ramsey County Road C $8,000,000 Not Selected  RQI does not reflect on the ground conditions
88 I94 Major rehabilitation from Western Ave to Mounds Blvd $28,500,000 2022 Very bad pavement condition; extra maintenance required. SP 6283-247.
88 I494 Medium mill and overlay from 5th Ave to Dakota/Hennepin County Line $13,600,000 Not Selected  RQI does not reflect on the ground conditions
88 I394 Medium mill and overlay from Hwy 100 to Washington Ave N $3,200,000 Not Selected  Recent major rehab. Low RQI attributed largely to high percentage of bridge decks. Also, after a recent lane reconfiguration of WB, part of the outside lane is on rough bituminous shoulder.
86 I394 Thin mill and overlay from I-494 to Hwy 100 $26,800,000 2029 Projected poor pavement conditions.
85 I494 Medium mill and overlay from Hardman bridge to 5th Ave $2,200,000 Not Selected  RQI does not reflect on the ground conditions
85 I35E Major rehabilitation from 10th St Bridge to University ave Bridge $1,100,000 2022 Poor pavement conditions. SP 6283-247.
85 I35W Medium mill and overlay from 27th St to Washington Ave Bridge  $8,300,000 2029 Projected poor pavement conditions.
83 I94 Unbonded concrete overlay from Ramsey/Washington County Line to west end of St Croix River bridge $117,800,000 2023 Poor pavement conditions. SP 8282-132.
83 US169 Medium mill and overlay from Hwy 62 to Hwy 55 $6,300,000 Not Selected  Program limited by available funding.
83 I35W Minor rehabilitation from 66th St to 42nd St bridge $5,700,000 2031 Repair early distresses.
83 I694 Medium mill and overlay from I-494/694 to Lexington Ave $2,900,000 Not Selected  This segment consists of older concrete pavement with recent CPR and fairly new UBOLs. 2020 RQI is very good to excellent. Minor CPR is ongoing due to dowel bar issues.
82 Hwy 55 Thick mill and overlay from Fernbrook to General Mills Blvd $10,200,000 2024 Poor pavement conditions. SP 2723-144.
81 Hwy 7 Medium mill and overlay from Six mile creek to Division St $5,800,000 Not Selected  Program limited by available funding. Recent resurfacing project. Construction in progress at time of DIV run. Roughness at intersection contribute to poor ride.
81 I494 Medium mill and overlay from Tamarack bridge to Hardman bridge $6,100,000 Not Selected  RQI does not reflect on the ground conditions
81 I35W Medium mill and overlay from Washington Ave bridge to 4th St Bridge $1,600,000 Not Selected  This is new pavement but is predominantly comprised of St. Anthony Falls bridge deck. 2020 RQI is excellent.
79 I35E Unbonded overlay from I35W/E to Lone Oak Rd $76,700,000 2030 Projected poor pavement conditions. SP1982-207
79 US10 Thin mill and overlay from Hwy 65 to I35W $9,600,000 2027 Poor pavement conditions; bad longitudinal joints.
78 Hwy 7 Medium mill and overlay from Shady Oak Rd to Texas Ave $3,000,000 Not Selected  RQI does not reflect on the ground conditions
78 Hwy 65 Thin mill and overlay from Bunker Lake Rd to 217th Ave $5,100,000 2024 Poor pavement conditions. SP 0208-165.
78 US169 Medium mill and overlay and CPR from Hwy 21 to 173rd St W $12,600,000 2024 Poor pavement conditions. SP 7009-085.
78 I35W Medium mill and overlay from 42nd st bridge to Chicago Ave Bridge $6,500,000 Not Selected  Construction of Lake St project at time of DIV run, bypass pavement is rough.
77 US61 Medium mill and overlay from Carver Ave to I-94 $23,100,000 2030 Poor pavement conditions.
77 Hwy 610 NA $2,300,000 Not Selected  Program limited by available funding.
77 I35 Medium mill and overlay from US 8 to Hwy 95 $15,700,000 Not Selected  Program limited by available funding. Proposed thin overlay within next few years.
76 US169 Medium mill and overlay from 77th Ave to 93rd Ave in Osseo $5,600,000 2028 Poor pavement conditions.
76 Hwy 610 Medium mill and overlay from Hwy 252 to Mississippi River Bridge  $1,000,000 Not Selected  Program limited by available funding.
76 US52 Medium mill and overlay from Lafayette bridge to I-94 $200,000 Not Selected  Program limited by available funding.
76 US10 Medium mill and overlay from Foley Blvd to Hwy 56 $4,100,000 Not Selected  RQI does not reflect on the ground conditions
76 Hwy 100 Medium mill and overlay from Cedar Lake Bridge to I-894  $31,900,000 2027 Poor pavement conditions; preventive maintenance. SP 2735-212
76 Hwy 100 Medium mill and overlay from I-494 to Cedar Lake Bridge $10,900,000 Not Selected  RQI does not reflect on the ground conditions. 
75 Hwy 65 Medium mill and overlay from Anoka County Road 10 to Bunker Lake blvd $5,400,000 2024 Poor pavement conditions. SP 0207-110.
75 I35E Medium mill and overlay from University Ave to Cayuga/Railroad Bridge $2,100,000 Not Selected  Program limited by available funding. Section is predominantly bridge decks.
74 Hwy 62 Medium mill and overlay from Tracy ave bridge to Penn Ave Bridge $3,200,000 Not Selected  Program limited by available funding.
74 US10 Whitetop overlay from US169/Hwy 47 to Creek Meadows bridge $21,600,000 2030 Projected poor pavement conditions.
74 Hwy 25 Medium mill and overlay from Hwy 5 to Hwy 7 $3,900,000 Not Selected  Program limited by available funding.
74 Hwy 13 Medium mill and overlay from Hwy 13 to Dakota Ave $700,000 Not Selected  Program limited by available funding.
73 Hwy 7 Medium mill and overlay from Texas Ave to Railroad Bridge  $700,000 Not Selected  RQI does not reflect on the ground conditions
73 Hwy 62 Medium mill and overlay from 43rd Ave to Mendota Bridge $1,600,000 Not Selected  Program limited by available funding.
73 Hwy 65 Minor rehabilitation from 217th Ave to Anoka/Isanti County line $4,900,000 2029 Repair early distresses.
73 US212 Minor rehabilitation from Hennepin County Road 4 to I-494 $13,200,000 2027 Preventive maintenance.
73 Hwy 55 Medium mill and overlay from Mendota Bridge to Argenta Trail $11,600,000 2022 Poor pavement conditions. SP 1909-099.
73 US52 Medium mill and overlay from Dakota County Road 42 to Clayton Ave $800,000 Not Selected  Program limited by available funding.
73 US10 Medium mill and overlay from Cleveland RT/Jarvis LT to Fairoak Ave $14,800,000 2027 Poor pavement conditions.
73 I694 Medium mill and overlay from County Road 10 to Anoka Isanti County Line $1,000,000 Not Selected  Under construction at time of DIV run. New concrete pavement at system interchange (94/494/694).
72 US61 Medium mill and overlay from US 10 to 70th St $8,500,000 Not Selected  Program limited by available funding.
72 US169 Medium mill and overlay from Catrerbury rd to Valley View Rd $8,600,000 Not Selected  Program limited by available funding.
72 US169 Medium mill and overlay from Anderson Lakes Pkwy to Valley View Rd $1,500,000 Not Selected  Program limited by available funding.
72 Hwy 610 NA $1,500,000 Not Selected  Program limited by available funding.
72 I35E Thin mill and overlay from bridge 9532 to 10th St bridge $5,700,000 2028 Projected poor pavement conditions.
72 Hwy 55 Medium mill and overlay from Wright/Hennepin County Line to Fernbrook $21,500,000 2027 Poor pavement conditions.
72 Hwy 280 Major rehabilitation from I-94 to Como Ave $10,800,000 2026 Poor pavement conditions; coordinate with bridge work. 6242-083
72 Hwy 13 Medium mill and overlay from Dakota to Washburn ave $1,600,000 Not Selected  Program limited by available funding.
71 Hwy 7 Medium mill and overlay from Hwy 25 to Six mile Creek $9,400,000 2030 Projected poor pavement conditions.
71 US10 Medium mill and overlay from east of 114th Ave NW to east Foley Blvd $2,200,000 Not Selected  RQI does not reflect on the ground conditions
70 US12 Medium mill and overlay from County Road 90 to eastern Independence City limits $400,000 Not Selected  Program limited by available funding.
70 Hwy 610 Minor rehabilitation from US169 to Braun bridge $29,800,000 2031 Projected poor pavement conditions.
70 I35W Medium mill and overlay from 76th St to 66th ST $1,800,000 Not Selected  Program limited by available funding.
70 Hwy 101 Minor rehabilitation from Wright County Road 38 to US10 $5,300,000 2031 Poor pavement conditions. 8608-33
69 US212 Medium mill and overlay from Hwy 5 to Tacoma Ave $3,500,000 Not Selected  Program limited by available funding.
69 Hwy 316 Medium mill and overlay from Southern to northern limits $7,600,000 2025 Poor pavement conditions. SP 1926-023.
69 Hwy 55 Major rehabilitation from Dakota County Road 63 to US52 $5,900,000 2028 Poor pavement conditions.
69 US52 Medium mill and overlay from Goodhue/Dakota County Line to County Road 86 $2,300,000 Not Selected  Program limited by available funding.
69 Hwy 252 Medium mill and overlay from 85th to Hwy 610 $1,100,000 Not Selected  Program limited by available funding.
68 Hwy 62 Minor rehabilitation from Penn ave bridge to Portland Ave bridge $11,000,000 2031 Repair early distresses.
68 Hwy 65 Medium mill and overlay from 26th St to 10th ST $1,300,000 Not Selected  Program limited by available funding.
68 US169 Medium mill and overlay from Elm creek Blvd to Mississippi River Bridge $500,000 Not Selected  Program limited by available funding.
68 US212 Medium mill and overlay from 2.2 miles east of Hwy 284 to 4 lane section $2,200,000 Not Selected  Program limited by available funding.
68 Hwy 101 Medium mill and overlay from NB split with US169 to SB merge with US169  $3,400,000 Not Selected  Program limited by available funding.
67 US12 Medium mill and overlay from Wright/Hennepin County line to Hennepin County Road 90 $7,600,000 2029 Poor pavement conditions.
67 Hwy 7 Medium mill and overlay from Railroad bridge to Hwy 100 $900,000 Not Selected  Program limited by available funding.
67 Hwy 41 Medium mill and overlay from Carver County Road 61 to Pioneer Trail $12,800,000 2027 Poor pavement conditions.
67 Hwy 41 Medium mill and overlay from US169 to Pioneer Trail $1,200,000 Not Selected  Program limited by available funding.
67 US212 Minor rehabilitation from Hwy 41 to Hennepin County Road 4 $10,700,000 2028 Preventive maintenance.
66 Hwy 7 Medium mill and overlay from I-494 to Shady Oak Road $1,000,000 Not Selected  Program limited by available funding.
66 Hwy 36 Medium mill and overlay from I35W to east of Edgerton St $9,500,000 2025 Poor pavement conditions; maintenance liability. SP 6212-192.
66 Hwy 41 Reconstruction from Minnesota River to Carver County Road 61 $800,000 2022 MnDOT contribution to locally led reconstruction in Chaska. SP 1008-087.
66 US212 Meduim mill and overlay from Hwy 5 to .4 miles east of Hwy 5 $400,000 Not Selected  Program limited by available funding.
66 I35E Medium mill and overlay from 76th St to 66th ST $900,000 Not Selected  Program limited by available funding.
66 Hwy 252 Thin mill and overlay from I-94 to 85th Ave $11,800,000 2029 Poor pavement conditions. Coordination with 252 CoC project.
66 Hwy 13 Medium mill and overlay from .4 miles west of Dakota Ave to .2 miles east of Dakota ave $700,000 Not Selected  Program limited by available funding.
65 US8 Medium mill and overlay from Tern Ave roundabout to Minnesota/Wisconsin State line $1,900,000 Not Selected  Program limited by available funding.
65 Hwy 62 Medium mill and overlay from I-494 to Clearwater Dr $300,000 Not Selected  Program limited by available funding.
65 US169 Medium mill and overlay from Hwy 282 to Hwy 21 $1,400,000 Not Selected  Program limited by available funding.
65 Hwy 55 Medium mill and overlay from Railroad overpass to Lyndale Ave $6,700,000 2026 Poor pavement conditions. Frontage road and ADA needs. SP 2751-059
65 Hwy 13 Medium mill and overlay from Dakota County Line to Washburn Ave $700,000 Not Selected  Program limited by available funding.
64 US12 Medium mill and overlay from Hennepin County Road 29 to Wayzata Blvd exit $3,000,000 Not Selected  Program limited by available funding.
63 Hwy 41 Medium mill and overlay from Hundermark to Pioneer Trail $300,000 Not Selected  Program limited by available funding.
63 US61 Medium mill and overlay from 70th St to Carver Ave $4,400,000 Not Selected  Program limited by available funding.
63 Hwy 62  Medium mill and overlay from Portland Ave to 28th ave $1,800,000 Not Selected  Program limited by available funding.
63 US212 Medium mill and overlay from Tacoma Ave to Carver County Road 36 $2,700,000 Not Selected  Program limited by available funding.
62 US8 Unbonded overlay from Wyoming Ave to Tern Ave roundabout $32,200,000 2030 Poor pavement conditions.
62 Hwy 62 Medium mill and overlay from Clearwater to Tracy Ave $3,300,000 Not Selected  Program limited by available funding.
62 Hwy 65 Medium mill and overlay from 53rd Ave N to Moore Lk Dr $3,900,000 2027 Poor pavement conditions.
62 Hwy 55 Medium mill and overlay and ADA work from Hwy 100 to Railroad overpass $3,400,000 2025 Poor pavement conditions. SP 2752-043.
62 Hwy 55 Medium mill and overlay from Pine Bend Trail to Hastings CL $3,500,000 Not Selected  Program limited by available funding.
61 US12 Medium mill and overlay from Railroad bridge to 7th St $300,000 Not Selected  Program limited by available funding.
61 Hwy 7 Minor CPR from Kings Dr to I-494 $800,000 2030 Poor pavement conditions.
61 Hwy 62 Medium mill and overlay from Portland Ave bridge to .154 miles east of Portland bridge $200,000 Not Selected  Program limited by available funding.
61 US212 Unbonded concrete overlay from I-494 to Hwy 62 $26,200,000 2028 Poor pavement conditions.
60 Hwy 77 Medium mill and overlay from Minnesota River bridge to I-494 $3,100,000 Not Selected  Program limited by available funding.
60 US212 Medium mill and overlay from Chaska Creek to Hwy 41 $1,700,000 Not Selected  Program limited by available funding.
60 I694 Medium overlay from Dupont Ave to I-35W $57,600,000 2030 Projected poor pavement conditions.
59 Hwy 36 Medium mill and overlay from Washington Ave to Hwy 95  $1,800,000 Not Selected  Program limited by available funding.
59 US61 Medium mill and overlay from 3rd St Railroad crossing to US10 $4,200,000 2029 Poor pavement conditions.
59 US169 Medium mill and overlay from .1 miles north of Ash St to 1.2 miles north of Ash St $1,300,000 Not Selected  Program limited by available funding.
59 I35W Medium mill and overlay from County Road C to Sunset Ave $15,100,000 Not Selected  Program limited by available funding.
59 US10 Medium mill and overlay from Fairoak Ave to US169/Hwy 47 $900,000 Not Selected  Program limited by available funding.
59 Hwy 252 Medium mill and overlay from I-94 WB in Brooklyn Center to .4 miles north of I-94 $500,000 Not Selected  Program limited by available funding.
58 US169 Medium mill and overlay from 4.5 miles north of Hwy 19 to 5.7 miles north of Hwy 19 $1,100,000 Not Selected  Program limited by available funding.
58 US169 Medium mill and overlay from Elm Creek Blvd to US10 $1,400,000 Not Selected  Program limited by available funding.
58 US212 Medium mill and overlay from 4 lane section to Chaska Creek $2,700,000 Not Selected  Program limited by available funding.
57 Hwy 62 Medium mill and overlay from Mendota bridge to I-35E $6,700,000 2024 Poor pavement conditions. SP 1918-119.
57 US169 Medium mill and overlay from LeSueur/Scott County line to Hwy 19 $400,000 Not Selected  Program limited by available funding.
57 Hwy 55 Medium mill and overlay from US52 to US61 $26,000,000 2028 Poor pavement conditions.
56 Hwy 610 Medium mill and overlay from I-94 to Elm Creek Blvd $2,400,000 Not Selected  Program limited by available funding.
55 Hwy 62 Medium mill and overlay from Clearwater Dr to .32 miles east of Clearwater $400,000 Not Selected  Program limited by available funding.
55 I694 Medium mill and overlay from Lexington Ave to Hwy 49 $4,600,000 Not Selected  Program limited by available funding.
55 Hwy 121 Medium mill and overlay from I35W to Pedestrian bridge $300,000 Not Selected  Program limited by available funding.
54 US212 Medium mill and overlay from .1 miles south of Hwy 62 to Hwy 62 $1,000,000 Not Selected  Program limited by available funding.
54 I494 Medium mill and overlay from US12 to I-94 $12,800,000 Not Selected  Program limited by available funding.
53 Hwy 62 Reconstruction from 28th Ave S to 43rd Ave $12,300,000 2027 Poor pavement conditions.
51 US52 Unbonded concrete overlay from Clayton to I-494 $43,300,000 2028 Poor pavement conditions.
50 I35W Unbonded concrete overlay from I35W/I35E to Cliff Rd exit $72,300,000 2025 Mobility needs; bridge replacement coordination. SP 1981-140.
50 I35 Medium mill and overlay from Scott County road 2 to Hwy 50 $6,400,000 Not Selected  Program limited by available funding.
49 I35W Medium mill and overlay from 90th St to 76th St $1,000,000 2024 Poor pavement conditions. Coordinate with 494 CoC project. SP 2785-424.
46 Hwy 36 Medium mill and overlay from east of Edgerton St to Washington Ave $8,900,000 2022 Poor pavement conditions; maintenance liability. SP 8204-077.
46 Hwy 101 Reclaim NB lanes & medium mill and overlay SB lanes from I-94 to Wright County Road 38 $10,900,000 2026 Poor pavement conditions. 2738-031
45 US169 Thin mill and overlay from Minnesota River Bridge to Anderson Lake Blvd $10,300,000 2028 Poor pavement conditions. 2776-112
45 I35 Medium mill and overlay from Hwy 95 to Chisago County Road 9 $6,700,000 Not Selected  Program limited by available funding.
44 US52 Unbonded overlay from Dakota County Road 86 to Dakota County Road 42 $66,100,000 2023 Poor pavement conditions. SP 1906-071.
43 I94 Medium mill and overlay from Mounds Blvd to Ramsey/Washington County line $6,800,000 Not Selected  Program limited by available funding.
43 Hwy 5 Medium mill and overlay from I-494 to Hennepin/Ramsey County line $3,900,000 Not Selected  Program limited by available funding.
40 US8 Medium mill and overlay from I-35 to Wyoming Ave $12,100,000 2025 Coordination with County safety improvements. Poor pavement conditions. SP 1308-027.
40 Hwy 13 Medium mill and overlay from Washburn Ave to I-35 $1,400,000 Not Selected  Program limited by available funding.
39 US12 Reconstruction and mill and overlay from Wayzata Blvd to I-494 $60,600,000 2026 Concrete segment is in poor condition; maintenance liability 2716-129
39 I35E Replace short segment of pavement either side of bridge 9532 $3,000,000 2026 Poor pavement conditions. Coordinate with Shepard Rd bridge replacement.
39 I694 Major rehabilitation from Hwy 49 to Washington County Road 10 $18,400,000 2029 Repair early distresses.
38 I94 Medium mill and overlay from Exit 207 to I494 $14,500,000 Not Selected  Program limited by available funding.
36 US12 Thin mill and overlay from the eastern Independence City limits to Hennepin County Road 29 $3,800,000 2029 Poor pavement conditions.
36 US169 Medium mill and overlay from Valley View Rd to US 212/Hwy 62 $1,900,000 Not Selected  Program limited by available funding.
35 Hwy 77 Medium mill and overlay from I-494 to Hwy 62 $13,200,000 2022 Poor pavement conditions. SP 2758-077.
35 Hwy 55 Medium mill and overlay from General Mills Blvd to Schaper Rd $2,100,000 Not Selected  Program limited by available funding.
34 US61 Thin mill and overlay from Hwy 316 to 3rd st $3,700,000 2026 Poor pavement conditions. 1913-107
33 I94 Medium mill and overlay from Wright/Hennepin County line $3,400,000 Not Selected  Program limited by available funding.
32 Hwy 280 Unbonded overlay from Como to I-35W $23,400,000 2027 Poor pavement conditions.
32 I35 Medium overlay from Dakota County Road 70 to I35E/I35W $18,500,000 2029 Poor pavement conditions.
31 I35W Medium mill and overlay from 106th to 76th $7,300,000 2023 Poor pavement conditions. Coordinate with 494 CoC project. SP 2782-352.
29 Hwy 65 Medium mill and overlay from south of E Moore Lake Dr to Anoka County Road 10 $3,100,000 Not Selected  Program limited by available funding.
29 I494 Medium mill and overlay from I-94/694 to Lake Dr $2,300,000 Not Selected  Program limited by available funding.
29 Hwy 610 Medium mill and overlay from Elm Creek Blvd to US 169 $2,700,000 Not Selected  Program limited by available funding.
29 I35E Medium mill and overlay from Cayuga to Little Canada Rd $7,700,000 Not Selected  Program limited by available funding.
29 US10 Medium mill and overlay from Hwy 101 to Cleveland Ave $3,400,000 Not Selected  Program limited by available funding.
28 I35E Medium mill and overlay from Ramsey County Road 96 to 80th St $10,600,000 Not Selected  Program limited by available funding.
27 I35W Medium mill and overlay from Sunset Ave to I35W/I35E $7,100,000 Not Selected  Program limited by available funding.
25 I35 Medium mill and overlay from I35W/E to US8 $6,400,000 Not Selected  Program limited by available funding.
25 I35 Medium mill and overlay from Chisago County Road 9 to Chisago/Pine County line $8,600,000 Not Selected  Program limited by available funding.
23 I494 Medium mill and overlay from I94/694 to Tamarack Rd $800,000 Not Selected  Program limited by available funding.
21 US169 Medium mill and overlay from Hwy 19 to Hwy 25 $4,500,000 Not Selected  Program limited by available funding.
19 US212 Major rehabilitation from Carver County Road 36 to 2.2 miles east of Hwy 284 $8,400,000 2023 Poor pavement conditions. SP 1013-101.
18 Hwy 77 Unbonded overlay from 138th St to Dakota/Hennepin County line $51,600,000 2026 Poor pavement conditions. 1929-050
18 US169 Major rehabilitation from Scott County Road 16 to Canterbury Rd $13,100,000 2026 Poor pavement conditions. 7009-129
18 US169 Medium mill and overlay from 1.2 miles north of Hwy 282 to .27 miles north of Hwy 282 $5,900,000 Not Selected  Program limited by available funding.
18 US169 Medium mill and overlay from 93rd Ave to Elm Creek Blvd $4,000,000 Not Selected  Program limited by available funding.
17 I35E Medium mill and overlay from County Road E to County Road 96 $2,300,000 Not Selected  Program limited by available funding.
15 US169 Medium mill and overlay from Hwy 25 to Ash St $1,800,000 Not Selected  Program limited by available funding.
11 I35E Medium mill and overlay from  south of I-35W to I35E/W $1,300,000 Not Selected  Program limited by available funding.

View more detailed scores (Excel).

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
96 I-494 Medium mill and overlay from Hardman Ave to 5th Ave $2,000,000 Not Selected Resurfaced in 2019
95 I-94 Medium mill and overlay from Nicollet Ave Bridge to Western Ave $42,500,000 2028 NA
95 I-94 Medium mill and overlay from County Road 13 to Hwy95 $4,000,000 2023 NA
95 I-494 Minor resurfacing from France Ave to Hwy12 $26,000,000 2029 NA
94 I-35E Major reconstruction from I35W to Lone Oak Rd $34,400,000 2026 NA
94 I-694 Minor resurfacing from Hwy 49 to Washington County Road 10 $14,000,000 2029 NA
91 US 169/US 12 Medium mill and overlay on 169 from Hwy 55 to 77th ave and on Hwy 12 from Hennepin County Road 9 to Reference point 148 $4,100,000 Not Selected Not a district priority will continue to monitor pavement performance
90 I-35E Minor reconstruction from Little Canada road to County Road E $1,800,000 2029 NA
89 I-94 Unbonded overlay from Ramsey/Washington County Line to Washington  County Road 13 $8,600,000 2023 NA
89 I-35W Major rehabilitation from South of 106th St to 90th St $2,700,000 2023 NA
88 I-94 Medium mill and overlay from Hwy101 overpass to Hennepin County Road 81 $1,400,000 Not Selected Not a district priority will continue to monitor pavement performance
88 US 52 Major rehabilitation from I-494 to Concord Blvd $2,800,000 2021 NA
87 I-94 Medium mill and overlay from Hwy95 to Minnesota river Bridge $1,500,000 2023 NA
87 I-394 Medium mill and overlay from Hwy100 to Xerxes Ave $2,200,000 Not Selected Many bridge decks adversely affect smoothness.
86 I-94 Major rehabilitation from Western Ave to I-35E $1,100,000 2022 NA
86 I-494 Medium mill and overlay from 5th Ave to Peiper Rd $4,500,000 Not Selected NA
86 Hwy 101 Medium mill and overlay from I-94 to Moore Lake Rd $4,000,000 2025 NA
86 I-35W Medium mill and overlay from Hwy36 to County Road C $2,100,000 Not Selected Resurfaced in 2017
86 I-35E Major reconstruction  from 10th St bridge to University Ave bridge $1,200,000 2022 NA
85 Hwy 65 Medium mill and overlay from Hwy10 to 117th Ave $4,800,000 Not Selected NA
85 I-694 Medium mill and overlay from Hwy49 to I-35E $1,200,000 2029 NA
84 US 169 Medium mill and overlay from Hwy 55 to 77th Ave $3,900,000 Not Selected Not a district priority will continue to monitor pavement performance
84 US 10 Whitetop overlay from Hwy169 to Creek Meadows Bridge $15,600,000 2030 NA
84 I-35W Medium mill and overlay from 4th St to Hwy36 $5,800,000 Not Selected Resurfaced in 2017
84 I-35W Minor reconstruction from 66th St to 42nd St $3,700,000 2028 NA
84 I-394 Thin mill and overlay from I-494 to Hwy 100 $28,000,000 2029 NA
83 I-694 Medium mill and overlay from County Road 10 to Reference point 58 north of I-94 $1,000,000 Not Selected Data collected during System Interchange construction.
82 US 12 Medium mill and overlay from Wright/Hennepin County Line to Independence eastern City limits $8,000,000 2029 NA
82 I-35 Medium overlay from Dakota County Road 70 to I35 $19,300,000 2029 NA
82 I-694 Medium mill and overlay from I35W to Lexington Ave $700,000 Not Selected Not a district priority will continue to monitor pavement performance
81 I-94 Unbonded overlay from Washington County Road 13 to Hwy 95 $14,600,000 2023 NA
81 US 169 Medium mill and overlay from Anderson Lake Bridge to Valley View Rd $700,000 Not Selected Interchange area - numerous bridge decks.
81 I-35W Medium mill and overlay from Washington bridge to 4th St bridge $1,600,000 Not Selected St. Anthony Falls Bridge.
80 US 10 Thin mill and overlay from Hwy 65 to I35W $7,700,000 2026 NA
80 I-694 Major rehabilitation and overlay from I-94 to Hwy252 $500,000 2021 NA
79 US 169 Medium mill and overlay from Scott County road 18 bridge to Minnesota River Bridge $1,600,000 Not Selected NA
79 Hwy 100 Medium mill and overlay from Cedar Lake Road to Railroad bridge $9,900,000 2026 NA
79 I-35 Medium mill and overlay from .05 miles north of County road 2 to 1 mile north of County Road 2 $500,000 Not Selected Not a district priority will continue to monitor pavement performance
78 I-494 Medium mill and overlay from I-94/I-694 to Jct I-94 $100,000 Not Selected Bridge deck affects smoothness.
78 US 169 Medium mill and overlay from Cedar Lake Road to Hwy 55 $1,100,000 Not Selected Not a district priority will continue to monitor pavement performance
78 I-35 Whitetop overlay from Hwy8 to Hwy 95 $63,900,000 2027 NA
77 I-94 Medium mill and overlay from Brooklyn Blvd to Humboldt bridge $2,200,000 2021 NA
77 US 212 Minor overlay from McLeod/Carver County line to Hwy 5 $1,700,000 2028 NA
77 US 8 Unbonded overlay from Wyoming Ave to Tern Ave $33,300,000 2030 NA
77 US 61 Whitetop overlay from Carver Ave to I-94 $23,900,000 2030 NA
76 US 52 Medium mill and overlay from Lafayette Bridge to under I-94 $100,000 Not Selected Not a district priority will continue to monitor pavement performance
76 Hwy 100 Medium mill and overlay from .04 miles south of Hwy 62 to 1.3 miles north of Hwy 62 $2,100,000 Not Selected Bridge decks affect  smoothness rating.
74 Hwy 100 Minor overlay from Railroad Bridge to Hennepin County Road 152 $4,500,000 2026 NA
73 US 212 Minor overlay from Hennepin  County Road 4 to I-494 $4,000,000 2027 NA
73 US 52 Medium mill and overlay from Dakota County road 42 to Clayton Ave $800,000 Not Selected Not a district priority will continue to monitor pavement performance
73 Hwy 7 Medium mill and overlay from Shady Oak rd. to Texas Ave $2,700,000 Not Selected Not a district priority will continue to monitor pavement performance
73 US 169 Major rehabilitation from 173rd St to Shakopee Bypass $2,200,000 2024 NA
73 US 10 Medium mill and overlay from Cleveland Fairoak Ave $14,100,000 2026 NA
73 Hwy 280 Major reconstruction from I-94 to Como Ave $7,700,000 2026 NA
73 Hwy 610 Medium mill and overlay from Mississippi River Bridge to east of Coon Rapids Blvd $1,200,000 Not Selected Not a district priority will continue to monitor pavement performance
73 I-394 Medium mill and overlay from HOV overpass to I-94 $200,000 Not Selected Many bridge decks adversely affect smoothness.
73 Hwy 610 Medium mill and overlay from East of Coon Rapids Blvd to Hwy10 $1,120,000 Not Selected Not a district priority will continue to monitor pavement performance
72 US 52 Medium mill and overlay from Dakota County Road 86 to Hwy 50 $5,200,000 Not Selected NA
72 Hwy 55 Medium mill and overlay from Wright/Hennepin County line to Fernbrook $22,400,000 2027 NA
72 Hwy 7 Medium mill and overlay from Hwy25 to end of Six mile creek $9,700,000 2030 NA
72 US 12 Medium mill and overlay from Hennepin County Road 101 Bridge to east of Crosby Rd $6,800,000 2025 NA
72 Hwy 62 Medium mill and overlay from 43rd Ave to Mendota Bridge $1,400,000 2026 NA
72 I-35E Thin mill and overlay from Railroad Bridge to 10th St Bridge  $10,000,000 2027 NA
71 Hwy 55 Medium mill and overlay from 13th Ave to 32nd st $2,900,000 Not Selected NA
71 Hwy 7 Medium mill and overlay from Division st to Hennepin County Road 101 $2,800,000 2026 NA
71 Hwy 65 Major rehabilitation  from 229th Ave to 217th Ave $6,600,000 2024 NA
71 US 169 Major rehabilitation from Shakopee bypass to Reference point 102 $200,000 2026 NA
71 Hwy 100 Medium mill and overlay from I-494 to Hwy62 $2,500,000 Not Selected NA
71 I-394 Medium mill and overlay from I-94 to Washington Ave $1,200,000 Not Selected Many bridge decks adversely affect smoothness.
71 Hwy 610 Medium mill and overlay from 1.2 miles east of Mississippi River Bridge to east of Coon Rapids Blvd  $210,000 Not Selected Not a district priority will continue to monitor pavement performance
70 Hwy 7 Medium mill and overlay from Bridge #8518 to Carver County Road 33 $200,000 Not Selected NA
70 US 169 Medium mill and overlay from the Shakopee bypass to Scott County Road 15 $100,000 Not Selected NA
70 Hwy 610 Medium mill and overlay from Coon Rapids Blvd overpass to 1.2 miles east of Mississippi River Bridge  $320,000 Not Selected NA
69 US 212 Medium mill and overlay from Hwy 5 to Faxon Rd $3,200,000 Not Selected NA
69 Hwy 316 Medium mill and overlay from south junction with Hwy61 to northern junction with Hwy61  in Hastings  $8,700,000 2025 NA
69 US 10 Medium mill and overlay from east of Fairoak aver to Jct Hwy169/Hwy47 $900,000 Not Selected NA
69 Hwy 252 Medium mill and overlay from 85th Ave to Hwy610 $600,000 Not Selected NA
68 US 212 Medium mill and overlay from 2.2 miles east of Hwy 284 to reference point 145 (begin 4 lane section) $1,100,000 Not Selected NA
68 Hwy 7 Medium mill and overlay from Railroad bridge to Wooddale Ave $700,000 Not Selected NA
68 Hwy 65 Medium mill and overlay from 143rd Ave to 229th Ave $500,000 Not Selected NA
68 Hwy 65 Medium mill and overlay from Bunker Lake Blvd to Anoka County Road 61 $1,000,000 Not Selected NA
68 Hwy 65 Medium mill and overlay from east of Reference point 13 to Bunker Lake Blvd $700,000 Not Selected NA
68 US 169 Major Reconstruction from Scott County Road 15 to Canterbury Road $10,900,000 2026 NA
68 Hwy 62 Minor overlay from Penn Ave to Portland Ave $2,100,000 2026 NA
67 US 212 Minor overlay from Hwy 41 to Hennepin County Road 4 $12,000,000 2030 NA
67 US 52 Medium mill and overlay from Hwy 19 to Goodhue/Dakota County Line $400,000 Not Selected NA
67 Hwy 55 Medium mill and overlay from Mendota Heights Blvd to Hwy149 $800,000 Not Selected NA
67 Hwy 55 Medium mill and overlay from Hwy 100 to Lyndale Ave $13,000,000 2025 NA
67 US 169 Medium mill and overlay from Elm Creek Blvd. to Old 252 in Champlin $400,000 Not Selected NA
67 US 10 Medium mill and overlay from .2 miles west I-694 bridge to I-694 $500,000 Not Selected NA
67 US 61 Medium mill and overlay from EB I-94 exit ramp to Jct I-94 $100,000 Not Selected NA
67 US 61 Medium mill and overlay from Roselawn aver to Hwy 36 $1,100,000 Not Selected NA
67 Hwy 62 Medium mill and overlay from Mendota Bridge to I-35E $7,300,000 2025 NA
67 Hwy 252 Thin mill and overlay from Brooklyn Center to 85th  $12,300,000 2029 NA
66 US 52 Medium mill and overlay from Inver Grove Trail to Hwy 55. $3,600,000 2028 NA
66 Hwy 55 Medium mill and overlay from 46th St to Minnehaha Bridge $1,900,000 Not Selected NA
66 Hwy 7 Reclaim and overlay from east end of Six mile creek to Division St $29,600,000 2026 NA
66 Hwy 41 Medium mill and overlay from Hwy169 to Railroad crossing  $400,000 Not Selected NA
66 Hwy 41 Medium mill and overlay from Railroad Crossing to Scott/Carver County line $300,000 Not Selected NA
65 US 52 Medium mill and overlay from Concord Blvd to Plato Blvd $900,000 Not Selected NA
65 US 52 Unbonded overlay from Hwy 50 to Dakota County Road 42 $25,900,000 2023 NA
65 Hwy 7 Medium mill and overlay from I-494 to Shady Oak Road. $400,000 Not Selected NA
65 Hwy 7 Medium mill and overlay from Wooddale Ave to Hwy 100 $300,000 Not Selected NA
65 US 12 Medium mill and overlay from .01 miles east of Reference point 148 to .45 miles east of Reference point 148 $200,000 Not Selected NA
65 US 10 Medium mill and overlay from East of Foley Blvd to Hwy 65 bridge $2,700,000 2021 Selected prior to policy (in 2019-2022 STIP)
65 US 61 Medium mill and overlay from I-694 to White Bear Ave $2,500,000 Not Selected NA
65 US 61 Major rehabilitation from .7 miles west of Hwy 316 to Hwy 316 $2,500,000 2026 NA
65 Hwy 62 Medium mill and overlay from I-494 to Clearwater Dr $300,000 Not Selected NA
65 Hwy 62 Medium mill and overlay from Clearwater Dr to .32 miles east of Clearwater Dr $400,000 Not Selected NA
64 Hwy 55 Medium mill and overlay from Hwy52 to Hwy61 $27,000,000 2028 NA
64 US 10 Medium mill and overlay from south of Ramsey County Road 96 to North of I-694 $700,000 Not Selected NA
64 Hwy 62 Medium mill and overlay from Tracey Ave to Penn Ave $9,500,000 2026 NA
64 Hwy 77 Medium mill and overlay from Hwy 13 to Dakota/ Hennepin County Line $4,500,000 2026 NA
64 Hwy 610 Major Reconstruction from Hwy169 to Braun Dr $20,500,000 2029 NA
63 Hwy 55 Medium mill and overlay from Hwy 149 to Dakota County Road 63 $500,000 2022 NA
63 Hwy 55 Medium mill and overlay from Hwy 149 to Dakota County Road 63 $600,000 Not Selected NA
63 Hwy 55 Major Reconstruction from Dakota County Road 63 to Hwy52 $6,100,000 2028 NA
63 Hwy 41 Medium mill and overlay from Engler Blvd to Pioneer Trail $600,000 Not Selected NA
63 Hwy 41 Medium mill and overlay from Pioneer Trail to Hwy 5 $600,000 Not Selected NA
62 Hwy 65 Medium mill and overlay from 53rd Ave NE to Reference Point 7 $4,000,000 2027 NA
62 Hwy 101 Medium mill and overlay from Mississippi River Bridge to Hwy10 $300,000 Not Selected NA
62 US 61 Medium mill and overlay from Forest Lake Circle to south of 250th St (RP163) $400,000 Not Selected NA
61 US 212 Unbonded overlay from I-494 to Hwy 62 $23,400,000 2030 NA
61 Hwy 101 Major rehabilitation from Hwy 5 to Town Line Rd $500,000 2024 NA
61 US 61 Medium mill and overlay from Frenchman Rd to Trailer park entrance $200,000 Not Selected NA
61 Hwy 41 Minor overlay from Carver County Road 61 to South of Engler Blvd $4,900,000 2028 NA
60 US 212 Medium mill and overlay from Faxon Rd to Carver County Road 134 $600,000 Not Selected NA
60 US 61 Medium mill and overlay from Chisago County Road 31 to 267th St in Wyoming $100,000 Not Selected NA
60 US 61 Major rehabilitation from Hwy 97 to south of 170th St Roundabout $2,800,000 2030 NA
60 I-694 Unbonded overlay from I-694 to I-35W $103,100,000 2030 NA
59 US 52 Medium mill and overlay from Goodhue/Dakota County line to Dakota County Road 86 $2,300,000 Not Selected NA
59 US 10 Medium mill and overlay from Hwy 61 to Saint Croix River Bridge $3,400,000 2027 NA
59 Hwy 77 Medium mill and overlay from Minnesota River Bridge to I-494 $2,500,000 Not Selected NA
59 Hwy 77 Medium mill and overlay from 63rd St to Hwy 62 $500,000 Not Selected NA
58 I-35E Thin mill and overlay from Lone Oak Rd to Marie Ave $15,300,000 2027 NA
57 I-94 Medium mill and overlay from 1.4 miles east of Hwy 101 to I-494 $6,000,000 Not Selected NA
57 US 212 Medium mill and overlay from 4 lane section to Chaska Creek $2,700,000 Not Selected NA
57 Hwy 55 Medium mill and overlay from Mendota Heights Rd to Hwy 149 $800,000 Not Selected NA
56 Hwy 55 Medium mill and overlay from Douglas Drive to Shaper Rd $400,000 Not Selected NA
56 US 61 Medium mill and overlay from Hwy 36 to I-694 $1,700,000 Not Selected NA
54 I-494 Medium mill and overlay from Pieper Rd to I-35 $2,000,000 Not Selected NA
54 US 61 Medium mill and overlay from entrance ramp from EB I-694 to WB I-694 entrance ramp $300,000 Not Selected NA
53 US 12 Reconstruction from Wayzata Blvd to Hennepin County Road 101 Bridge $21,000,000 2025 NA
53 Hwy 62 Unbonded overlay from 28th Ave S to 43rd Ave S $9,000,000 2026 NA
53 Hwy 41 Medium mill and overlay from Hwy 5 to Hwy 7 $600,000 Not Selected NA
52 I-35W Minor overlay from Sunset Ave to I-35E $2,300,000 2026 NA
50 I-494 Medium mill and overlay from Robert St to I-35E $2,500,000 Not Selected NA
48 US 52 Thin mill and overlay from Hwy 55 to I-494 $10,000,000 2028 NA
47 Hwy 55 Medium mill and overlay from Fernbrook to General Mills Blvd $4,500,000 Not Selected NA
46 I-35W Unbonded overlay from I35E/W to South of Cliff Rd $23,800,000 2025 NA
44 US 52 Unbonded overlay from Clayton to Inver Grove Trail $31,400,000 2028 NA
43 Hwy 65 Minor overlay from 217th Ave to Anoka/Isanti County line $5,100,000 2029 NA
43 US 169 Medium mill and  overlay from Scott County Road 15 to Shakopee western City limits $3,100,000 Not Selected NA
42 I-35E Reconstruction from Marie to Railroad bridge $2,700,000 2027 NA
37 US 169 Major rehabilitation from Shakopee bypass to Western Shakopee City Limits. $200,000 2024 NA
36 US 52 Major rehabilitation from Plato Blvd to South end of Lafayette Bridge $200,000 2021 Selected prior to policy (in 2019-2022 STIP)
35 Hwy 100 Medium mill and overlay from .6 miles south of I694 to I694 $300,000 Not Selected NA
35 I-35 Medium mill and overlay from Hwy 95 to Chisago County Road 9 $4,900,000 2022 Selected prior to policy (in 2019-2022 STIP)
34 US 61 Thin mill and overlay from Hwy 316 to 3rd St crossing $3,900,000 2026 NA
33 Hwy 65 Medium mill and overlay from 26th St to 10th St $1,300,000 Not Selected NA
33 US 169 Medium mill and overlay from Mississippi River Bridge to Hayden Lake Rd $900,000 Not Selected NA
33 US 61 Thin mill and overlay from 3rd St crossing to Hwy10 $4,400,000 2029 Combined with another segment with a high score of 65
33 Hwy 62 Medium mill and overlay from Portland Ave to 28th Ave S  $6,400,000 2026 NA
33 Hwy 280 Unbonded overlay from Como to I35W $17,300,000 2028 NA
32 Hwy 55 Medium mill and overlay from General Mills Blvd to Hwy 100 $1,000,000 Not Selected NA
32 Hwy 55 Medium mill and overlay from 32nd St to 46th St $2,100,000 Not Selected NA
32 Hwy 100 Reclaim and overlay from Hennepin County Road 152 to I-694 $11,200,000 2026 NA
31 Hwy 7 Minor overlay from Kings Dr to I-494 $800,000 2030 NA
31 US 12 Thin mill and overlay from Independence to Hennepin County Road 29 $3,900,000 2029 NA
30 Hwy 77 Unbonded overlay from 138th St to Hwy 13 $42,900,000 2026 Combined with another segment with a high score of 64
29 Hwy 55 Medium mill and overlay from General Mills Blvd to Douglas Dr $800,000 Not Selected NA
28 US 10 Medium mill and overlay from I35W to north of I-494/I694 $1,000,000 Not Selected NA
28 I-35W Medium mill and overlay from 42nd st to Washington  $8,000,000 2027 NA
26 Hwy 101 Medium mill and overlay from Hennepin County Road 14 to Kiowa Trail $1,100,000 Not Selected NA
26 Hwy 41 Medium mill and overlay from Minnesota River to Carver County Road 61 $500,000 Not Selected NA
25 Hwy 101 Medium mill and overlay from Kiowa Trail to Lyman Blvd $200,000 Not Selected NA
25 US 61 Medium mill and overlay from 25ft north of Reference point 155 to .1 miles north of 170th St $100,000 Not Selected NA
21 US 61 Medium mill and overlay from 267th St to I35W $200,000 Not Selected NA
20 US 169 Thin mill and overlay from Minnesota River to Anderson Lake Rd $10,700,000 2028 NA
16 Hwy 100 Major major rehabilitation from 36th St to Cedar Lake Ramp $200,000 Not Selected NA
15 Hwy 7 Major rehabilitation from Hennepin County Road 101 to I-494 $1,800,000 2022 Selected prior to policy (in 2019-2022 STIP)

View more detailed scores (Excel).

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
100 I-494 Medium mill and overlay from 24th Ave to France Ave $7,000,000 2025 Part of corridors of commerce project
100 I-94 Medium mill and overlay from Nicollet to Western Ave  $13,300,000 2028 NA
100 I-35W Reconstruction from 4th St to Ramsey County Road C $86,000,000 Not selected Additional funding needed for I-35W Hwy PASS Project in the Major Capacity project list.
96 I-494 Major concrete rehabilitation Minnesota River Bridge to 24th Ave  $4,800,000 2024 NA
95 I-35E Major concrete rehabilitation from I-35 to 10th St  $38,000,000 2027 NA
93 I-35W Medium mill and overlay from Dakota/Hennepin County line to 106th St $500,000 2020 NA
93 I-35E Major concrete rehabilitation/diamond grinding from 10th St Bridge to University Ave Bridge  $1,600,000 2022 NA
93 Hwy 100 Medium mill and overlay Cedar Lake Bridge to I-694  $12,900,000 2025 NA
89 I-35W Medium mill and overlay from Bridge 9601 to Sunset Ave currently under construction (Hwy PASS) $6,400,000 2021 NA
89 I-35E Minor concrete rehabilitation from Little Canada Road to Ramsey County Road E  $2,300,000 2027 NA
89 I-35W Minor concrete rehabilitation from 66th St to 42nd St  $2,300,000 2028 NA
89 I-394 Thin mill and overlay from I-494 to Highway 100  $6,400,000 2029 NA
88 Hwy 5 Unbonded overlay from I-494 to Hennepin/Ramsey County Line $15,200,000 2020 NA
88 I-94 Medium overlay Highway 101 to I-494  $10,900,000 2021 NA
87 I-494 Medium mill and overlay I-94/I-694 to Tamarack  $400,000 2020 NA
87 I-94/I-694 Mill and overlay at multiple locations in Brooklyn Center $2,100,000 2021 NA
87 I-94 Major concrete repair from Western Ave to Mounds Blvd  $4,800,000 2022 NA
87 I-35 Medium mill and overlay from Dakota County Road 70 to I-35  $5,800,000 2029 NA
86 US212 Minor Concrete rehabilitation Hennepin County Road 4 to Highway 62  $3,300,000 2027 NA
85 Hwy 55 Medium mill and overlay from Bridge 27116 to Hennepin County Road 63 $4,700,000 2022 NA
85 US12 Medium mill and overlay from Wayzata to junction of I-494/I-394 $5,000,000 2025 NA
85 I-694 Concrete rehabilitation Highway 49 to Highway 61  $1,400,000 2027 NA
84 Hwy 65 Reconstruction from I-35W to 10th St $1,700,000 2021 NA
83 US169 Concrete rehabilitation and mill and overlay from Highway 21 to Reference point 102 $7,000,000 2024 NA
83 US169 Concrete rehabilitation from Scott County Road 15 to Minnesota River Bridge $4,600,000 2026 NA
83 US10 Medium mill and overlay from reference point 232 to Highway 65  $3,100,000 Not selected Not a current district priority, but will continue to monitor pavement performance
81 I-94 Unbonded concrete Overlay Ramsey/Washington County line to West End of Saint Croix river Bridge $52,000,000 2024 NA
81 Hwy 280 Concrete rehabilitation I-94 to Como entrance ramp $2,600,000 2026 Coordinated with a bridge project
80 US61 Mill and overlay from Carver Ave to I-94 $3,500,000 2026 NA
79 Hwy 55 Reclaim from Fernbrook to General Mills Blvd $5,500,000 2024 NA
79 Hwy 62 Medium mill and overlay from Portland Ave bridge to 28th Ave Bridge $23,000,000 Not selected Not a current district priority, but will continue to monitor pavement performance
78 US52 Medium mill and overlay from I-494 to Plato Blvd $4,900,000 2020 NA
78 Hwy 36 Mill and overlay from I-35W to reference point 6 $5,300,000 2024 NA
78 US52 Concrete pavement rehabilitation from Clayton to I-494  $14,500,000 2028 NA
78 US12 Medium mill and overlay from Wright/Hennepin County line to Hennepin County Road 29 $3,500,000 2028 NA
78 US169 Medium overlay from 77th Ave N to reference point 142 $2,200,000 2029 NA
78 Hwy 7 Reclaim and overlay from Carver County Line to Division St $13,600,000 2029 NA
77 US10 Medium mill and overlay from Fairoak to Highway 169/Highway 47  $900,000 2022 NA
77 Hwy 62 Medium mill and overlay From Tracy Ave to Penn Ave $2,900,000 2026 Coordinated with a bridge project
77 I-35 Medium mill and overlay from Highway 8 to Highway 95 $15,400,000 2028 NA
76 I-694 Medium mill and overlay from Washington County Road 10 to junction of I-94/I-494 $500,000 2020 NA
76 Hwy 65 Medium mill and overlay from 53rd Ave NE to reference Point 7 $1,000,000 2027 NA
74 Hwy 77 Medium mill and overlay from Minnesota River Bridge to Highway 62 $5,000,000 2021 NA
74 Hwy 36 Medium mill and overlay from reference point 6 to Washington County Limits $8,300,000 2022 NA
74 US52 Concrete overlay from Dakota County County Road 86 to Dakota County Road 42 $28,000,000 2023 NA
74 US212 Minor concrete rehabilitation from Washington/McLeod line to Highway 5 $600,000 2027 NA
73 Hwy 101 Medium mill and overlay from I-94 to northbound bridge over Highway 10 $8,200,000 2025 NA
72 Hwy 65 Medium mill and overlay from Highway 10 to Coon Creek $7,200,000 2024 NA
72 US8 Thin mill and overlay from 2nd St bridge to Wyoming Ave $2,700,000 2025 NA
72 US10 Medium mill and overlay from Jevis St to Fairoak Ave $5,900,000 2026 NA
71 Hwy 13 Medium mill and overlay from old Highway 101 to Dakota Ave  $700,000 Not selected Not a current district priority, but will continue to monitor pavement performance
70 Hwy 7 Concrete overlay and micro surface from Division St to I-494 $9,500,000 2022 NA
70 Hwy 62 Major concrete rehabilitation from Highway 55 to I-35E $2,500,000 2024 NA
70 Hwy 62 Minor concrete rehabilitation from Penn Ave bridge to Portland Ave bridge  $800,000 2026 Coordinated with a corridors of commerce project
69 US212 Major concrete rehabilitation from Scott County Road 36 to Chaska Bypass $5,200,000 2023 NA
68 US212 Medium mill and overlay from Scott County Road 36 to Highway 5 $9,200,000 2020 NA
66 US52 Unbonded overlay from Goodhue/Dakota County Line to Dakota County Road 86 $7,600,000 2020 NA
66 Hwy 252 Thin mill and overlay from I-94 to Highway 610 $3,400,000 2029 NA
65 Hwy 316 Medium mill and overlay from Higway 61 to Michael Ave $4,100,000 2025 NA
65 I-494 Minor concrete rehabilitation from France Ave to Highway 12 $4,100,000 Not selected District anticipates the pavement condition will not deteriorate as fast as the model is projecting
63 Hwy 610 Major concrete rehabilitation from Highway 169 to Braun Ave $9,600,000 2029 NA
63 US8 Medium mill and overlay from Wyoming Ave to Thrush Ave $5,300,000 Not selected Not a current district priority, but will continue to monitor pavement performance
62 Hwy 316 Reconstruction from Michael Ave to Vermillion St/Highway 61 $1,700,000 2021 NA
60 Hwy 55 Medium mill and overlay from 13th Ave to pedestrian bridge $5,800,000 2022 NA
60 I-694 Unbonded concrete overlay from I-94/I-694 to I-35W $28,000,000 2026 NA
60 Hwy 55 Concrete rehabilitation from Dakota County Road 63 to Highway 52 $4,200,000 2028 NA
60 I-35W Minor concrete rehabilitation from Washington Bridge to 4th St bridge $400,000 Not selected District anticipates the pavement condition will not deteriorate as fast as the model is projecting
58 US169 Medium mill and overlay from Mississippi River Bridge to Highway 10/Highway 47 $1,100,000 2021 Selected prior to policy (in 2019-2022 STIP)
58 I-35W Medium mill and overlay from 106th St bridge to 82nd St bridge  $5,700,000 2023 Coordinated with a corridors of commerce project
58 I-35W Unbonded Overlay from I-35E/W to Cliff Rd $22,000,000 2025 Coordinated with a bridge project
58 I-35W Minor concrete rehabilitation from Sunset Ave to I-35E $2,400,000 2026 Selected prior to policy (in 2019-2028 CHIP)
57 I-35W Medium mill and overlay from 82nd St bridge to 76th St $3,800,000 2024 Selected prior to policy (in 2019-2028 CHIP)
57 Hwy 62 Unbonded concrete overlay from 28th Ave to 43rd Ave $3,400,000 2026 Coordinated with a corridors of commerce project
57 US169 Thin mill and overlay from County Road 5 to Highway 55 $1,800,000 Not selected Not a current district priority, but will continue to monitor pavement performance
55 I-494 Minor concrete rehabilitation from Tamarack bridge to south of Washington County Line $1,300,000 2025 Selected prior to policy (in 2019-2028 CHIP)
55 US169 Thin mill and overlay from Highway 55 to 77th Ave N $5,100,000 Not selected NA
53 Hwy 100 Thin mill and overlay from I-494 to Highway 62 $1,800,000 Not selected NA
52 US169 Minor concrete rehabilitation from Anderson Lake Blvd to Valley View Blvd $300,000 Not selected NA
51 US10 Thin mill and overlay from Highway 65 to I-35W $2,700,000 2026 Selected prior to policy (in 2019-2028 CHIP)
49 I-35W Minor concrete rehabilitation from 76th St to 66th St $400,000 2020 Selected prior to policy (in 2019-2022 STIP)
44 Hwy 55 Thin mill and overlay from Rockford Rd to Fernbrook $9,300,000 2027 Limited funding for bigger fix, which scores higher
44 Hwy 280 Unbonded concrete overlay from Como exit ramp to bridge 62821 $6,000,000 2028 District anticipates the pavement condition will  deteriorate faster than model is projecting
44 Hwy 100 Thin mill and overlay from Hennepin County Road 5 to Cedar Lake Bridge  $500,000 Not selected NA
44 I-35 Minor concrete rehabilitation from Scott County Road 2 to 1 mile north of Scott County Road 2  $200,000 Not selected NA
44 I-35E Major concrete rehabilitation from Marie St to CP railroad bridge $200,000 Not selected NA
41 Hwy 55 Medium mill and overlay from General Mills Blvd to ramp to southbound Highway 100 $1,700,000 2021 Selected prior to policy (in 2019-2022 STIP)
40 Hwy 65 Reclaim and overlay from Coon Creek to 217th Ave N $12,200,000 2024 Coordinated with a bridge project
39 Hwy 77 Unbonded concrete overlay 138th St to Dakota/Hennepin County line  $23,000,000 2026 Coordinated with County Project
38 I-35W Medium mill and overlay from Portland/Park Ave to Washington Ave bridge  $6,500,000 2027 This section is currently on a 7 year rehabilitation cycle
36 Hwy 100 Major concrete rehabilitation from south I-694 to I-694 $500,000 2020 Selected prior to policy (in 2019-2022 STIP)
36 Hwy 280 Minor concrete rehabilitation from Ramsey County Road B to I-35W $200,000 Not selected NA
36 Hwy 55 Thin mill and overlay from Highway 52 to Highway 61 $1,100,000 Not selected NA
34 US52 Minor concrete pavement rehabilitation from Dakota County 42 to Clayton $200,000 Not selected NA
31 US169 Thin mill and overlay from Minnesota River Bridge to Anderson Lake bridge $3,300,000 2029 District anticipates the pavement condition will  deteriorate faster than model is projecting
30 Hwy 7 Minor concrete rehabilitation from Kings Dr to I-494 $100,000 Not selected NA
30 US61 Thin mill and overlay from 3rd St railroad crossing to Highway 10 $1,000,000 Not selected NA
30 Hwy 41 Thin mill and overlay from rail crossing to Scott/Carvery County line $400,000 Not selected NA
30 Hwy 41 Medium mill and overlay from Minnesota River Bridge to Highway 61 $300,000 Not selected NA
29 Hwy 41 Minor concrete rehabilitation from Highway 61 to Hundertmark Rd $900,000 2026 Score is low because of included urban section.
29 US52 Minor concrete rehabilitation from Lafayette Bridge to I-94 $100,000 Not selected NA
29 US12 Medium mill and overlay from Hennepin County Road 29 to reference point 48 $400,000 Not selected NA
29 US12 Thin mill and overlay from east of reference point 48 to reference point 48 $200,000 Not selected NA
29 I-394 Thin overlay from Highway 100 to Washington Ave  $2,200,000 Not selected NA
25 Hwy 121 Minor concrete rehabilitation from Richfield to pedestrian bridge $100,000 Not selected NA
24 US8 Medium mill and overlay from I-35 to 2nd St Bridge $400,000 Not selected NA
16 Hwy 55 Thin mill and overlay from Douglas Dr to BNSF Railroad bridge $1,900,000 2024 Coordinated with a bridge project
15 I-35 Minor concrete rehabilitation from Highway 95 to Chisago County Road 9 $2,800,000 Not selected NA
6 US61 Thin mill and overlay from Highway 316 to 3rd St Crossing  $1,100,000 2026 Coordinated with a city project