Project selection

Increasing the transparency of how we select highway construction projects

Urban non-freeway/non-expressway pavement projects

MnDOT Metro District

Scoring criteria for urban non-freeway, non-expressway pavement projects. Out of 100 possible points, 25 points are based on the timing of the improvement, 25 points are based on cracking, rutting and patching, 10 points are based on traffic volume, 10 points are based on compliance with the Americans with Disability Act, 10 points are based on active transportation and transit, 10 points are based on other infrastructure needs, 5 points are based on the condition of local utilities under the road, and 5 points are based on whether the project will benefit an environmental justice population.

Learn more about how MnDOT evaluates and selects urban pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. MnDOT scores and prioritizes urban non-freeway/non-expressway pavement projects separately from the normal pavement scoring process, because of their complexity, utilities and other infrastructure and level of required local coordination and public involvement. In many instances, these roads function both as state highways and as city streets. These pavement projects can be on either National Highway System or non-NHS.

Freeways have full access control (no driveways, signals or at-grade intersections). Expressways have partial access control (limited or no driveways, few and widely spaced intersections, and may include some grade separated crossings). Both are high speed roads designed to facilitate longer trips.

For the purposes of this scoring category, MnDOT uses a flexible, context-based definition of urban. This includes areas with medium-to-high density adjacent development with small to medium setbacks, and in some instances no setback. This includes both residential, industrial and commercial areas. In some instances, the urban context may cover less than a quarter mile.

Urban pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related Links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2024

Score Route  Community Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
45 Hwy 120 Oakdale, Maplewood Medium mill and overlay from Ridge Dr to 4th St  $1,400,000 Not Selected  Projected poor pavement conditions.
30 Hwy 121 Minneapolis Medium mill and overlay from Pedestrian Bridge to 58th ST  $1,200,000 Not Selected  Poor pavement conditions.
50 Hwy 13 LILYDALE, MENDOTA, MENDOTA HEIGHTS Resurface Hwy 13 from Hwy 55 to Hwy 13 in St. Paul $13,296,239 2032 NA
60 Hwy 156 Saint Paul  Medium mill and overlay from Dakota/Ramsey County Line to US52 $500,000 Not Selected  Program limited by available funding.
55 Hwy 156 South Saint Paul  Medium mill and overlay from I-494 to Armour Ave $600,000 Not Selected  Program limited by available funding.
50 Hwy 156 South Saint Paul  Medium mill and overlay from Armour Ave to Wentworth Ave $1,200,000 Not Selected  Program limited by available funding.
35 Hwy 156 South Saint Paul  Medium mill and overlay from Wentworth Ave to Dakota/Ramsey County line $900,000 Not Selected  Program limited by available funding.
55 Hwy 21 Jordan Thin mill and overlay from Mill st to US169  $2,300,000 Not Selected  Poor pavement conditions.
35 Hwy 244 Mahtomedi, White Bear Lake Reconstruction from Hwy 120 to Ash St $6,000,000 Not Selected  Turnback. Recent surface treatment concealing poor pavement conditions.
70 Hwy 284 Waconia, Cologne Thick mill and overlay from US212 to Hwy 5  $8,400,000 Not selected Many issues with this pavement including geometric and ADA needs in Cologne. RQI data not reflective of the poor pavement conditions.
75 Hwy 3 St Paul  Medium mill and overlay from Mendota Rd to Wyoming St $2,700,000 Not Selected  Program limited by available funding.
65 Hwy 3 Rosemount Medium mill and overlay from Dakota County Road 58 to 145th  $1,300,000 Not Selected  Program limited by available funding.
40 Hwy 3 St Paul Resurface and jurisdictional transfer Hwy 3 (Robert St) from Mississippi River Bridge to E 11th St in St Paul    $14,610,000   Not Selected Poor pavement conditions. Turnback to city. 
40 Hwy 3 St Paul Thin mill and overlay from Kellogg Blvd to I35E  $7,700,000 Not selected Poor pavement conditions. Turnback to city.
25 Hwy 3 St Paul  Rehab pavement, sidewalk replacement and ADA improvements on Hwy 3 (Robert St) from Annapolis St E to Mississippi River in St Paul   $13,529,000   2027   Poor pavement conditions. 
55 Hwy 5 Waconia Medium mill and overlay from Oak ave to Hwy 284  $1,500,000 Not Selected  Program limited by available funding.
55 Hwy 5 Waconia Medium mill and overlay from Hwy 284 to Elm St  $100,000 Not Selected  Program limited by available funding.
45 Hwy 5 Waconia Medium mill and overlay from Elm St to Birch St $300,000 Not Selected  Program limited by available funding.
50 Hwy 51 St Paul, Falcon Heights, Roseville Medium mill and overlay from Pierce Butler to Hwy 36 $3,000,000 Not Selected  Program limited by available funding.
45 Hwy 51 St Paul Thin mill and overlay from St Clair Ave to Grand Ave  $1,000,000 Not Selected  Poor pavement conditions. 
65 Hwy 65 Minneapolis Reconstruction, ADA and BR repair on Hwy 65 from 2nd ST to 37th Ave NE in Mpls and 37st Ave to 53rd Ave in Columbia Heights   $1   Not Selected NA
60 Hwy 65 Minneapolis Medium mill and overlay from 3rd Ave S to 27th Ave  $4,800,000 Not Selected  Poor pavement conditions.
35 Hwy 65 NA Repair road from University Ave SE. to NE 27th Ave   $3,300,000   Not Selected Poor pavement conditions.
60 Hwy 95 Taylors Falls Medium mill and overlay from County Road 16/Taylors Falls to US8 $300,000 Not Selected  Program limited by available funding.
65 US52 Minneapolis Medium mill and overlay from Hwy 65 to University Ave $3,200,000 Not selected Poor pavement conditions plus ADA and bike needs. 
75 US61 Forest Lake Medium mill and overlay from Hwy 95 to Forest Lake Cl  $7,400,000 Not Selected Poor pavement conditions.
70 US61 White Bear Lake Medium mill and overlay from White Bear Ave to Hwy 96 $1,700,000 Not Selected  Program limited by available funding.
55 US61 White Bear Lake Medium mill and overlay from 8th St to Hwy 96 $300,000 Not Selected  Program limited by available funding.
10 US61 NA Resurface road from Jct Hwy 316 to W 36th St in Hastings $9,924,926 2029 Projected poor pavement conditions. 
67 US61, Hwy 5 NA Improve pavement conditions, stormwater drainage, corridor safety, walkability, traffic signals, landscaping, trails, bus stops, lighting, and sidewalk curb ramps on Hwy 61 (Arcade) from East 7th St to 0.2 miles south Roselawn Ave in Maplewood and on Hwy 5 from east end bridge 62703 to Minnehaha Ave in St Paul    $33,300,000   2025   NA

Previous years

View more detailed scores (Excel).

Last updated October 2023

Score Route  Community Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
50 Hwy 120 Mahtomedi, White Bear Lake Resurface pavement on Hwy 120 from north ramp of I-694/Hwy 120 to junction CR 12 (old Hwy 244) in White Bear Lake and Mahtomedi   $974,000   2027, Prior   Poor pavement conditions. Safety. 
45 Hwy 120 Oakdale, North St Paul, Maplewood, White Bear Lake Resurface road on Hwy 120 (Century Ave) from 35 feet north of 4th St in Maplewood and bituminous mill and overlay on Hwy 120 (Century Ave) from Hwy 36 to Hwy 244 in White Bear Lake    $8,770,000   2027   Poor pavement conditions. 
30 Hwy 121 Minneapolis Resurface pavement, signals, drainage and ADA on Hwy 121 (Lyndale Conn) from 0.5 miles west of I-35W pedestrian bridge over Lyndale Ave to W 58th St in Mpls    $1,642,000   2025   Poor pavement conditions. 
55 Hwy 13 Eagan, Mendota Heights Repair concrete from I-494 to Hwy 55    $5,055,915   2029 Poor pavement conditions. 2020 Remaining service life 0 to 5 years. 
50 Hwy 13 Mendota Heights Resurface road from Hwy 55 to Hwy 13   $10,165,320   2032 NA
35 Hwy 149 NA Resurface Hwy 149 from Hwy 55 to bridge over I-494.   $3,780,000   2033 Preventive maintenance.
60 Hwy 156 Saint Paul  Medium mill and overlay from Dakota/Ramsey County Line to US52 $500,000 Not Selected  Program limited by available funding.
55 Hwy 156 South Saint Paul  Medium mill and overlay from I-494 to Armour Ave $600,000 Not Selected  Program limited by available funding.
50 Hwy 156 South Saint Paul  Medium mill and overlay from Armour Ave to Wentworth Ave $1,200,000 Not Selected  Program limited by available funding.
35 Hwy 156 South Saint Paul  Medium mill and overlay from Wentworth Ave to Dakota/Ramsey County line $900,000 Not Selected  Program limited by available funding.
55 Hwy 21 Jordan Thin mill and overlay from Mill st to US169  $2,300,000 Not Selected Poor pavement conditions.
45 Hwy 244 Dellwood, Mahtomedi Resurface Hwy 244 (Dellwood/Mahtomedi Ave) from CR 12 (Stillwater Rd) in Mahtomedi to Hwy 96 (Dellwood Rd) in Dellwood    $6,299,000   2026   Poor pavement conditions. 
35 Hwy 244 Mahtomedi, White Bear Lake Reconstruction from Hwy 120 to Ash St $6,000,000 Not Selected  Turnback. Recent surface treatment concealing poor pavement conditions.
50 Hwy 282 Jordan Medium mill and overlay from US169 to Hwy 244 $500,000 Not Selected  Program limited by available funding.
45 Hwy 282 NA Resurface Hwy 282, from bridge over Sand Creek to Mill St $1,250,000 Not Selected  NA
75 Hwy 3 St Paul  Medium mill and overlay from Mendota Rd to Wyoming St $2,700,000 Not Selected  Program limited by available funding.
65 Hwy 3 Rosemount Medium mill and overlay from Dakota County Road 58 to 145th  $1,300,000 Not Selected  Program limited by available funding.
55 Hwy 3 St Paul  Rehab pavement, sidewalk replacement and ADA improvements on Hwy 3 (Robert St) from Annapolis St E to Mississippi River in St Paul   $13,775,000   2026   Poor pavement conditions. 
40 Hwy 3 St Paul Resurface and jurisdictional transfer Hwy 3 (Robert St) from Mississippi River Bridge to E 11th St in St Paul    $14,610,000   2025   Poor pavement conditions. Turnback to city. 
40 Hwy 3 St Paul Thin mill and overlay from Kellogg Blvd to I35E  $7,700,000 Not Selected Poor pavement conditions. Turnback to city.
70 Hwy 47 Minneapolis Resurface, drainage, sidewalks, ADA work and signal replacement on Hwy 47 (University Ave) from Hwy 65 (NE Central Ave) to just south of 27th northeast Ave in Mpls    $7,653,000   2027   Poor pavement conditions. 
60 Hwy 47 Minneapolis Medium mill and overlay from 27th Ave to 40th Ave $1,900,000 Not Selected  Program limited by available funding.
NA Hwy 47 Columbia Heights Reconstruct on Hwy 47 from 53rd Ave NE to 85th Ave NE in Columbia Heights and Fridley   $1   2028 NA
70 Hwy 5 St Paul Resurface road from Munster Ave to ST. Claire Ave    $7,393,539   2028 Poor pavement conditions. 
60 Hwy 5 St Paul Resurface road from St. Clair Ave to bridge over I94, resurface Hwy 5 bridge.   $13,854,031   2029 Poor pavement conditions. 
55 Hwy 5 Waconia Medium mill and overlay from Hwy 284 to Elm St $100,000 Not Selected  Program limited by available funding.
55 Hwy 5 Waconia Medium mill and overlay from Oak ave to Hwy 284  $1,500,000 Not Selected  Program limited by available funding.
55 Hwy 5 Waconia Reconstruct road, manage access and construct multi-use trail at Hwy 5 from CR 284 (W 13th St) to CR 59/Main St in Waconia  $12,177,972 2026 NA
45 Hwy 5 Waconia Medium mill and overlay from Elm St to Birch St $300,000 Not Selected  Program limited by available funding.
10 Hwy 5 Maplewood Replace traffic signals, ADA and various safety upgrades at Forest, Earl, Ruth and Johnson Parkway on Hwy 5, 0.3 miles east of Mendota St in St Paul to north jct Hwy 120 (Century Ave N) in Maplewood   $10,784,000   2024, Prior   NA
60 Hwy 51 St Paul  Medium mill and overlay from Dayton Ave to Pierce Butler $1,600,000 Not Selected  Program limited by available funding.
50 Hwy 51 St Paul, Falcon Heights, Roseville Medium mill and overlay from Pierce Butler to Hwy 36 $3,000,000 Not Selected  Program limited by available funding.
65 Hwy 65 Minneapolis Medium mill and overlay from 27th Ave to 37th Ave   $1,400,000 Not Selected  Program limited by available funding.
65 Hwy 65 Minneapolis Reconstruction, ADA and BR repair on Hwy 65 from 2nd ST to 37th Ave NE in Mpls and 37st Ave to 53rd Ave in Columbia Heights   $1   2028 NA
35 Hwy 65 Columbia Heights Repair road from University Ave SE. to NE 27th Ave   $3,300,000   2030 Poor pavement conditions.
60 Hwy 95 Taylors Falls Medium mill and overlay from County Road 16/Taylors Falls to US8 $300,000 Not Selected  Program limited by available funding.
65 US52 Minneapolis Medium mill and overlay from Hwy 65 to University Ave $3,200,000 Not selected Poor pavement conditions plus ADA and bike needs. 
75 US61 Forest Lake Medium mill and overlay from Hwy 95 to Forest Lake Cl  $7,400,000 Not Selected Poor pavement conditions.
70 US61 White Bear Lake Medium mill and overlay from White Bear Ave to Hwy 96 $1,700,000 Not Selected  Program limited by available funding.
55 US61 White Bear Lake Medium mill and overlay from 8th St to Hwy 96 $300,000 Not Selected  Program limited by available funding.
45 US61 NA Resurface Hwy 61 from Hwy 97 to N of Hwy 8   $5,121,000   2029 Poor pavement conditions.
10 US61 Hastings Resurface road from Jct Hwy 316 to W 36th St in Hastings   $6,882,750   2029 Projected poor pavement conditions. 
67 US61, Hwy 5 Maplewood Improve pavement conditions, stormwater drainage, corridor safety, walkability, traffic signals, landscaping, trails, bus stops, lighting, and sidewalk curb ramps on Hwy 61 (Arcade) from East 7th St to 0.2 miles south Roselawn Ave in Maplewood and on Hwy 5 from east end bridge 62703 to Minnehaha Ave in St Paul and Improve pavement conditions, stormwater drainage, corridor safety, walkability, traffic signals, landscaping, trails, bus stops, lighting, and sidewalk curb ramps on Hwy 61 (Arcade) from East 7th St to 0.2 miles south Roselawn Ave in Maplewood and on Hwy 5 from east end bridge 62703 to Minnehaha Ave in St Paul and Improve pavement conditions, stormwater drainage, corridor safety, walkability, traffic signals, landscaping, trails, bus stops, lighting, and sidewalk curb ramps on Hwy 61 (Arcade) from East 7th St to 0.2 miles south Roselawn Ave in Maplewood and on Hwy 5 from east end bridge 62703 to Minnehaha Ave in St Paul    $30,800,000   2025   Poor pavement conditions.

View more detailed scores (Excel).

Last updated October 2022

Score Community Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
50 Hwy 120 Mahtomedi, White Bear Lake Mill and overlay, intersection improvements at Hwy 120 and Long Lake Road, construct roundabouts at South Century College Drive and Woodland Drive, construct mixed use trail $0 2025 Poor pavement conditions. Safety. 
45 Hwy 120 Oakdale, North St Paul, Maplewood, White Bear Lake Reconstruct road from 4th St in Maplewood to Hwy 244 in White Bear Lake $15,559,000 2026 Poor pavement conditions. 
30 Hwy 121 Minneapolis Resurface pavement, signals, drainage and ADA on Hwy 121 (Lyndale Conn) from 0.5 miles west of I-35W pedestrian bridge over Lyndale Ave to W 58th St in Mpls $1,540,000 2025 Poor pavement conditions. 
55 Hwy 13 Eagan, Mendota Heights Repair concrete from I-494 to Hwy 55 $5,000,000 2031 Poor pavement conditions. 2020 Remaining service life 0 to 5 years. 
50 Hwy 13 Mendota Heights Resurface road from Hwy 55 to Hwy 13 $10,200,000 2032 NA
35 Hwy 149 Eagan Repair road from I-494 to Hwy 55 $1,500,000 2032 Preventive maintenance.
60 Hwy 156 Saint Paul  Medium mill and overlay from Dakota/Ramsey County Line to US52 $500,000 Not Selected  Program limited by available funding.
55 Hwy 156 South Saint Paul  Medium mill and overlay from I-494 to Armour Ave $600,000 Not Selected  Program limited by available funding.
50 Hwy 156 South Saint Paul  Medium mill and overlay from Armour Ave to Wentworth Ave $1,200,000 Not Selected  Program limited by available funding.
35 Hwy 156 South Saint Paul  Medium mill and overlay from Wentworth Ave to Dakota/Ramsey County line $900,000 Not Selected  Program limited by available funding.
45 Hwy 244 Dellwood, Mahtomedi Rebuild road from County Rd. 12 to Hwy 96 $4,000,000 2025 Poor pavement conditions. 
35 Hwy 244 Mahtomedi, White Bear Lake Reconstruction from Hwy 120 to Ash St $6,000,000 Not Selected  Turnback. Recent surface treatment concealing poor pavement conditions.
50 Hwy 282 Jordan Medium mill and overlay from US169 to Hwy 244 $500,000 Not Selected  Program limited by available funding.
45 Hwy 282 Jordan Resurface Hwy 282, from bridge over Sand Creek to Mill St $1,250,000 2031 NA
70 Hwy 284 Waconia, Cologne Thick mill and overlay from US212 to Hwy 5 $8,400,000 Not Selected  Many issues with this pavement including geometric and ADA needs in Cologne. RQI data not reflective of the poor pavement conditions.
74 Hwy 284 Waconia Reconstruct road from US 212 to 122nd St $11,000,000 2031 Many issues with this pavement including geometric and ADA needs in Cologne. RQI data not reflective of the poor pavement conditions.
55 Hwy 3 St Paul  Rehab pavement, sidewalk replacement and ADA improvements on Hwy 3 (Robert St) from Annapolis St E to Mississippi River in St Paul $13,529,000 2026 Poor pavement conditions. 
40 Hwy 3 St Paul Resurface and jurisdictional transfer Hwy 3 (Robert St) from Mississippi River Bridge to E 11th St in St Paul $14,610,000 2025 Poor pavement conditions. Turnback to city. 
75 Hwy 3 St Paul  Medium mill and overlay from Mendota Rd to Wyoming St $2,700,000 Not Selected  Program limited by available funding.
65 Hwy 3 Rosemount Medium mill and overlay from Dakota County Road 58 to 145th  $1,300,000 Not Selected  Program limited by available funding.
76 Hwy 36 ROSEVILLE Reconstruct ramps, resurface, drainage, improve ADA and signals on Hwy 36 at Fairview interchange in Roseville $3,732,000 2023 NA
20 Hwy 41 Chaska Resurface road from Hundertmark to Pioneer Trail $1,250,000 2031 RQI does not match on the ground conditions
70 Hwy 47 Minneapolis Resurface, drainage, sidewalks and ADA work on Hwy 47 from Hwy 65 to just south of 27th northeast Ave in Mpls $3,400,000 2026 Poor pavement conditions. 
60 Hwy 47 Minneapolis Medium mill and overlay from 27th Ave to 40th Ave $1,900,000 Not Selected  Program limited by available funding.
10 Hwy 5 St Paul Resurface road, repair/replace drainage; improve intersection pedestrian accessibility and safety improvements from 0.3 miles east of Mendota St in St Paul to the north jct Hwy 120 (Century Ave) in Maplewood and on Hwy 36 construct stormwater treatment ponds at Edgerton interchange and White Bear Ave in Maplewood  $9,442,000 2023 NA
55 Hwy 5 Waconia Medium mill and overlay from Hwy 284 to Elm St $100,000 Not Selected  Program limited by available funding.
55 Hwy 5 Waconia Medium mill and overlay from Oak ave to Hwy 284  $1,500,000 Not Selected  Program limited by available funding.
45 Hwy 5 Waconia Medium mill and overlay from Elm St to Birch St $300,000 Not Selected  Program limited by available funding.
70 Hwy 5 St Paul Resurface road from Munster Ave to ST. Claire Ave $14,800,000 2027 Poor pavement conditions. 
60 Hwy 5 St Paul Resurface road from St. Clair Ave to bridge over I94 $14,439,000 2027 Poor pavement conditions. 
45 Hwy 51 St Paul Resurface road and ADA improvements on Hwy 51 (Snelling Ave) from Grand Ave to St Clair Ave in St Paul $1,760,000 2024 Poor pavement conditions. 
60 Hwy 51 St Paul  Medium mill and overlay from Dayton Ave to Pierce Butler $1,600,000 Not Selected  Program limited by available funding.
50 Hwy 51 St Paul, Falcon Heights, Roseville Medium mill and overlay from Pierce Butler to Hwy 36 $3,000,000 Not Selected  Program limited by available funding.
65 Hwy 65 Minneapolis Medium mill and overlay from 27th Ave to 37th Ave  $1,400,000 Not Selected  Program limited by available funding.
35 Hwy 65 Minneapolis Repair road from Washington Ave. to NE 27th Ave $3,300,000 2030 Poor pavement conditions.
60 Hwy 95 Taylors Falls Medium mill and overlay from County Road 16/Taylors Falls to US8 $300,000 Not Selected  Program limited by available funding.
65 US52 Minneapolis Medium mill and overlay from Hwy 65 to University Ave $3,200,000 Not Selected  Poor pavement conditions plus ADA and bike needs. 
67 US61 St Paul, Maplewood Resurface, drainage sidewalks and ADA improvements on Hwy 61 (Arcade) from East 7th to 0.2 miles south Roselawn Ave in Maplewood and on Hwy 5 from east end bridge 62703 to Minnehaha Avenue in St Paul $11,935,000 2024 Poor pavement conditions.
70 US61 White Bear Lake Medium mill and overlay from White Bear Ave to Hwy 96 $1,700,000 Not Selected  Program limited by available funding.
55 US61 White Bear Lake Medium mill and overlay from 8th St to Hwy 96 $300,000 Not Selected  Program limited by available funding.
45 US61 Forest Lake Resurface road from Hwy 97 to Forest Lake city line $5,000,000 2030 Poor pavement conditions.
10 US61 Hastings Resurface road from Jct Hwy 316 to W 36th St in Hastings $7,000,000 2028 Projected poor pavement conditions. 

View more detailed scores (Excel).

Last updated October 2021

Score Community Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
75 US61 Forest Lake Medium mill and overlay from Hwy 95 to Forest Lake Cl  $7,400,000 2030 Poor pavement conditions.
75 Hwy 3 St Paul  Medium mill and overlay from Mendota Rd to Wyoming St  $2,700,000 Not Selected  Program limited by available funding.
70 US61 White Bear Lake Medium mill and overlay from White Bear Ave to Hwy 96  $1,700,000 Not Selected  Program limited by available funding.
70 Hwy 5 St Paul Medium mill and overlay from Munster Ave to St Clair  $19,000,000 2027 Poor pavement conditions. SP 6201-091.
70 Hwy 284 Waconia, Cologne Thick mill and overlay from US212 to Hwy 5  $8,400,000 2031 Many issues with this pavement including geometric and ADA needs in Cologne. RQI data not reflective of the poor pavement conditions.
70 Hwy 47 Minneapolis Medium mill and overlay from Central Ave to 27th Ave  $4,300,000 2026 Poor pavement conditions. SP 2726-078.
65 Hwy 3 Rosemount Medium mill and overlay from Dakota County Road 58 to 145th   $1,300,000 Not Selected  Program limited by available funding.
65 Hwy 65 Minneapolis Medium mill and overlay from 27th Ave to 37th Ave   $1,400,000 Not Selected  Program limited by available funding.
65 UN52 Minneapolis Medium mill and overlay from Hwy 65 to University Ave  $3,200,000 2027 Poor pavement conditions plus ADA and bike needs. SP 2726-075.
60 Hwy 5 St Paul Medium mill and overlay from St Clair to Kellogg Blvd  $18,600,000 2027 Poor pavement conditions. SP 6201-095.
60 Hwy 65 Columbia Heights Medium mill and overlay from 37th Ave to 53rd Ave  $7,100,000 2028 Projected poor pavement conditions.
60 Hwy 65 Minneapolis Medium mill and overlay from 3rd Ave S to 27th Ave  $4,800,000 2030 Poor pavement conditions.
60 Hwy 95 Taylors Falls Medium mill and overlay from County Road 16/Taylors Falls to US8  $300,000 Not Selected  Program limited by available funding.
60 Hwy 156 Saint Paul  Medium mill and overlay from Dakota/Ramsey County Line to US52  $500,000 Not Selected  Program limited by available funding.
60 Hwy 47 Columbia Heights, Fridley, Spring Lake Park Thin mill and overlay from 40th Ave to US10  $15,300,000 2030 Poor pavement conditions.
60 Hwy 47 Minneapolis Medium mill and overlay from 27th Ave to 40th Ave  $1,900,000 Not Selected  Program limited by available funding.
60 Hwy 51 St Paul  Medium mill and overlay from Dayton Ave to Pierce Butler  $1,600,000 Not Selected  Program limited by available funding.
55 Hwy 55 Minneapolis Medium mill and overlay from 13th Ave S to Minnehaha Ave bridge  $15,600,000 2022 Poor pavement conditions. SP 2724-124 and -126.
55 US61 White Bear Lake Medium mill and overlay from 8th St to Hwy 96  $300,000 Not Selected  Program limited by available funding.
55 Hwy 3 St Paul  Medium mill and overlay from Wyoming St to Kellogg Blvd  $5,300,000 2026 Poor pavement conditions. 6217-050
55 Hwy 5 Waconia Medium mill and overlay from Oak ave to Hwy 284   $1,500,000 Not Selected  Program limited by available funding.
55 Hwy 5 Waconia Medium mill and overlay from Hwy 284 to Elm St  $100,000 Not Selected  Program limited by available funding.
55 Hwy 156 South Saint Paul  Medium mill and overlay from I-494 to Armour Ave  $600,000 Not Selected  Program limited by available funding.
55 Hwy 13 Eagan, Mendota Heights Reconstruction from I-494 to Hwy 55  $7,600,000 2031 Poor pavement conditions. 2020 Remaining service life 0 to 5 years. 1901-193
55 Hwy 21 Jordan Thin mill and overlay from Mill st to US169  $2,300,000 2031 Poor pavement conditions.
50 Hwy 156 South Saint Paul  Medium mill and overlay from Armour Ave to Wentworth Ave  $1,200,000 Not Selected  Program limited by available funding.
50 Hwy 282 Jordan Medium mill and overlay from US169 to Hwy 244  $500,000 Not Selected  Program limited by available funding.
50 Hwy 51 St Paul, Falcon Heights, Roseville Medium mill and overlay from Pierce Butler to Hwy 36  $3,000,000 Not Selected  Program limited by available funding.
50 Hwy 120 Mahtomedi, White Bear Lake Medium mill and overlay from County Road D to Hwy 244  $900,000 2025 Poor pavement conditions. Safety. 6227-081
50 Hwy 25 Belle Plaine Thin mill and overlay from US169 to Scott County Line  $3,600,000 2031 Poor pavement conditions. 7003-115
45 Hwy 5 Waconia Medium mill and overlay from Elm St to Birch St  $300,000 Not Selected  Program limited by available funding.
45 Hwy 51 St Paul Thin mill and overlay from St Clair Ave to Grand Ave  $1,000,000 2025 Poor pavement conditions. SP 6215-114.
45 Hwy 51 St Paul Thin mill and overlay from Hwy 5/7th ST to Dayton Ave  $8,900,000 2030 Poor pavement conditions.
45 Hwy 244 Dellwood, Mahtomedi Thin mill and overlay from Ash St to Hwy 96  $900,000 2025 Poor pavement conditions. SP 8219-026.
45 Hwy 120 Oakdale, Maplewood Medium mill and overlay from Ridge Dr to 4th St  $1,400,000 2026 Projected poor pavement conditions.
45 Hwy 120 Oakdale, North St Paul, Maplewood, White Bear Lake Thick mill and overlay from 4th St to County Road D  $14,800,000 2026 Poor pavement conditions. 6227-086
40 US61 St Paul, Maplewood Thin mill and overlay from Hwy 5 to Roselawn  $4,800,000 2024 Poor pavement conditions. SP 6221-107.
40 Hwy 3 St Paul Thin mill and overlay from Kellogg Blvd to I35E  $7,700,000 2025 Poor pavement conditions. Turnback to city. 6217-051
40 Hwy 5 St Paul Thin mill and overlay from Kellogg Blvd to US61  $4,200,000 2024 Poor pavement conditions. SP 6221-107.
40 Hwy 5 St Paul Thin mill and overlay from Arcade St/US61 to Century Ave/Hwy 120  $6,100,000 2023 Poor pavement conditions. 6229-037
35 Hwy 156 South Saint Paul  Medium mill and overlay from Wentworth Ave to Dakota/Ramsey County line  $900,000 Not Selected  Program limited by available funding.
35 Hwy 244 Mahtomedi, White Bear Lake Reconstruction from Hwy 120 to Ash St  $6,000,000 2031 Turnback. Recent surface treatment concealing poor pavement conditions.
35 Hwy 149 Eagan Thin mill and overlay from Hwy 55 to I-494  $1,400,000 2028 Preventive maintenance.
30 Hwy 121 Minneapolis Medium mill and overlay from Pedestrian Bridge to 58th ST  $1,200,000 2025 Poor pavement conditions. 6282-052

View more detailed scores (Excel).

Last updated December 2020

Score Community Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
80 Saint Paul  Hwy 5 Medium mill and overlay from McKnight to Hwy 5 $600,000 Not Selected Not a district priority. Will continue to monitor pavement performance
78 Lakeville Hwy 3 Medium mill and overlay from Dakota County Road 58 to Railroad Bridge $400,000 Not Selected Not a district priority. Will continue to monitor pavement performance
78 Rosemount Hwy 3 Medium mill and overlay from Railroad Bridge to 145th St $400,000 Not Selected Not a district priority. Will continue to monitor pavement performance
77 Saint Paul  Hwy 5 Medium mill and overlay form McKnight to Century Ave/Hwy 120 $300,000 Not Selected Not a district priority. Will continue to monitor pavement performance
77 Oakdale Hwy 120 Medium mill and overlay from 4th St to Hwy 244 $2,200,000 2024 Older pavement requires reconstruction. Local interest in improvements. Microsurfaced in CY 2020 to hold together.
73 White Bear Lake US 61 Medium mill and overlay from 8th St to Hwy 96 $300,000 Not Selected NA
71 Saint Paul  US 61 Medium mill and overlay from Mounds Blvd to Hwy 5 $700,000 Not Selected NA
71 South Saint Paul  US 52 Medium mill and overlay from Moreland Ave to Wyoming St $900,000 Not Selected NA
70 White Bear Lake US 61 Medium mill and overlay from White Bear Ave to Hwy 96 $1,700,000 Not Selected NA
70 Minneapolis Hwy 65 Medium mill and overlay from 27th Ave to 37th Ave $1,700,000 2028 Poor riding urban section. Requires resurfacing. Combined with additional sections with a high score of 70
70 Minneapolis Hwy 65 Medium mill and overlay from 37th Ave to 53rd Ave NE $1,900,000 2028 Poor riding urban section. Requires resurfacing. Combined with additional sections with a high score of 70
69 Waconia Hwy 5 Medium mill and overlay from Oak Ave to Hwy 284 $800,000 Not Selected NA
69 Eagan Hwy 149 Medium mill and overlay from I-494 to Mendota Heights Rd $400,000 Not Selected NA
68 Saint Paul  Hwy 5 Medium mill and overlay from Hwy 61/Arcade St to McKnight $800,000 Not Selected NA
68 South Saint Paul  US 52 Medium mill and overlay from Mendota Rd to Marie Ave $600,000 Not Selected NA
68 West Saint Paul US 52 Medium mill and overlay from Marie Ave to Moreland Ave $1,300,000 Not Selected NA
67 Waconia Hwy 284 Medium mill and overlay from Elm Creek Rd to Hwy 5 $300,000 Not Selected NA
65 Saint Paul  Hwy 5 Thin mill and overlay from Hennepin/Ramsey County Line to Munster Ave $600,000 Not Selected NA
65 Saint Paul  Hwy 51 Medium mill and overlay from Dayton Ave to Pierce Butler $1,600,000 Not Selected NA
65 Saint Paul  Hwy 149 Medium mill and overlay from High Bridge to Hwy 5/W7th St $100,000 Not Selected NA
64 Waconia Hwy 5 Medium mill and overlay from Hwy 284 to Elm St $100,000 Not Selected NA
64 Waconia Hwy 5 Medium mill and overlay from Elm st to Birch St $200,000 Not Selected NA
64 Saint Paul  US 61 Medium mill and overlay from Hwy 5 to Wheelock Pkwy $800,000 Not Selected NA
63 Mendota Heights Hwy 149 Medium mill and overlay from Mendota Heights Rd to Maple St $400,000 Not Selected NA
63 South Saint Paul  Hwy 156 Medium mill and overlay from Armour Ave to Wentworth Ave $1,200,000 Not Selected NA
62 Anoka Hwy 47 Medium mill and overlay from Hwy 10 to .4 miles north of Hwy 10 $300,000 Not Selected NA
62 Anoka Hwy 47 Medium mill and overlay from .4 miles north of Hwy 10 to Industry Ave $400,000 Not Selected NA
62 West Saint Paul Hwy 149 Medium mill and overlay from Maple St to Smith Ave $600,000 Not Selected NA
62 Waconia Hwy 284 Medium mill and overlay from Somerset Dr to Hwy 5 $100,000 Not Selected NA
62 Saint Paul  US 52 Medium mill and overlay from Plato Blvd to Kellogg Blvd $700,000 Not Selected NA
61 Minneapolis US 52 Medium mill and overlay from I35W to Hwy 65 $400,000 2029 Notoriously poor riding urban section. Requires resurfacing. Other MnDOT and local needs included. Microsurfacing completed in CY 2020 to hold together.
60 Minneapolis Hwy 65 Medium mill and overlay from 3rd Ave to NE 27th Ave   $2,700,000 2028 Poor riding urban section. Requires resurfacing. Combined with additional sections with a high score of 70
60 Saint Paul  US 52 Medium mill and overlay from Concord Blvd to Plato Blvd $500,000 Not Selected NA
59 WSP/Mendota Heights Hwy 149 Medium mill and overlay from Hwy 13 to High Bridge  $200,000 Not Selected NA
59 South Saint Paul  Hwy 156 Medium mill and overlay from I-494 to Armour Ave $600,000 Not Selected NA
59 Minneapolis US 52 Medium mill and overlay from Hwy 65 to University Ave $500,000 2029 Notoriously poor riding urban section. Requires resurfacing. Other MnDOT and local needs included. Microsurfacing completed in CY 2020 to hold together.
59 Saint Paul  US 52 Medium mill and overlay from Elizabeth St to Concord Blvd $200,000 Not Selected NA
59 Saint Paul  US 52 Medium mill and overlay from Kellogg Blvd to I-35E $600,000 Not Selected NA
58 Saint Paul  Hwy 5 Thin mill and overlay from Munster St to St. Clair Ave $2,700,000 2025 Notoriously poor riding urban section. Requires resurfacing. Other MnDOT and local needs included.
58 Saint Paul  Hwy 5 Thin mill and overlay from St. Clair to Mounds Blvd $3,700,000 2026 Notoriously poor riding urban section. Requires resurfacing. Other MnDOT and local needs included.
58 West Saint Paul Hwy 149 Medium mill and overlay from Smith Ave to Hwy 13 $100,000 Not Selected NA
56 Jordan Hwy 282 Medium mill and overlay from Hwy 169 to Hwy 21 $300,000 Not Selected NA
55 Saint Paul  Hwy 51 Thin mill and overlay from Hwy 5/W7th St to Dayton Ave $1,600,000 2030 Notoriously poor riding urban section. Requires resurfacing. Other MnDOT needs included.
55 Saint Paul  Hwy 51 Medium mill and overlay from Pierce Butler to Como $600,000 Not Selected NA
55 Saint Paul  US 52 Medium mill and overlay from Wyoming St to Elizabeth St $300,000 Not Selected NA
53 Mahtomedi Hwy 244 Thin mill and overlay from Wildwood Rd to Hwy 96 $500,000 2025 Notoriously poor riding urban section. Requires resurfacing. Other MnDOT and local needs included.
53 South Saint Paul  Hwy 156 Medium mill and overlay from Wentworth ave to Dakota Ramsey County line $500,000 Not Selected NA
51 Lakeville  I35 Medium mill and overlay from Dakota County Road 70 to Dakota County Road 50 $1,900,000 Not Selected NA
50 Saint Paul  Hwy 51 Thin mill and overlay from St. Clair to Grand Ave $300,000 2025 Poor ride quality requires resurfacing. Many other MnDOT needs included with project (ADA and Water Resources).
50 Taylors Falls Hwy 95 Medium mill and overlay from Chisago County Road 16 to Reference Point 74 $200,000 Not Selected NA
49 Jordan Hwy 21 Thin mill and overlay from Mill St to Hwy 169 $200,000 2027 Poor riding urban section. Requires resurfacing. Other MnDOT and local needs included.
47 Waconia Hwy 284 Medium mill and overlay from Hwy 5 to Somerset Dr $100,000 Not Selected NA
39 Belle Plaine Hwy 25 Thin mill and overlay from Hwy 169 to Scott County line $400,000 2027 Poor riding urban section. Requires resurfacing.
Lakeville  I35 Medium mill and overlay from Scott/Dakota County line to Scott County Road 70 $600,000 Not Selected NA

View more detailed scores (Excel).

Last updated December 2019

Score Community Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
90 Saint Paul US952A Medium mill and overlay from Wyoming St to I-35E $18,000,000 2022 NA
87 Oakdale / Maplewood Hwy 120 Reclaim and overlay from 4th St in Oakdale to Highway 244 $4,400,000 2024 NA
75 Saint Paul Hwy 51 Medium mill and overlay from Dayton Ave to Como Ave  $2,100,000 Not Selected Waiting to coordinate with transit 
73 Minneapolis US952A Medium mill and overlay from I-35W to University Ave $600,000 2027 NA
70 Saint Paul Hwy 51 Medium mill and overlay from St. Clair to Grand Ave $300,000 2024 NA
70 Columbia Heights Hwy 65 Medium mill and overlay from 37th Ave to 53rd Ave NE $1,900,000 2027 NA
67 Saint Paul US61 Medium mill and overlay from Highway 5 to Roselawn Ave $2,400,000 2023 NA
67 Saint Paul Hwy 5 Thin mill and overlay from Munster Ave to Highway 61 $3,500,000 2024 NA
66 Anoka Hwy 47 Thin mill and overlay from Highway 10 to Industry Ave NW $800,000 2021 NA
66 Minneapolis Hwy 65 Medium mill and overlay from 3rd Ave S to NE 27th Ave $2,700,000 2027 NA
65 Saint Paul Hwy 5 Medium mill and overlay from Highway 61 to Highway 129 $3,400,000 2022 NA
65 Saint Paul Hwy 51 Thin mill and overlay from Highway 5/West 7th St to Dayton Ave $1,900,000 2029 NA
65 Waconia Hwy 5 Thin mill and overlay from Oak Ave to Birch St $1,000,000 Not Selected NA
65 West Saint Paul US952A Medium mill and overlay from Old Highway 110 to Wyoming St $3,000,000 Not Selected NA
60 Mahtomedi Hwy 244 Nova Chip from Washington County Road 12 to Highway 96 $1,100,000 2025 Selected prior to policy (in 2019-2028 CHIP)
60 Saint Paul Hwy 5 Medium mill and overlay from Ramsey/Hennepin County Line to Highway 52 $700,000 Not Selected NA
58 Saint Paul US61 Thin mill and overlay from Mounds Blvd to Highway 5 $600,000 2021 Selected prior to policy (in 2019-2022 STIP)
58 Saint Paul Hwy 156 Thin mill and overlay from Dakota/Ramsey County Line $200,000 2021 Selected prior to policy (in 2019-2022 STIP)
56 South Saint Paul Hwy 156 Major Concrete Rehabilitation from I-494 to Dakota/Ramsey County Line  $4,300,000 2021 Selected prior to policy (in 2019-2022 STIP)
50 Rosemount Hwy 3 Thin mill and overlay from Dakota County Road 58 to 145th St  $800,000 Not Selected NA
47 Taylors Falls Hwy 95 Thin mill and overlay from Chisago County Road 16 to Highway 8 $200,000 Not Selected NA
44 Jordan Hwy 282 Thin mill and overlay from Jordan to Highway 21 $400,000 Not Selected NA
39 Jordan Hwy 21 Thin mill and overlay from Mill St to Highway 169 $300,000 2027 Coordinated with larger pavement project
33 Belle Plaine Hwy 25 Thin mill and overlay from Highway 169 to Scott County Line $700,000 2027 Coordinated with larger pavement project
26 Waconia Hwy 284 Thin mill and overlay from Elm Creek Rd to Highway 5 $400,000 Not Selected NA
25 White Bear Lake US61 Medium mill and overlay from White Bear Ave to Highway 96  $700,000 Not Selected Preventive maintenance scheduled in 2020 to extend surface life
22 Minneapolis Hwy 65 Thin mill and overlay from 27th Ave to 37th Ave $900,000 Not Selected NA
12 New Prague Hwy 21 Minor concrete repair from Scott/Le Sueur County line to 7th St $100,000 Not Selected NA